Assignment Content 1. Quiz #2 is from the second week material, i.e. Chapter 3 of the textbook (Schwalbe's IT Project Management). o 15 minutes for 10 questions (MCQs ) o Backtracking Prohibited (You can not go back to previous questions, no matter if you answered or not; so do NOT go to next question before answering, otherwise you can not come back) o One question at a time o Random questions and random answers By beginning the test you affirm that you will not give or receive any unauthorized help, and that all work will be your own. You agree to abide by Seneca's Academic Integrity Policy and you understand any violation of academic integrity will be subject to the penalties outlined in the policy. 2. Question 1 1/1 Which planning process is associated with project scope management? Hide answer choices Correct: Collecting requirements Correct answer Performing qualitative risk analysis Planning schedule management Estimating costs Feedback Rationale: Feedback: Process improvement plans are an output of project quality management.
3. Question 2 1/1 The project cost management knowledge area maps to which process group through the activities of estimating costs and budget determination? Hide answer choices initiating Correct: planning Correct answer executing monitoring and controlling Feedback Rationale: Feedback: The project cost management knowledge area maps to the planning process group through the activities of estimating costs and budget determination. 4. Question 3 1/1 What process group does the project integration management knowledge area map to through the activities of developing project charters? Hide answer choices
Correct: initiating Correct answer planning executing monitoring and controlling Feedback Rationale: Feedback: The project integration management knowledge area maps to the initiating process group through the activities of developing project charters. 5. Question 4 1/1 What processes include defining and authorizing a project or project phase? Hide answer choices Correct: Initiating Correct answer Planning
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
Executing Monitoring and controlling Feedback Rationale: Feedback: Initiating processes include defining and authorizing a project or project phase. Initiating processes take place during each phase of a project. 6. Question 5 1/1 The project stakeholder management knowledge area maps to which process group by identifying stakeholders? Hide answer choices Correct: initiating Correct answer planning executing monitoring and controlling Feedback Rationale: Feedback: The project stakeholder management knowledge area maps to the initiating process group by identifying stakeholders.
7. Question 6 1/1 Which is an example of a pre-initiation task? Hide answer choices Drawing up a work breakdown structure Correct: Developing a business case for a project Correct answer Drafting the project charter Identifying stakeholders Feedback Rationale: Feedback: It is good practice to lay the groundwork for a project before it officially starts. Senior managers often perform several tasks, sometimes called pre-initiation tasks which include the development of a business case for a project. 8. Question 7 1/1 Which framework is an iterative software development process that focuses on team productivity and delivers software best practices to all team members? Hide answer choices
Agile Unified Process Dynamic Systems Development Method Correct: Rational Unified Process Correct answer Six Sigma 9. Question 8 1/1 Which process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end? Hide answer choices executing Correct: closing Correct answer planning
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
monitoring Feedback Rationale: Feedback: The closing process involves gaining stakeholder and customer acceptance of the final products and services and then bringing the project or project phase to an orderly end. It includes verifying that all of the deliverables are complete, and it often includes a final project report and presentation. 10.Question 9 1/1 An organizational process assets update is the output of which closing process? Hide answer choices Correct: project integration management Correct answer project quality management project procurement management project time management Feedback Rationale: Feedback: The closing process involves gaining stakeholder and customer acceptance of the final products and services and then bringing the project or project phase to an orderly end. It includes verifying that all of the deliverables are complete, and it often includes a final project report and presentation.
11.Question 10 1/1 In the Scrum method, during which meeting is the improvement of the product and process discussed? Hide answer choices Correct: sprint retrospective Correct answer sprint review kick-off daily Scrum Feedback Rationale: Feedback: The improvement of the product and process in the Scrum method is discussed at the sprint reflection meeting.