University of Illinois Urbana Champaign Department of Civil and Environmental Engineering
CEE 422 Construction Cost Analysis
Assignment
Fall 2023
Assignment # 1 – Solution
Page | 1
Assignment # 1
(Rough Estimating and Cost Indexes)
"I pledge to uphold the CEE Honor Code.”
Mohammed Mujthaba Ajazul Haq
ulhaq3@illinois.edu
Q
1)
Exercise
1
(3
points)
Over 7 years ago your company built a restaurant in New London, Connecticut. It was completed
in 2016 with a total cost of $4,940,000. You were awarded a contract for a similar restaurant. (Almost same design) that you are building this year (2023) in Daytona Beach, Florida.
a) What is the estimated cost of the restaurant?
b) If in 2020 you had built a similar restaurant in Decatur, Illinois, what would have been the cost of it?
Solution
: -
a) DAYTONA BEACH, FLORIDA.
1)
Time adjustment using the Historical Cost Indexes INDEX New London, Connecticut: - 207.3
INDEX Daytona Beach, Florida: - 318.8
Cost in Year A = Cost in Year B X 𝐼𝑛𝑑𝑒𝑥
𝐴
𝐼𝑛𝑑𝑒𝑥 𝐵
I assumed the basic cost of restaurant of New London, Connecticut 2016 $4940000
= 4940000 = x X 207.3
318.8
= $7597067.035
2)
Location adjustment using the City Cost Indexes: City A Cost (Unknown) = City B Cost (Known) X 𝐶𝑖𝑡𝑦
𝐴
𝐼𝑛𝑑𝑒𝑥
𝐶𝑖𝑡𝑦 𝐵 𝐼𝑛𝑑𝑒𝑥
= x = 7597067.035 X 87.9
101.4
= $6585623.21
University of Illinois Urbana Champaign Department of Civil and Environmental Engineering
CEE 422 Construction Cost Analysis
Assignment
Fall 2023
Assignment # 1 – Solution
Page | 2
b) DECATUR, ILLINOIS
1)
Time adjustment using the Historical Cost Indexes INDEX New London, Connecticut: - 207.3
INDEX Decatur, Illinois: - 234.6
Cost in Year A = Cost in Year B X 𝐼𝑛𝑑𝑒𝑥
𝐴
𝐼𝑛𝑑𝑒𝑥 𝐵
= 4940000 = x X 207.3
234.6
= $5590564.399
2)
Location adjustment using the City Cost Indexes: City A Cost (Unknown) = City B Cost (Known) X 𝐶𝑖𝑡𝑦
𝐴
𝐼𝑛𝑑𝑒𝑥
𝐶𝑖𝑡𝑦 𝐵 𝐼𝑛𝑑𝑒𝑥
= x =5590564.399 X 101.2
101.4
= $5579537.645
University of Illinois Urbana Champaign Department of Civil and Environmental Engineering
CEE 422 Construction Cost Analysis
Assignment
Fall 2023
Assignment # 1 – Solution
Page | 3
Q
2) Exercise
2
(3
points)
You are doing a rough cost estimate for a warehouse. The estimated gross area of the warehouse
is 210,000 sf. You have historical cost data from similar previous projects (shown below). Based
on these data, what is your estimate for this warehouse? State which estimating method you have
used.
Project
Total Project Cost
Size (sf)
1
$46,478,500
223000
2
$13,609,300
96500
3
$23,087,100
100960
4
$12,107,360
65500
5
$38,645,500
176000
6
$31,266,510
193000
Solution
: -
Project
Total Project Cost
Size (sf)
Cost Per Square ft
1
$46,478,500
223000
$
208.42
2
$13,609,300
96500
$
141.03
Smallest Unit Cost
3
$23,087,100
100960
$
228.68
Largest Unit Cost
4
$12,107,360
65500
$
184.85
5
$38,645,500
176000
$
219.58
6
$31,266,510
193000
$
162.00
Formula: - UC = 𝑨+𝟒𝑩+𝑪
𝟔
UC = forecast unit cost of proposed project
A = minimum unit cost of previous projects
B = average unit cost of previous projects
C = maximum unit cost of previous projects
Average: - ∑ (Unit Cost)/total no of Projects
1144.56
=
6
= 190.7
UC = 𝟏𝟒𝟏.𝟎𝟑+𝟒(𝟏𝟗𝟎.𝟕𝟔)+𝟐𝟐𝟖.𝟔𝟖
𝟔
UC = 188.8
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
Engineering Management
arrow_forward
Construction-Management: i need the answer quickly,i need all the steps, clear and understandable handwriting, please.
