1. Should BestLine's ordering department have been more involved during the project? 2. Sarah used expert interviews for this project. Were there more effective methods for gathering the requirements? 3. What crucial step(s) did Sarah skip in the requirements process? 4. Which downstream activities would likely be affected by her approach? At what point in the project would the problems likely emerge? 5. Should Sarah have presented the requirements to the ordering manager at this point? Should the ordering manager have signed off on them?
1. Should BestLine's ordering department have been more involved during the project? 2. Sarah used expert interviews for this project. Were there more effective methods for gathering the requirements? 3. What crucial step(s) did Sarah skip in the requirements process? 4. Which downstream activities would likely be affected by her approach? At what point in the project would the problems likely emerge? 5. Should Sarah have presented the requirements to the ordering manager at this point? Should the ordering manager have signed off on them?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Please answer in one paragraph each question

Transcribed Image Text:Mastering Scope and Requirements Management
Case
BestLine Hardware
Study I|
In spring of last year, BestLine Hardware undertook an ambitious program to overhaul their supply chain.
In early planning, BestLine predicted that they could save over 25% of their entire supply chain costs by
streamlining and optimizing their practices.
One of the areas that had the most promise for savings and efficiency was that of order communication and
fulfillment. In the existing system, Bestline's inventory management department triggered a request to the
ordering department. The ordering department then created an order and faxed it out to one of their suppliers.
The supplier marked down on the fax what could be fulfilled against the order and would fax it back
to BestLine for processing.
Over time, this fax-based system proved to be inefficient and error-prone. Faxes were often lost or garbled,
and hand-written comments could be very difficult to interpret accurately. As a part of their supply-chain
efficiency effort, BestLine decided that they would try to modernize their ordering and fulfillment system
by creating an Internet-based system. BestLine believed that the Internet solution would improve the
speed, reliability, and accuracy of order placement.
A project was commissioned, and Sarah Davis, a senior project manager, was assigned to the effort.
Immediately, Sarah went about analyzing the project, understanding the reasons it had been undertaken. She
identified the needs and the stakeholders for each need, and she properly identified the project's constraints.
As Sarah began to gather the requirements, however, she started experiencing difficulty with the project.
Members of senior management expressed a strong idea about the scope of the project, but the Information
Technology department had a thorough set of technical requirements that did not completely fit senior
management's goals. Additionally, the supplier-relations group commissioned a focus group of suppliers
and insisted that this group be allowed to give input on the project.
Ultimately, Sarah elected to try and involve as many of the stakeholders as possible. She and her lead
Business Analyst set up a series of ninety minute one-on-one expert interviews with the stakeholders.
They gathered nearly two hundred pages of documentation as a result of these meetings, and from there,
Sarah and the analyst worked to create usability scenarios that represented all of the requirements she had
captured.
The focus group continued to be involved in the process, and in general they were pleased with what they
saw. When the requirements were presented to the ordering department for sign off, however, the manager
of the ordering department complained that he had not been adequately involved and that the documented
requirements were nearly impossible for a non-technical person to understand. Sarah stated that the
requirements had been thoroughly analyzed and pointed out the ordering department had been given the
opportunity to be involved. She also noted that two department members had been interviewed, and she
stressed that any delay on the signature at this point would almost certainly delay the project.
Ultimately, the manager of the ordering department signed off on the requirements, even though he did not
feel comfortable with his understanding of the material. Sarah and her team then began designing the new
system.

Transcribed Image Text:Case Study II Questions
BestLine Hardware:
1. Should BestLine's ordering department have been more involved during the project?
2. Sarah used expert interviews for this project. Were there more effective methods for gathering the
requirements?
3. What crucial step(s) did Sarah skip in the requirements process?
4. Which downstream activities would likely be affected by her approach? At what point in the project
would the problems likely emerge?
5. Should Sarah have presented the requirements to the ordering manager at this point? Should the ordering
manager have signed off on them?
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education

Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,

Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning

Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.