17. Use the longest task time rule to balance the assembly line described in Table 10.21; the line can produce 30 units per hour. (a) What is the cycle time? (b) What is the theoretical minimum number of stations? (c) Which work elements are assigned to which workstations? (d) What are the resulting efficiency and balance delay percentages? 388 CHAPTER 10 • Facility Layout TABLE 10.21 Assembly-Line Task Information Immediate Predecessor o Task Time (sec) Work Element None 25 30 15 30 C, D 40 19 20 10 15 bE, F, H 35 J 25 K 25

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Question in comments 

17. Use the longest task time rule to balance the assembly
line described in Table 10.21; the line can produce 30
units per hour.
(a) What is the cycle time?
(b) What is the theoretical minimum number of
stations?
(c) Which work elements are assigned to which
workstations?
(d) What are the resulting efficiency and balance
delay percentages?
Transcribed Image Text:17. Use the longest task time rule to balance the assembly line described in Table 10.21; the line can produce 30 units per hour. (a) What is the cycle time? (b) What is the theoretical minimum number of stations? (c) Which work elements are assigned to which workstations? (d) What are the resulting efficiency and balance delay percentages?
388 CHAPTER 10 • Facility Layout
TABLE 10.21 Assembly-Line Task Information
Immediate
Predecessor
o Task Time
(sec)
Work Element
None
25
30
15
30
C, D
40
19
20
10
15
bE, F, H
35
J
25
K
25
Transcribed Image Text:388 CHAPTER 10 • Facility Layout TABLE 10.21 Assembly-Line Task Information Immediate Predecessor o Task Time (sec) Work Element None 25 30 15 30 C, D 40 19 20 10 15 bE, F, H 35 J 25 K 25
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Knowledge Booster
Introduction to Maintenance and Reliability
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.