The Center for Information Technology at State University has outgrown its office in Bates (B) Hall and is moving to Allen (A) Hall, which has more space. The move will take place during the 3-week break between the end of summer semester and the beginning of fall semester. Movers will be hired from the university's physical plant to move the furniture, boxes of books, and files that the faculty will pack. The center has hired a local retail computer firm to move its office comput- ers so they won't be damaged. Following is a list of activities, their precedence relationships, and probabilistic time estimates for this project: Activity Description Predecessor Most likely Optimistic estimate (a) Pessimistic estimate (b) estimate (m) a Pack A offices 1 3 5 b Network A offices 2 3 5 с Pack B offices 2 4 7 d Movers move A a 1 3 4 offices Paint and clean A d 2 5 8 offices f Move computers b. e 1 2 2 Movers move B b, c, e 3 6 8 offices Computer f 2 4 5 installation Faculty move and g 3 4 6 unpack j h, i 1 2 Faculty set up computers and offices a. Draw up a table including activity, expected time and variance and then construct the project network. b. Find the critical path. c. Determine the expected completion time for the project. d. Calculate the probability that the project will be completed within 3 weeks. OD h t
The Center for Information Technology at State University has outgrown its office in Bates (B) Hall and is moving to Allen (A) Hall, which has more space. The move will take place during the 3-week break between the end of summer semester and the beginning of fall semester. Movers will be hired from the university's physical plant to move the furniture, boxes of books, and files that the faculty will pack. The center has hired a local retail computer firm to move its office comput- ers so they won't be damaged. Following is a list of activities, their precedence relationships, and probabilistic time estimates for this project: Activity Description Predecessor Most likely Optimistic estimate (a) Pessimistic estimate (b) estimate (m) a Pack A offices 1 3 5 b Network A offices 2 3 5 с Pack B offices 2 4 7 d Movers move A a 1 3 4 offices Paint and clean A d 2 5 8 offices f Move computers b. e 1 2 2 Movers move B b, c, e 3 6 8 offices Computer f 2 4 5 installation Faculty move and g 3 4 6 unpack j h, i 1 2 Faculty set up computers and offices a. Draw up a table including activity, expected time and variance and then construct the project network. b. Find the critical path. c. Determine the expected completion time for the project. d. Calculate the probability that the project will be completed within 3 weeks. OD h t
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Only part (d) is needed
Part a,b and have already been answered, but the expert at Bartleby asked me to submit as a separeate question.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.