5.
Given the following project network, baseline, and status information, develop status
reports for periods 1–4 and complete the project summary graph (or a similar one).
Report the final SV, CV, CPI, and PCIB. Based on your data, what is your assessment of
the current status of the project? At completion?
46
60
2
3
-2
3
0
2
-2
0
0
-3
0
0
0
0
-3
0
0
0
0
-3
0
0
-3
6
6
2
14
12
12
6
30
12
8
3
0
3
38
8
6
3
6
0
50
0
-2
-1
-3
-1
-2
-2
-5
-1
-3
-2
-1
0
-1
-8
-1
-3
-2
-2
0
-2
0
-10
4
11
12
10
8
30
12
15
8
3
0
3
38
12
15
8
6
6
6
0
53
7.
The following data have been collected for a British health care IT project for two-week
reporting periods 2 through 12. Compute the SV, CV, SPI, and CPI for each period. Plot
the EV and the AC on the summary graph provided. Plot the SPI, CPI, and PCIB on
the index graph provided. (You may use your own graphs.) What is your assessment of
the project at the end of period 12?
Status Report: Ending Period 2
($00)
Task
% Complete
EV
AC
PV
CV
SV
1
50%
--
4
--
--
--
Cumulative Totals
--
4
--
--
--
Status Report: Ending Period 4
($00)
Task
% Complete
EV
AC
PV
CV
SV
1
Finished
--
10
--
--
--
Cumulative Totals
--
10
--
--
--
Status Report: Ending Period 6
($00)
Task
% Complete
EV
AC
PV
CV
SV
1
Finished
--
10
--
--
--
2
25%
--
15
--
--
--
3
33%
--
12
--
--
--
4
0%
--
0
--
--
--
Cumulative Totals
--
37
--
--
--
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Status Report: Ending Period 8
($00)
Task
% Complete
EV
AC
PV
CV
SV
1
Finished
--
10
--
--
--
2
30%
--
20
--
--
--
3
60%
--
25
--
--
--
4
0%
--
0
--
--
--
Cumulative Totals
--
55
--
--
--
Status Report: Ending Period 10
($00)
Task
% Complete
EV
AC
PV
CV
SV
1
Finished
--
10
--
--
--
2
60%
--
30
--
--
--
3
Finished
--
40
--
--
--
4
50%
--
20
--
--
--
5
0%
--
0
--
--
--
6
30%
--
24
--
--
--
Cumulative Totals
--
124
--
--
--
Status Report: Ending Period 12
($00)
Task
% Complete
EV
AC
PV
CV
SV
1
Finished
--
10
--
--
--
2
Finished
--
50
--
--
--
3
Finished
--
40
--
--
--
4
Finished
--
40
--
--
--
5
50%
--
30
--
--
--
6
50%
--
40
--
--
--
Cumulative Totals
--
210
--
--
--
Indexes
Perio
d
SPI
CPI
PCIB
2
--
--
--
4
--
--
--
SPI = EV / PV
6
--
--
--
CPI = EV / AC
8
--
--
--
PCIB = EV / BAC
10
--
--
--
12
--
--
--