Assignment-2 1 Fanshawe College CONS- 6003- (20-21)-23F-Construction Project Management Fundamentals Assignment: Part I: Instructor: Hazar Sasila Student ID & Names: Anmol Tiwari 1173316 PROJECT: Construction method 2023, September 21 st
Assignment-2 2 1. List ICI project types in Canada with examples? Answer: ICI stands for Institutional Commercial and Industrial buildings in Canada examples of Institutional buildings are: Hospitals Libraries Religious buildings Government buildings Educational buildings Commercial: Shopping malls Theatres Plazas Resorts Hotels Offices Industrial: Production plants Factories Oil refineries 2. Fill the following missing words: a. Low rise building: 1-4 Floors b. Mid-size building: 5-12 Floors c. High rise building: 13 and more Floors 3. Bungalow house has Single/one storey/s 4. As an example of construction definition, fill the following words: a. Low rise building : The Process. b. Residential: The Industry. c. Steel structure with curtain wall : The method and materials. 5. What is CMAR in construction Answer: The construction sector uses the project delivery approach known as Construction Manager at Risk (CMAR). In CMAR, the construction manager collaborates with the owner and architect from the very beginning of the project's design phase. Construction managers are responsible for controlling construction risks and completing projects within a guaranteed maximum price (GMP). They offer cost estimates, timetables, and risk management.
Assignment-2 3 6. Can Canadian government perform 3P as construction method? Answer: Yes, the Canadian government is permitted to use 3P public-private partnerships for building. Typically, public infrastructure projects like roads, hospitals, and schools are financed, designed, built, and operated in collaboration between the government and private enterprises with duties and risks distributed equally. 7. DBB generally used on complicated projects? a. False 8. Integrated project delivery IPD when the owner selects a designer where this designer selects the construction manager prior to the kick-off of the project design. a. False 9. IPD is the best suited for project in private sector that are complex under tight schedule a. True 10. Give example of construction method PPP (not mentioned in the lecture)? Public-private partnerships (PPPs) are often employed in Canada for infrastructure development projects. The building of the Royal Alberta Museum in Edmonton, Alberta, serves as an illustration. To develop, construct, and run the museum, the government collaborated with private businesses. The government kept ownership, but the private sector was able to provide management and building experience. Through cooperation and risk- sharing, it sought to efficiently, on-time, and cost-effectively complete the project.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help