Assessment Resource Summary
Unit Details
CPCCBC4005A Produce labour and material schedules for ordering
Assessment Type
This is a summative assessment
, which requires each
student to have adequate practice prior to undertaking
this assessment
This assessment has been contextualised for
Building and Construction, and must be undertaken
in a real or simulated Building and Construction
environment
Assessment
Projects
Assessment 1 - 5
Written assessment
Assessment 6
(Written Assessment attached)
Last Modification Date
Nov 18
Verified By: Training Manager
Proposed Review Date
Nov 19
Approved by: CEO
Version no.
UED-112019-0013
Unit Summary
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
This unit describes the performance outcomes, skills and knowledge required to implement, monito
and review strategies for the ongoing management of a small business's finances. It also includes day to day financial management of the small business.
Specific legal requirements apply to the management of a small business.
This unit describes the skills and knowledge required to implement and review financial management strategies on a regular basis.
It applies to individuals who operate a small business that stands alone, or is part of a department within a larger organisation. Individuals in this role interpret financial reports and other numerical data to develop financial management strategies.
No licensing, legislative or certification requirements apply to this unit at the time of publication.
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
ASSESSMENT SUMMARY / COVERSHEET
This form is to be completed by the assessor and used a final record of student competency.
All student submissions including any associated checklists (outlined below) are to be attached to this cover
sheet before placing on the students file.
Student results are not to be entered onto the Student Database unless all relevant paperwork is completed
and attached to this form.
Student Name:
JAYATUNGA WITHANAGE BUDDHIKA DANANJAYA SIRIWARDANA
Student ID No:
UEDT334
Final Completion Date:
Unit Code:
CPCCBC4005A
Unit Title:
Produce labour and material schedules for ordering
Please attach the following documentation to this form:
Result
S = Satisfactory
NS = Not Satisfactory
Assessment 1
Heritage overlay report attached
S | NS Assessment 2
Roofing schedule attached
S | NS Assessment 3
Call forward sheets attached
S | NS Assessment 4
Updated project documentation attached
S | NS Assessment 5
Observation checklist attached
S | NS Assessment 6
Written assessment attached
S | NS Final Assessment Result for this unit
C / NYC
Student Feedback: ________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Student Declaration:
I declare that I have been assessed in this unit, and I have been advised of my result. I also am aware of my appeal rights.
Name: ________________________________
Signature: ____________________________
Date: ____/_____/_____
Assessor Declaration: I declare that I have conducted a fair, valid, reliable and flexible assessment with this student, and I have provided appropriate feedback
Name: ________________________________
Signature:
____________________________
Date: ____/_____/_____
Administrative use only
Entered onto Student Management Database
________________
Date
Initials
Student Instructions
CPCCBC4005A – Produce labour and material schedules for ordering Metharom Construction (MC) plans to become a leading provider of housing construction and renovation services in the South-East Melbourne area. The company's overall strategy
will be based on a continuing improvement process of setting objectives, measuring results,
and providing feedback to facilitate further growth and progress. They have been involved in large scale construction for 3 years and are now branching out to residential housing. During this unit, you will need to take on the role of the site supervisor. Your responsibilities are to: enforce site safety plans, ensure all tradespersons are inducted before they begin work, conduct regular inspections to ensure building quality, ensure that any contractors are complying with site rules and safe work method statements, identify and correct hazards, ensure that the site is ready for each trade before they arrive, and have frequent toolbox talks to ensure that WHS procedures are known and followed.
For more information regarding Metharom Construction, please see the appendices and Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
company policy documentation.
Assessment 1: Find the heritage overlay relevant to the site and produce a report for the client. (Maximum 250 words)
Using the information supplied in the project documents; determine the heritage overlay requirements for the site. Next, produce a report for the client that details any changes that will have to be made to the plans, because of the information found in the heritage overlay.
The report must not exceed 250 words.
Tree controls legacy overlay is needed for the site. This control is intended to secure trees that are of inborn importance, (for example, trees that are remembered for the National Trust Heritage Register), or trees that add to the meaning of a legacy place (for instance, trees that add to the meaning of a nursery or region). This implies we need an arranging grant to chop down the trees. We have not many trees present in the north side of the property where our proposed building's face is found. The trees are available close to the proposed footings in north face.