arrow_forward
One-page resume that can be apply jobs for civil engineering after 3-4 years when you graduate in Civil Engineering
arrow_forward
Develop a CPM schedule using the information provided and making assumptions as needed identifying all major milestones, including general conditions and mobilizations and clean up. you may use ms project if wanted
Project duration 67 days
building an office building in a crowded area of a college
4 story building with glass and metal curtain wall /R/Conc frame
story height (LF) 24.00
Floor area (SF) 72000
no basement
building cost $11,439,000
Please assume any information needed.
arrow_forward
One-page resume that can be used when you apply for your dream jobs after 3-4 years when you graduate in Civil Engineering.
arrow_forward
OSHA Subject ( give sample answer ) 5 lines
arrow_forward
Part 1: Take-home and Viva activity related to topics covered in LO1.
|You work as a mechanical software engineer in a mechanical company which provides modelling and
design services for different types of mechanical applications. Your main tasks are to analyze and assess
different designs and obtain optimal solutions prior to any prototyping or manufacturing step. Your
direct manager assigned you to work on specific tasks for different running projects.
Project 1:
Simply supported beams are usually used in structures due to their high stability and performance in resisting
shear stress and bending moment, they are applied in variety of applications such as steel-frame used for
advertisement cars' chassis and bridges. Your role in a structure design company is to analyze and design the
bridge based on simply supported beam theory. Your manager asked you to calculate the distribution of shear
force, bending moment and stress đue to bending for bridge modeled as simply supported beam…
arrow_forward
(a)
Your construction company plans to be involved in a Design and Build (DB) project.
As a project manager of the company, you are responsible to give a briefing on the
design and build project stages to you. Explain the stages of the project for DB to your
project team members.
arrow_forward
Note: I don't have time.. Please kindly give me all answers otherwise leave it.. Help me?
Thank you
arrow_forward
Personal profile description for a currently civil eng student example?
arrow_forward
What are the practical constraint?
arrow_forward
Give an example of a computation showing
the length of service (duration) of a
replacement in BAC (Bids and Awards
Committee) ( Subject: Construction
Engineering Project Management)
arrow_forward
Using the same CPM diagram, what is the total project duration?
Immediate
Estimated
Activity
Activity Description
Predecessors
Duration
A
Excavate
2 weeks
Lay the foundation
Put up the rough wall
Put up the roof
Install the exterior plumbing
Install the interior plumbing
Put up the exterior siding
Do the exterior painting
B
A
4 weeks
C
10 weeks
D
C
6 weeks
4 weeks
5 weeks
7 weeks
9 weeks
7 weeks
8 weeks
4 weeks
E
C
F
E
G
D
E, G
Do the electrical work
F, I
Put up the wallboard
Install the flooring
Do the interior painting
Install the exterior fixtures
K
5 weeks
M
2 weeks
N
Install the interior fixtures
K, L
6 weeks
Total = 79 weeks
arrow_forward
pls answer ASAP
Why is safety management important? How will it affect the entire project construction? 10 points (Minimum of 100 words)
arrow_forward
What is Environmental Management System (EMS) in the construction industry?
arrow_forward
Concepts materials used for green building which freindly for disabled people? please include 3 examples list one by one if you can include picture will be very good.
arrow_forward
A chew – good restaurants, Inc. grew from a highly successful first restaurant made from two turn-of- the- century railroad cars . Similar restaurants followed and the décor, menus and operating procedures were standardized.
One of critical aspect of arrangement is design and construction of the restaurant itself. This job has broken into the set tasks or activities presented in the following table: Draw Gantt Chart, Calculate the total the minimum time of the project , Find the critical path
arrow_forward
Need help with this please!!
arrow_forward
Assessment
Take it to your limit. Mastery is a must. Economy counts. As a carpenter,
VOu have to learn every detail of your endeavour. Re-check your learning.
Activity 5: Matching Type
Directions: Read each statement in column A and match it with the choices in
column B. Write the letter of your answer on the activity sheet.
Column A
Column B
10. an organic substance that supports a tree
11. the term used to describe wood once it's no
longer a part of a living tree.
