1)Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity Description Immediate Predecessor Time (weeks) A Survey building site 7 B Develop initial design 11 C Obtain board approval A, B 15 D Select architect C 2 E Establish budget C 5 F Finalize design D, E 17 G Obtain financing E 13 H Hire contractor F, G 8 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) (c) Develop the activity schedule for the project. Activity Earliest Start Latest Start Earliest Finish Latest Finish Slack A B C D E F G H (d) Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project? The expected completion time is weeks, which is greater than 1 year.
1)Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity Description Immediate Predecessor Time (weeks) A Survey building site 7 B Develop initial design 11 C Obtain board approval A, B 15 D Select architect C 2 E Establish budget C 5 F Finalize design D, E 17 G Obtain financing E 13 H Hire contractor F, G 8 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) (c) Develop the activity schedule for the project. Activity Earliest Start Latest Start Earliest Finish Latest Finish Slack A B C D E F G H (d) Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project? The expected completion time is weeks, which is greater than 1 year.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
100%
Please need help with the correct answers in details: Thank you
1)Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.
Activity | Description | Immediate Predecessor |
Time (weeks) |
---|---|---|---|
A | Survey building site | 7 | |
B | Develop initial design | 11 | |
C | Obtain board approval | A, B | 15 |
D | Select architect | C | 2 |
E | Establish budget | C | 5 |
F | Finalize design | D, E | 17 |
G | Obtain financing | E | 13 |
H | Hire contractor | F, G | 8 |
(a)
Draw a project network. (Submit a file with a maximum size of 1 MB.)
(c)
Develop the activity schedule for the project.
Activity | Earliest Start |
Latest Start |
Earliest Finish |
Latest Finish |
Slack |
---|---|---|---|---|---|
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G | |||||
H |
(d)
Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?
The expected completion time is weeks, which is greater than 1 year.
2)
You may need to use the appropriate technology to answer this question.
Blue Lagoon is a contractor that installs residential swimming pools, projects that consist of nine major activities. The activities, their immediate predecessors, and the activity time estimates (in days) are shown.
Activity | Immediate Predecessor | Optimistic | Most Probable | Pessimistic |
---|---|---|---|---|
A | 3 | 5 | 6 | |
B | 2 | 4 | 6 | |
C | A, B | 6 | 7 | 8 |
D | A, B | 8 | 10 | 11 |
E | B | 2 | 4 | 6 |
F | C | 1 | 2 | 3 |
G | D | 6 | 10 | 12 |
H | D, F | 7 | 9 | 11 |
I | E, G, H | 3 | 4 | 5 |
(a)
What are the critical activities? (Enter your answers as a comma-separated list.)
(b)
What is the expected time (in days) to complete the project? (Round your answer to two decimal places.)
days
(c)
Based only on the critical path, what is the estimated probability that the project can be completed in 28 or fewer days? (Round your answer to four decimal places.)
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 4 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.