3. Does the delay of activity B delay all other activities in the plan? 4. What is the ES, EF, LS, LF of activity G?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
A project P consists of 9 activities as shown below:
Activity
Predecessor(s)
Duration (days)
Cost ($)
A
1
100
B
A
2000
B
1
300
B
200
E
200
C, E
4
400
G
2
1600
G
1000
C, E
4
1600
2.
Transcribed Image Text:A project P consists of 9 activities as shown below: Activity Predecessor(s) Duration (days) Cost ($) A 1 100 B A 2000 B 1 300 B 200 E 200 C, E 4 400 G 2 1600 G 1000 C, E 4 1600 2.
3. Does the delay of activity B delay all other activities in the plan?
4. What is the ES, EF, LS, LF of activity G?
Now we observe the project at week 13 and we want to conduct an EVA to determine the project efficiency. The progress status of the project is given by the table below.
Activity
Status
Actual Start
Actual duration (days)
Actual cost (S)
(days)
A
100%
300
B
100%
+1 day
+2 days
1800
100%
+3 days
+1 day
500
ID
100%
+3 days
200
100%
+3 days
200
IF
100%
+3 days
150
IG
0%
+3 days
0%
+3 days
10%
+4 days
200
1. What is the cumulative planned value of the project?
2. What is the cumulative actual cost of the project?
3. What is the cumulative earned value of the project?
4. What is the CPI of the project?
5. What is the SPI of the project?
6. How is the project performing?
Transcribed Image Text:3. Does the delay of activity B delay all other activities in the plan? 4. What is the ES, EF, LS, LF of activity G? Now we observe the project at week 13 and we want to conduct an EVA to determine the project efficiency. The progress status of the project is given by the table below. Activity Status Actual Start Actual duration (days) Actual cost (S) (days) A 100% 300 B 100% +1 day +2 days 1800 100% +3 days +1 day 500 ID 100% +3 days 200 100% +3 days 200 IF 100% +3 days 150 IG 0% +3 days 0% +3 days 10% +4 days 200 1. What is the cumulative planned value of the project? 2. What is the cumulative actual cost of the project? 3. What is the cumulative earned value of the project? 4. What is the CPI of the project? 5. What is the SPI of the project? 6. How is the project performing?
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.