Trees have antagonistic impact on the exhibition of footings. Expulsion of trees are needed to forestall this yet a gathering should be booked with the board individuals to examine about the evacuation of trees. It very well may be a drawn-out and costly methodology. Thus, I have suggested a few changes in the structure intend to adapt with the impact of trees. We need to a plan uncommon kind of balance for the structure, introduce root hindrances and need to unearth essentially 200mm underneath the upset soil. Substantial chunk balance should be utilized rather than strip footings which is set on a layer of sand for seepage or to go about as a pad. This will forestall soil dampness from aggregation close to the balance.
Assessment 2: Prepare a schedule for the roofing of the building. (Maximum of 700 words)
Prepare a schedule for the roofing of the build. Your schedule will need to include:
a)
Statutory requirements, such as inspections
person who carried out the inspection should have a valid license
roofer’s license b)
Choose a colour for the roof tiles and provide details so that they can be ordered (such as colour, brand, and product number)
Colour – blue
Brand – Boral
Product number – B324111
c)
Add the supplier to the current list of suppliers. You will need to include the supplier’s name, address and the goods that they provide. Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
d)
Determine which of the subcontractors would be most suitable for this part of the project.
Raucous roofers
e)
Provide an estimate of the materials and labour
roof area = 259.6 = 260 sqm
tiles = 0.265 x 0.165 = 0.0437sqm
total tiles = 260/0.0437
10% wastage
total tiles need = 6500 X $4 (per tile) = $26000
membrane = 260sqm x $8 = $ 2080
nails = $150
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Gutters 60m x $13 = $780
DOWN PIPES 7 X $28 = $196
Material TOTAL = $26000 + $2080 + $150 + $780 + $196 = $29206.00
total tiling area = 260sqm roof tiler Level 3 (CW/ECW3) roof tiler $25.44 per hour
1 tiler can do 8sqm per day
total labour days = 33 days
8hrs per day
1 day = $203.52
33 days = $ 6716.1
total estimate is $29206.00 + $6716.1 = $35922.1 The sheet must not contain more than 700 words.
Assessment 3: Create two call forward sheets. (Maximum of 500 words)
Create two call forward sheets (using the template provided) for material orders for the site. Each sheet must be for a different order. For your work team to be able to use the sheet effectively, it must contain information regarding:
a)
The orders required from each supplier
b)
Name of the nominated supplier (refer to the supplier list)
c)
Any special instructions required regarding storage and delivery
The sheet must not contain more than 500 words.
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
Assessment 4: Incorporate client variations into the project documents. (Maximum of
500 words)
The client has requested that the ceramic tiles in the bathrooms, kitchen and laundry be replaced with marble. Now that the project requirements have been changed, you will need to do the following:
a)
Produce a new schedule for this stage of the build, which incorporates the variation
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
Task
Start
date
End date
Duration
Start date
12/9/16
12/9/16
1 day
Approvals
12/9/16
4/10/16
15 days (1 day + 14 days wait time)
Contract and project management
(including surveying, ordering and
subcontracting)
12/9/16
21/9/16
7 days
Site preparation: fencing, office,
toilets, and first aid 22/9/16
22/9/16
1 day
Site preparation: security cameras
and safety signage
23/9/16
23/9/16
1 day
Site preparation: supply of materials,
equipment and plant
26/9/16
26/9/16
1 day
Excavation prep
26/9/16
28/9/16
2 days
Foundation backfill
28/9/16
29/9/16
1 day
Footings/retaining walls
29/9/16
11/10/16
7 days
Slab
11/10/1
6
14/10/16
3 days
Framing
14/10/1
6
8/12/16
38 days
Roof
9/12/16
11/1/17
20 days
Plumbing rough-in
11/1/17
6/3/17
37 days
Electrical rough-in
6/2/17
6/3/17
20 days
HVAC
7/3/17
31/3/17
17 days
Exterior finishes
1/6/17
4/8/17
45 days
Insulation
7/8/17
14/8/17
5 days
Plastering
15/8/17
12/9/17
20 days
Flooring
13/9/17
24/10/17
29 days
Paint
25/10/1
7
12/12/17
34 days
Trims
13/12/1
7
8/1/18
15 days
Hardware installation
9/1/18
16/1/18
5 days
Occupancy inspection
17/1/18
18/1/18
1 day
Punch list inspection
19/1/18
20/1/18
1 day
Completion of punch list
21/1/18
29/1/18
5 days
Cleaning
30/1/18
6/2/18
5 days
Final inspection