12.a sawn timber or processed timber ready to
p. reusability
q. wood
r. lumber
s. detailed drawing
use
t. once
u. twice
v. hardwood
w. softwood
x. dressed timber
13. a complete sketch of a plan
14.“Measure twice and cut
15. also known as rough timber
16.from broad-leaved tree
y. sawn timber
z. dressing
17. plane and smooth timber
18. from needle-leaved tree
10.the simplest way of fixing two pieces of timber
together
11.other term for timber
aa.nails
bb. timber
cc. measurement
12. a method used in making plans.
13. the…
arrow_forward
Describe the procedure for ensuring that all tools and equipment are available prior to undertaking the activity.
arrow_forward
|u AGREEN BUILDING DESIGN FOR A GOVERNMENT CENTER, AND BIBAK DORM"
STRENGTH
WEAKNESS
OPPORTUNITY
THREAT
REMARKS
arrow_forward
I need a quick solution within 15 minutes With my best wishesTon
arrow_forward
I need a quick solution within 15 minutes
arrow_forward
What are the major ITER buildings?
Select one:
A.Tokamak Building
B.Radio Frequency Building
C.Assembly Building
D.All of the above
arrow_forward
Draw manually a WBS for your assumed building project. Mention duration for each activity of your project and total completion time.
arrow_forward
urgent!
According to the information given in the table, draw the project (in a circle) and indicate it with
arrows. Please write legibly.
QUESTION 1: Draw the grid of this project using the activities in the table below.
Activity
A
B
с
D
סןחןדן
E
F
G
H
I
J
K
L
M
N
O
Previous Activity
B,C,D
ABCD
ABCD
F.G.I
A B C D
O.E.N
B,C,D
K
B,C,D
B,C,D
ABCD
arrow_forward
Write the five basic project planning steps when setting up a CPM Schedule?
arrow_forward
A contract to build a 2-storey residential building is awarded to you. A Notice to Proceed (NTP) is given to you in 7 days. List down at least 10 activities you are going to do to start the project on time and explain each relevant activity.
arrow_forward
Based on the following statement, select the System Request element.
This project has been initiated to access the attendance information in generating student attendance reports and reducing clerical work.
A.
Business Need
B.
Business Value
C.
Project Sponsor
D.
Business Requirement
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Architectural Drafting and Design (MindTap Course...
Civil Engineering
ISBN:9781285165738
Author:Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:Cengage Learning
Related Questions
- Develop a CPM schedule using the information provided and making assumptions as needed identifying all major milestones, including general conditions and mobilizations and clean up. you may use ms project if wanted Project duration 67 days building an office building in a crowded area of a college 4 story building with glass and metal curtain wall /R/Conc frame story height (LF) 24.00 Floor area (SF) 72000 no basement building cost $11,439,000 Please assume any information needed.arrow_forwardOne-page resume that can be used when you apply for your dream jobs after 3-4 years when you graduate in Civil Engineering.arrow_forwardOSHA Subject ( give sample answer ) 5 linesarrow_forward
- Part 1: Take-home and Viva activity related to topics covered in LO1. |You work as a mechanical software engineer in a mechanical company which provides modelling and design services for different types of mechanical applications. Your main tasks are to analyze and assess different designs and obtain optimal solutions prior to any prototyping or manufacturing step. Your direct manager assigned you to work on specific tasks for different running projects. Project 1: Simply supported beams are usually used in structures due to their high stability and performance in resisting shear stress and bending moment, they are applied in variety of applications such as steel-frame used for advertisement cars' chassis and bridges. Your role in a structure design company is to analyze and design the bridge based on simply supported beam theory. Your manager asked you to calculate the distribution of shear force, bending moment and stress đue to bending for bridge modeled as simply supported beam…arrow_forward(a) Your construction company plans to be involved in a Design and Build (DB) project. As a project manager of the company, you are responsible to give a briefing on the design and build project stages to you. Explain the stages of the project for DB to your project team members.arrow_forwardNote: I don't have time.. Please kindly give me all answers otherwise leave it.. Help me? Thank youarrow_forward
- Personal profile description for a currently civil eng student example?arrow_forwardWhat are the practical constraint?arrow_forwardGive an example of a computation showing the length of service (duration) of a replacement in BAC (Bids and Awards Committee) ( Subject: Construction Engineering Project Management)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Architectural Drafting and Design (MindTap Course...Civil EngineeringISBN:9781285165738Author:Alan Jefferis, David A. Madsen, David P. MadsenPublisher:Cengage Learning
Architectural Drafting and Design (MindTap Course...
Civil Engineering
ISBN:9781285165738
Author:Alan Jefferis, David A. Madsen, David P. Madsen
Publisher:Cengage Learning