1 Project Name of Student: Eric Adom Institutional Affiliation: APUS/AMU Course Code: ITMG624 Professor’s Name: Dr. H Date:03/12/2024
2 Work Breakdown Structure (WBS) for Future Technology Data Center Relocation Project: Project Initiation 1.4 Generate Project Charter and Statement of Work. 1.2 Team Recruitment 1.3 Set up the first team meeting as soon as you can Preparation Phase 2.1. Contractors are necessary for large-scale and intricate reformation. 2.2 Design Network 2.3 Order Ventilation System 2.4 Order Racks 2.5 Reorder supplies such as Power Supplies. Installation Phase 3.1 Install Ventilation System 3.2 Install Racks 3.3 Embed the power supplies and data cables 3.4 A raised floor is to be constructed. Testing and Approval Phase
3 4.1 Switchover Approval Meetings with Functional Units 4.2 Power Check for Racks 4.3 Installation of Test Servers 4.4 Primary Systems Check Execution Phase 5.1 Network Shutdown and Move Description In order to outline what work breakdown structure (WBS) presented in the case, I went through all the details about the project and tasks mentioned in the scenario and carefully took a look at them. In doing so, I created a list of project phases and then divided them into smaller tasks each. All the tasks of every phase were grouped clearly by phase to demonstrate an unbiased view of the project's overall scope and schedule. WBS develops a detailed and complete work schedule of the project's timeline and the expected outcome, which in turn allows the project manager to plan his/her activities. Risk Register for Future Technology Data Center Relocation Project: Contractor Delays Likelihood: Medium Impact: High Mitigation: Regular communication and monitoring of contractor progress.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help
4 Equipment Delivery Delays Likelihood: High Impact: Medium Mitigation: Ordering equipment well in advance, and exploring alternative suppliers. City Inspection Delay Likelihood: Low Impact: High Mitigation: Proactive scheduling and coordination with city authorities. Network Downtime Likelihood: Medium Impact: High Mitigation: Detailed contingency plan, thorough testing before shutdown. Technical Issues with Installation Likelihood: Medium Impact: Medium Mitigation: Training staff, hiring skilled technicians, and contingency plans. Description To elaborate risk register, I mainly considered all the risks which may arise due to not going well with the implementation of this project. I measured and ranked each risk in terms of its plausibility and the consequences arising from them, taking special care to consider challenges that may be derived from the project, having regard to external influencing factors.
5 The recoverable risk plan I proposed involved the mitigation of these risks to give the projected delivery time and tasks an accurate outlook. This tool is a tool of what we call proactive risk management, by which issues are identified and mitigated right from the beginning to consistently for the project period.