9.A Sample of EARNED VALUE ANALYSIS The following project is at the end of its 5 week.Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Duration Budget ($) 300 Actual Cost % Activity Predecessor (s) ($) 400 (week) Complete A 100 В 200 180 40 250 300 A 6 50 А, В 4 600 400 100 E А,В 2 400 200 100 F C 4 150 180 60 G D,F 100 200 75 H E,G 3 500 350 25
9.A Sample of EARNED VALUE ANALYSIS The following project is at the end of its 5 week.Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Duration Budget ($) 300 Actual Cost % Activity Predecessor (s) ($) 400 (week) Complete A 100 В 200 180 40 250 300 A 6 50 А, В 4 600 400 100 E А,В 2 400 200 100 F C 4 150 180 60 G D,F 100 200 75 H E,G 3 500 350 25
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Project Management
![9.A Sample of EARNED VALUE ANALYSIS
The following project is at the end of its 5 week.Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC
and EAC for the project.
Budget
($)
Duration
Actual Cost
Activity
Predecessor (s)
(week)
($)
400
Complete
A
4
300
100
В
200
180
40
A
6
250
300
50
D
А,В
4
600
400
100
400
200
E
А, В
2
100
F
4
150
180
60
G
D,F
100
200
75
500
350
Е,G
3
25](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F20034d01-f9df-412d-882a-b08e190052bb%2F2ae40578-d8bb-4657-87c5-769c1f3b6c8a%2Fxmtb1my_processed.png&w=3840&q=75)
Transcribed Image Text:9.A Sample of EARNED VALUE ANALYSIS
The following project is at the end of its 5 week.Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC
and EAC for the project.
Budget
($)
Duration
Actual Cost
Activity
Predecessor (s)
(week)
($)
400
Complete
A
4
300
100
В
200
180
40
A
6
250
300
50
D
А,В
4
600
400
100
400
200
E
А, В
2
100
F
4
150
180
60
G
D,F
100
200
75
500
350
Е,G
3
25
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.