![2) The following tasks been assigned for a project following the steps needed to develop
a project network. Show all necessary steps and graphical representations.
Find: 1) Critical Path for this project
2) Total free slack times for each activity
3) Total completion Time
4) The latest time that the activity D must be started to complete the project by
day 54
Activity
Predecessor
Activity Time
A
None
None
12
B
8.
D
B
E
9.
D
10
D
7
I
6.
J
15
K
I,J
11
H.
F,G
M,L,K
5.
46
BC
EFGH-
MLMN](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F9e81349d-4091-4cc6-9233-a2e1548b830b%2F13c69b31-4d11-4ab5-9a19-7e20a3f6989e%2Fxb6s4v_processed.jpeg&w=3840&q=75)
Transcribed Image Text:2) The following tasks been assigned for a project following the steps needed to develop
a project network. Show all necessary steps and graphical representations.
Find: 1) Critical Path for this project
2) Total free slack times for each activity
3) Total completion Time
4) The latest time that the activity D must be started to complete the project by
day 54
Activity
Predecessor
Activity Time
A
None
None
12
B
8.
D
B
E
9.
D
10
D
7
I
6.
J
15
K
I,J
11
H.
F,G
M,L,K
5.
46
BC
EFGH-
MLMN
![!) Define, indicate significance, and give pertinent relationship of the following:
a) WBS/ AON/AOA/ Bar chart
b) Events/task/activity
c) Duration/activity
d) LST/EST/EFT/LFT
e) Resources/ budget](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F9e81349d-4091-4cc6-9233-a2e1548b830b%2F13c69b31-4d11-4ab5-9a19-7e20a3f6989e%2Fl0oafda_processed.jpeg&w=3840&q=75)
Transcribed Image Text:!) Define, indicate significance, and give pertinent relationship of the following:
a) WBS/ AON/AOA/ Bar chart
b) Events/task/activity
c) Duration/activity
d) LST/EST/EFT/LFT
e) Resources/ budget
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning