Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
1/18
Mini PMP - Ch 6 - Project Activity and Risk Planning Due
Feb 25 at 11:59pm
Points
45
Questions
45
Available
until Feb 25 at 11:59pm
Time Limit
90 Minutes
This quiz was locked Feb 25 at 11:59pm.
Attempt History
Attempt
Time
Score
LATEST
Attempt 1
90 minutes
19 out of 45
Score for this quiz: 19
out of 45
Submitted Feb 25 at 10:01pm
This attempt took 90 minutes.
1 / 1 pts
Question 1
For projects that are constantly changing, the _____ methodology is
recommended.
Agile
Correct!
Correct!
orrect Answers
orrect Answers
agile 0 / 1 pts
Question 2
_____: The nominal plan for the entire project to which deviations will be
compared.
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
2/18
WBS
ou Answered
ou Answered
orrect Answers
orrect Answers
Project Plan 0 / 1 pts
Question 3
Unanswered
Unanswered
In a project charter, the _____ is a short summary directed to top
management and those unfamiliar with the project.
ou Answered
ou Answered
orrect Answers
orrect Answers
purpose 1 / 1 pts
Question 4
With regards to team member feedback, the characteristic of "open
communication encouraged by all team members" applies to which
approach?
Traditional waterfall approach Both approaches Neither approach Agile project management Correct!
Correct!
1 / 1 pts
Question 5
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
3/18
The success of the project launch meeting is dependent on the existence
of what?
The project's scope statement Project planning templates A well-defined set of objectives for the project Correct!
Correct!
A project charter 1 / 1 pts
Question 6
_____: Scrum artifact that contains a complete list of the requirements for
the product being developed or improved.
Product Backlog
Correct!
Correct!
orrect Answers
orrect Answers
Product Backlog 1 / 1 pts
Question 7
According to PMBOK, a proper project plan addresses the following issue:
Developing practices to manage the quality of the project deliverables.
True Correct!
Correct!
False
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
4/18
1 / 1 pts
Question 8
According to PMBOK, a proper project plan addresses the following issue:
Establishing the cost baseline for the project and developing a plan to
manage project costs.
True Correct!
Correct!
False 1 / 1 pts
Question 9
According to PMBOK, a proper project plan addresses the following issue:
Defining who will be the project sponsor.
True False Correct!
Correct!
0 / 1 pts
Question 10
In a project charter, the _____ contains a brief description of the
procedures to be followed in monitoring, collecting, storing, auditing, and
evaluating the project, as well as in the postproject evaluation following
project termination.
plan address
ou Answered
ou Answered
orrect Answers
orrect Answers
evaluation methods
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
5/18
1 / 1 pts
Question 11
According to PMBOK, a proper project plan addresses the following issue:
Developing a plan to raise funds to pay for the project.
True False Correct!
Correct!
0 / 1 pts
Question 12
With regards to experimentation, the characteristic of "discouraged so as
to meet project deadline and stay on budget" applies to which approach?
Neither approach Both approaches ou Answered
ou Answered
Traditional waterfall approach orrect Answer
orrect Answer
Agile project management 1 / 1 pts
Question 13
According to PMBOK, a proper project plan addresses the following issue:
Developing the WBS.
True Correct!
Correct!
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
6/18
False 1 / 1 pts
Question 14
According to PMBOK, a proper project plan addresses the following issue:
The process for hiring (and firing) project workers.
True False Correct!
Correct!
0 / 1 pts
Question 15
_____: Preplanned points during the project where progress is assessed
and the project cannot resume until re-authorization has been approved.
project charter
ou Answered
ou Answered
orrect Answers
orrect Answers
Phase-Gates 0 / 1 pts
Question 16
MTs stands for _____.
Make to Stock
ou Answered
ou Answered
orrect Answers
orrect Answers
multidisciplinary teams
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
7/18
0 / 1 pts
Question 17
_____: A scrum event held at beginning of each sprint that is attended by
the entire scrum team (product owner, scrum master, and developers).
Sprint planning
ou Answered
ou Answered
orrect Answers
orrect Answers
Sprint Planning Meeting 0 / 1 pts
Question 18
With regards to project execution, the characteristic of "work completed
based on comprehensive and highly structured plan" applies to which
approach?
Traditional waterfall approach orrect Answer
orrect Answer
Neither approach ou Answered
ou Answered
Agile project management Both approaches 1 / 1 pts
Question 19
With regards to work structure, the characteristic of "team members tend
to work independently and rely on project manager to coordinate tasks"
applies to which approach?
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
8/18
Traditional waterfall approach Correct!
Correct!
Neither approach Agile project management Both approaches 0 / 1 pts
Question 20
In a project charter, the _____ contains a statement of the general goals
of the project and a brief explanation of their relationship to the firm's
objectives.
WBS
ou Answered
ou Answered
orrect Answers
orrect Answers
purpose 1 / 1 pts
Question 21
Having key stakeholders involved early in the project tends to which of the
following?
To create more problems than it is worth Increased communication errors To create buy-in Correct!
Correct!
Increased project risk
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
9/18
0 / 1 pts
Question 22
With regards to team member feedback, the characteristic of "feedback
typically provided confidentially by project manager" applies to which
approach?
Traditional waterfall approach orrect Answer
orrect Answer
Both approaches Neither approach Agile project management ou Answered
ou Answered
1 / 1 pts
Question 23
The project sponsor generally takes responsibility for gathering the
necessary approvals and assuring that any changes incorporated into the
plan at higher levels are communicated to, and approved by, the units that
have already signed off on the plan.
True False Correct!
Correct!
0 / 1 pts
Question 24
With regards to priorities, the characteristic of "schedule is top priority
followed by scope and then team" applies to which approach?
Agile project management
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
10/18
Traditional waterfall approach orrect Answer
orrect Answer
Both approaches ou Answered
ou Answered
Neither approach 1 / 1 pts
Question 25
According to PMBOK, a proper project plan addresses the following issue:
Defining how project requirements will be managed.
True Correct!
Correct!
False 1 / 1 pts
Question 26
With regards to scope, the characteristic of "rigid" applies to which
approach?
Both approaches Neither approach Agile project management Traditional waterfall approach Correct!
Correct!
1 / 1 pts
Question 27
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
11/18
With regards to feedback on results, the characteristic of "at the end of
each iteration" applies to which approach?
Agile project management Correct!
Correct!
Both approaches Neither approach Traditional waterfall approach 1 / 1 pts
Question 28
With regards to process ownership, the characteristic of "the project
manager owns" applies to which approach?
Traditional waterfall approach Correct!
Correct!
Agile project management Neither approach Both approaches 1 / 1 pts
Question 29
There are 12 Agile Principles to guide the implementation of Agile Project
Management (APM). Which of the following is not one of those 12
principles?
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
12/18
Define all of the requirements up-front so that changes are minimized later
in the process.
Correct!
Correct!
Deliver working software frequently, from a couple of weeks to a couple of
months.
Business people and developers must work together daily throughout the
project.
Our highest priority is to satisfy the customer through early and continuous
delivery of valuable software.
0 / 1 pts
Question 30
With regards to process ownership, the characteristic of "the team owns"
applies to which approach?
Agile project management orrect Answer
orrect Answer
Both approaches Neither approach Traditional waterfall approach ou Answered
ou Answered
0 / 1 pts
Question 31
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
13/18
Agile IT project teams are typically _____ and located at _____ site/s.
small, a single site
ou Answered
ou Answered
orrect Answers
orrect Answers
small a single 0 / 1 pts
Question 32
Unanswered
Unanswered
_____: A pictorial representation of a product that shows how the
elements required to build a product fit together.
ou Answered
ou Answered
orrect Answers
orrect Answers
Gozinto Chart 0 / 1 pts
Question 33
Unanswered
Unanswered
The physical items to be delivered from a project are called _____.
ou Answered
ou Answered
orrect Answers
orrect Answers
deliverables 0 / 1 pts
Question 34
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
14/18
Planning a project should result in a number of outputs. Which of the
following is not one of those outcomes?
Basic areas of performance responsibility are accepted by the participants Any tentative delivery dates or budgets and their tolerances set by the
parent organization are clearly noted
ou Answered
ou Answered
Technical scope is established Every possible risk is identified and a contingency plan is developed orrect Answer
orrect Answer
0 / 1 pts
Question 35
Unanswered
Unanswered
In a project charter, the _____ provides a high-level description of the
project and its requirements.
ou Answered
ou Answered
orrect Answers
orrect Answers
overview 0 / 1 pts
Question 36
Unanswered
Unanswered
_____: A description of all the tasks to complete a project, organized by
some consistent perspective and containing a variety of information
needed for that perspective.
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
15/18
ou Answered
ou Answered
orrect Answers
orrect Answers
Work Breakdown Structure WBS 0 / 1 pts
Question 37
Unanswered
Unanswered
_____: A description of a task that defines all the work required to
accomplish it, including inputs and desired outputs.
ou Answered
ou Answered
orrect Answers
orrect Answers
Work Statement 0 / 1 pts
Question 38
In a project charter, the _____ has each major task is listed, with the
estimated time obtained from those who will do the work.
stockholder
ou Answered
ou Answered
orrect Answers
orrect Answers
schedule 0 / 1 pts
Question 39
Unanswered
Unanswered
_____: The set of physical elements required to build a product.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
16/18
ou Answered
ou Answered
orrect Answers
orrect Answers
Bill of Materials 0 / 1 pts
Question 40
There are 12 Agile Principles to guide the implementation of Agile Project
Management (APM). Which of the following is not one of those 12
principles?
At regular intervals, the team reflects on how to become more effective,
then tunes and adjusts its behavior accordingly.
ou Answered
ou Answered
The best architectures, requirements, and designs emerge from self-
organizing teams.
Continuous attention to technical excellence and good design enhances
agility.
Efficiency-the art of maximizing the amount of work that is accomplished in
a given period of time-is essential.
orrect Answer
orrect Answer
0 / 1 pts
Question 41
_____: Scrum artifact consisting of a subset of the product backlog to be
completed during the current sprint.
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
17/18
Sprint ou Answered
ou Answered
orrect Answers
orrect Answers
Sprint Backlog 0 / 1 pts
Question 42
Unanswered
Unanswered
In an agile project, teams are given several requirements but only deal
with one at a time, with each iteration being referred to as a _____.
ou Answered
ou Answered
orrect Answers
orrect Answers
sprint 0 / 1 pts
Question 43
When the project is to deliver a product/service to an outside client, the
project's scope cannot be altered without whose permission?
Client orrect Answer
orrect Answer
Project management ou Answered
ou Answered
Project Engineer Senior management 1 / 1 pts
Question 44
4/27/23, 10:10 PM
Mini PMP - Ch 6 - Project Activity and Risk Planning : MGMT641102-Global Project Management
https://njit.instructure.com/courses/27956/quizzes/88087?module_item_id=1002325
18/18
According to PMBOK, a proper project plan addresses the following issue:
Establishing the schedule baseline and developing a plan to manage the
project's schedule.
True Correct!
Correct!
False 0 / 1 pts
Question 45
The project plan must be designed in such a way that the project outcome
meets what?
Unauthorized requests for change in the project outcome The objectives of the parent organization orrect Answer
orrect Answer
Only the expressed warranties identified in the contract ou Answered
ou Answered
The requirements associated with scope creep Quiz Score: 19
out of 45
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help