2) Consider the Part Type Selection problem we covered in class. This problem helps us determine which parts we will produce in a new FMS. The problem assumes that we have candidate parts i = 1, 2, ...N, that the total savings achieved by producing part i in the FMS is s, and that we know that there is a 'key bottleneck' in the FMS, which has P available time units. Each part i requires a total processing time p, in the 'key bottleneck'. we saw that a way to solve this problem is the following Greedy Heuristic: Step 1: Order parts [1] to [N] such that P [1] P[2] P[N] Define remaining available time T = P Step 2: For i = 1...N select part [i] and add the part to the FMS if p, < T and s, > 0. Each time you add a new part i, update the remaining available time as T = T - P₁ Now suppose you had 3 'key bottlenecks' (that is 3 resources that each might be the bottleneck depending on the parts you choose to produce in the FMS). These resources have P, Q and R time units available respectively. And each part i requires a total processing time p, q, and r, in each of the three, respectively. Modify the algorithm above to solve the 3-bottleneck version of the problem. TIP: In Step 1 you need to consider the processing times at all 3 stations to do the ordering. In step 2, you must keep track of the remaining capacity at each station separately. 3) An FMS consists of five stations. Station 1 is a load/unload station with one server. Station 2 performs milling operations with one server. Station 3 performs drilling operations with two servers (two identical CNC drill presses). Station 4 is for performing grinding operations with three identical servers (three identical CNC grinding machines). Station 5 is an inspection station with one server that performs inspections on a sample of the parts. The stations are connected by a part handling system that has two work carriers and a mean transport time = 4.0 min. The FMS produces six parts A, B, C, D, E, and F. The part mix fractions and process routings for the six parts are presented in the table below. Note that the operation frequency at the inspection station (f_5jk) is less than 1.0 to account for the fact that only a fraction of the parts are inspected. For this system determine: (a) Maximum production rate of the FMS; (b) Corresponding production rate of each part; (c) Utilization of each station in the system; (d) Overall FMS utilization. Part Part mix Station Frequency J Pj Op k Description Process time tijk (min) fijk A 0.1 1 Load 1 3 1.0 2 Drill 3 12 1.0 3 Grind 4 28 1.0 4 Inspect 5 8 0.4 5 Unload 1 2 1.0 B 0.2 1 Load 1 3 1.0 2 Mill 2 12 1.0 3 Drill 3 12 1.0 4 Grind 4 33 1.0 5 Drill 3 11 1.0 6 Inspect 5 9 0.3 7 Unload 1 2 1.0 0.15 1 Load 1 3 1.0 2 Mill 2 14 1.0 3 Drill 3 11 1.0 4 Inspect 5 12 0.2 5 Unload 1 2 1.0 0.1 1 Load 1 3 1.0 2 Drill 3 17 1.0 3 Inspect 5 10 0.2 4 Unload 1 2 1.0 E 0.1 1 Load 1 3 1.0 2 Grind 4 32 1.0 3 Drill 3 13 1.0 4 Grind 4 37 1.0 5 Inspect 5 12 0.1 6 Unload 1 2 1.0 0.35 1 Load 1 3 1.0 2 Mill 2 26 1.0 3 Drill 3 13 1.0 4 Grind 4 39 1.0 5 Inspect 5 8 0.3 6 Unload 1 2 1.0

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
2) Consider the Part Type Selection problem we covered in class. This problem helps us
determine which parts we will produce in a new FMS. The problem assumes that we have
candidate parts i = 1, 2, ...N, that the total savings achieved by producing part i in the FMS
is s, and that we know that there is a 'key bottleneck' in the FMS, which has P available time
units. Each part i requires a total processing time p, in the 'key bottleneck'.
we saw that a way to solve this problem is the following Greedy Heuristic: Step 1:
Order parts [1] to [N] such that
P [1]
P[2]
P[N]
Define remaining available time T = P
Step 2: For i = 1...N select part [i] and add the part to the FMS if p, < T and s, > 0. Each
time you add a new part i, update the remaining available time as T = T - P₁
Now suppose you had 3 'key bottlenecks' (that is 3 resources that each might be the
bottleneck depending on the parts you choose to produce in the FMS). These resources
have P, Q and R time units available respectively. And each part i requires a total processing
time p, q, and r, in each of the three, respectively. Modify the algorithm above to solve the
3-bottleneck version of the problem.
TIP: In Step 1 you need to consider the processing times at all 3 stations to do the
ordering. In step 2, you must keep track of the remaining capacity at each station
separately.
3) An FMS consists of five stations. Station 1 is a load/unload station with one server.
Station 2 performs milling operations with one server. Station 3 performs drilling
operations with two servers (two identical CNC drill presses). Station 4 is for
performing grinding operations with three identical servers (three identical CNC
grinding machines). Station 5 is an inspection station with one server that performs
inspections on a sample of the parts. The stations are connected by a part handling
system that has two work carriers and a mean transport time = 4.0 min. The FMS
produces six parts A, B, C, D, E, and F. The part mix fractions and process routings
for the six parts are presented in the table below. Note that the operation frequency
at the inspection station (f_5jk) is less than 1.0 to account for the fact that only a
fraction of the parts are inspected. For this system determine:
(a) Maximum production rate of the FMS;
(b) Corresponding production rate of each part;
(c) Utilization of each station in the system;
(d) Overall FMS utilization.
Transcribed Image Text:2) Consider the Part Type Selection problem we covered in class. This problem helps us determine which parts we will produce in a new FMS. The problem assumes that we have candidate parts i = 1, 2, ...N, that the total savings achieved by producing part i in the FMS is s, and that we know that there is a 'key bottleneck' in the FMS, which has P available time units. Each part i requires a total processing time p, in the 'key bottleneck'. we saw that a way to solve this problem is the following Greedy Heuristic: Step 1: Order parts [1] to [N] such that P [1] P[2] P[N] Define remaining available time T = P Step 2: For i = 1...N select part [i] and add the part to the FMS if p, < T and s, > 0. Each time you add a new part i, update the remaining available time as T = T - P₁ Now suppose you had 3 'key bottlenecks' (that is 3 resources that each might be the bottleneck depending on the parts you choose to produce in the FMS). These resources have P, Q and R time units available respectively. And each part i requires a total processing time p, q, and r, in each of the three, respectively. Modify the algorithm above to solve the 3-bottleneck version of the problem. TIP: In Step 1 you need to consider the processing times at all 3 stations to do the ordering. In step 2, you must keep track of the remaining capacity at each station separately. 3) An FMS consists of five stations. Station 1 is a load/unload station with one server. Station 2 performs milling operations with one server. Station 3 performs drilling operations with two servers (two identical CNC drill presses). Station 4 is for performing grinding operations with three identical servers (three identical CNC grinding machines). Station 5 is an inspection station with one server that performs inspections on a sample of the parts. The stations are connected by a part handling system that has two work carriers and a mean transport time = 4.0 min. The FMS produces six parts A, B, C, D, E, and F. The part mix fractions and process routings for the six parts are presented in the table below. Note that the operation frequency at the inspection station (f_5jk) is less than 1.0 to account for the fact that only a fraction of the parts are inspected. For this system determine: (a) Maximum production rate of the FMS; (b) Corresponding production rate of each part; (c) Utilization of each station in the system; (d) Overall FMS utilization.
Part
Part mix
Station
Frequency
J
Pj
Op k
Description
Process time tijk (min)
fijk
A
0.1
1
Load
1
3
1.0
2
Drill
3
12
1.0
3
Grind
4
28
1.0
4
Inspect
5
8
0.4
5
Unload
1
2
1.0
B
0.2
1
Load
1
3
1.0
2
Mill
2
12
1.0
3
Drill
3
12
1.0
4
Grind
4
33
1.0
5
Drill
3
11
1.0
6
Inspect
5
9
0.3
7
Unload
1
2
1.0
0.15
1
Load
1
3
1.0
2
Mill
2
14
1.0
3
Drill
3
11
1.0
4
Inspect
5
12
0.2
5
Unload
1
2
1.0
0.1
1
Load
1
3
1.0
2
Drill
3
17
1.0
3
Inspect
5
10
0.2
4
Unload
1
2
1.0
E
0.1
1
Load
1
3
1.0
2
Grind
4
32
1.0
3
Drill
3
13
1.0
4
Grind
4
37
1.0
5
Inspect
5
12
0.1
6
Unload
1
2
1.0
0.35
1
Load
1
3
1.0
2
Mill
2
26
1.0
3
Drill
3
13
1.0
4
Grind
4
39
1.0
5
Inspect
5
8
0.3
6
Unload
1
2
1.0
Transcribed Image Text:Part Part mix Station Frequency J Pj Op k Description Process time tijk (min) fijk A 0.1 1 Load 1 3 1.0 2 Drill 3 12 1.0 3 Grind 4 28 1.0 4 Inspect 5 8 0.4 5 Unload 1 2 1.0 B 0.2 1 Load 1 3 1.0 2 Mill 2 12 1.0 3 Drill 3 12 1.0 4 Grind 4 33 1.0 5 Drill 3 11 1.0 6 Inspect 5 9 0.3 7 Unload 1 2 1.0 0.15 1 Load 1 3 1.0 2 Mill 2 14 1.0 3 Drill 3 11 1.0 4 Inspect 5 12 0.2 5 Unload 1 2 1.0 0.1 1 Load 1 3 1.0 2 Drill 3 17 1.0 3 Inspect 5 10 0.2 4 Unload 1 2 1.0 E 0.1 1 Load 1 3 1.0 2 Grind 4 32 1.0 3 Drill 3 13 1.0 4 Grind 4 37 1.0 5 Inspect 5 12 0.1 6 Unload 1 2 1.0 0.35 1 Load 1 3 1.0 2 Mill 2 26 1.0 3 Drill 3 13 1.0 4 Grind 4 39 1.0 5 Inspect 5 8 0.3 6 Unload 1 2 1.0
Expert Solution
steps

Step by step

Solved in 1 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman