For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31? Number For the Toy Car table above, what are the Planned Order Releases in the week of 9/21? Number For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7? Number For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31? Number For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24? Number For the Axle table above, what are the Gross Requirements in the week of 9/7? Number For the Axle table above, what are the Gross Requirements in the week of 9/14? Number For the Axle table above, what are the Planned Order Releases in the week of 8/17? Number

MATLAB: An Introduction with Applications
6th Edition
ISBN:9781119256830
Author:Amos Gilat
Publisher:Amos Gilat
Chapter1: Starting With Matlab
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31?
Number
For the Toy Car table above, what are the Planned Order Releases in the week of 9/21?
Number
For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7?
Number
For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31?
Number
For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24?
Number
For the Axle table above, what are the Gross Requirements in the week of 9/7?
Number
For the Axle table above, what are the Gross Requirements in the week of 9/14?
Number
For the Axle table above, what are the Planned Order Releases in the week of 8/17?
Number
Transcribed Image Text:For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31? Number For the Toy Car table above, what are the Planned Order Releases in the week of 9/21? Number For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7? Number For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31? Number For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24? Number For the Axle table above, what are the Gross Requirements in the week of 9/7? Number For the Axle table above, what are the Gross Requirements in the week of 9/14? Number For the Axle table above, what are the Planned Order Releases in the week of 8/17? Number
MS.52 A toy company needs to calculate material requirements for its top-selling toy car. The graphic above shows the bill of material for this item. Below
are three MRP tables for the top-level assembly (the car) and some of its components:
Toy Car Final Assembly
8/3
8/10
8/17
8/24
8/31
9/7
9/14
9/21
9/28
Gross Requirements
800
1000
2200
2300
Scheduled Receipts
320
670
370
Projected On-Hand Inv.
250
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks)
1
Lot Size
130
Wheel Assembly
8/3
8/10
8/17
8/24
8/31
9/7
9/14
9/21
9/28
Gross Requirements
Scheduled Receipts
1100
2000
1800
Projected On-Hand Inv.
900
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks)
1
Lot Size
250
Axle
8/3
8/10
8/17
8/24
8/31
9/7
9/14
9/21
9/28
Gross Requirements
Scheduled Receipts
1100
1700
Projected On-Hand Inv.
300
Net Requirements
Planned Order Receipts
Planned Order Releases
Lead Time (in weeks)
3
Lot Size
200
Transcribed Image Text:MS.52 A toy company needs to calculate material requirements for its top-selling toy car. The graphic above shows the bill of material for this item. Below are three MRP tables for the top-level assembly (the car) and some of its components: Toy Car Final Assembly 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 Gross Requirements 800 1000 2200 2300 Scheduled Receipts 320 670 370 Projected On-Hand Inv. 250 Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) 1 Lot Size 130 Wheel Assembly 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 Gross Requirements Scheduled Receipts 1100 2000 1800 Projected On-Hand Inv. 900 Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) 1 Lot Size 250 Axle 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 Gross Requirements Scheduled Receipts 1100 1700 Projected On-Hand Inv. 300 Net Requirements Planned Order Receipts Planned Order Releases Lead Time (in weeks) 3 Lot Size 200
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
MATLAB: An Introduction with Applications
MATLAB: An Introduction with Applications
Statistics
ISBN:
9781119256830
Author:
Amos Gilat
Publisher:
John Wiley & Sons Inc
Probability and Statistics for Engineering and th…
Probability and Statistics for Engineering and th…
Statistics
ISBN:
9781305251809
Author:
Jay L. Devore
Publisher:
Cengage Learning
Statistics for The Behavioral Sciences (MindTap C…
Statistics for The Behavioral Sciences (MindTap C…
Statistics
ISBN:
9781305504912
Author:
Frederick J Gravetter, Larry B. Wallnau
Publisher:
Cengage Learning
Elementary Statistics: Picturing the World (7th E…
Elementary Statistics: Picturing the World (7th E…
Statistics
ISBN:
9780134683416
Author:
Ron Larson, Betsy Farber
Publisher:
PEARSON
The Basic Practice of Statistics
The Basic Practice of Statistics
Statistics
ISBN:
9781319042578
Author:
David S. Moore, William I. Notz, Michael A. Fligner
Publisher:
W. H. Freeman
Introduction to the Practice of Statistics
Introduction to the Practice of Statistics
Statistics
ISBN:
9781319013387
Author:
David S. Moore, George P. McCabe, Bruce A. Craig
Publisher:
W. H. Freeman