7/2/18
8/2/18
1 day
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Move-in
9/2/18
9/2/18
-
b)
Estimate the cost of the variation, including labour and materials
tiles
marble
total tile area = 64sqm
total marble area = 64m
2
tile per sqm = $50
marble per sqm = $150
total tile supply price = $3520 (inc. wastage 10%)
marble supply price = $10560 (inc 10% wastage)
tiler $25.7 per hour (10m
2
per hour)
tiler can do 4m
2
per hour
8 (labours) x 8 (hours) x 25.7 (rate) = $1644
marble installation price is $3288
c)
Update the plans to include the changes
d)
Update the specifications lists to ensure that the new materials are listed
e)
Prepare an itemised final cost estimate for the laundry, using the project plans
laundry estimation
item
QTY
cost
thorough
1
$ 259.00
tap
2
$ 72.00
Washing machine tap
2
$ 72.00
Washing machine
1
$ 650.00
Drayer
1
$ 700.00
Labour (8 hrs) ($45 per hr)
1
$ 360.00
Total cost
$ 2113.00
Assessment 5: Meet with the construction manager, in a role play.
In a meeting with the construction manager (to be played by the assessor), present the new plans (from assessment 4) and analyse the cost. You will need to discuss both the tangible and intangible costs of the variation, with reference to your site file. This meeting is to assess the positives and negatives of completing the variation that the client requested, and analyse the variation’s effect on the cost of the whole project.
Your assessor will be looking for:
Consideration of labour and material costs
Evidence that the site file contains all information relevant to the project
Analysis of the cost of the variation, and the variation’s effect on the final cost of the project
Me: - Good Morning Faheem, how you doing?
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
Construction Manager: - I’m really good buddhika, what about you?
Me: - I’m good sir, just noticed you have some questions for me
Construction Manager: - yes, I have few questions related to Ascot vale job and hope you have enough information discuss with me
my first question is, what would be the potential benefits of completing the variation
Me: - good question sir, so I’m happy explain it this way, Variation allows the constructive
changes that allow changing on the mistake and error accidently occurred such as example in correcting a discrepancy in the contract drawing and specification.
Construction Manager: - are there any other marble options that have a lower cost but still meet the client requirements?
Me: - No, Faheem, this client is very fussy and wants add exact same marble as they selected
Construction Manager: - are there any potential downsides of completing the variation for the client?
Me: - yes sir, the disadvantage of variation is that allows the Architect, or other designers to delay making decisions almost until the last possible moment. This can be having serious repercussions on the planning of the project and in executing the works efficiently.
and also, there will major delay due to material change, as we need to order materials and also there will be add more time for delivery as well
Construction Manager: - is there another way of fulfilling both the clients wishes & those of original design.
Me: - yes sir, we can use quartz
which is more affordable option than marble and also white concrete
can affordable and touch elegance, stain protection and also heat resistance
as well. Note:
The work you submit must be your own. St
uden
t
s have the responsibility to maintain the highest ethical standards of academic integrity in their w
or
k. Academic misconduct by students in examinations or in other forms of assessment is un
a
cc
ep
t
ab
le
.
Prior to submitting an assessment, each student will be required to complete an a
ssessmen
t cover sheet which will ask them to sign a declaration to say they have not plagiarised and t
h
at they have read and understood the UEDPlagiarism po
lic
y.
All work submitted will be checked to ensure authenticity.
Students found to have plagiarised will be forced to re-submit the assessment and be required to pay the re-submission fee of $350 per unit of competency and may be subject to disciplinary action.
Preparation Date: AUG 2020 Proposed Review Date: AUG 2021 – Verified By: training Manager | Approved by CEO
RTO No: 31250 | CRICOS Provider Code: 03579K
Recommended textbooks for you

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningMarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing