Concept explainers
Concept introduction:
Variable
It is the difference between standard variable overhead rate and actual variable overhead rate and than multiplying with actual hours.
Variable overhead efficiency variances:
It is the difference between standard and actual hours, than multiplying with standard rate.
Variable overhead spending variances:
It is the combined value of the variable overhead rate variance and variable overhead efficiency variance.
Actual variable overhead:
It is calculated by multipling actual hourwith actual rate.
Applied variable overhead:
It is calculated by multipling standard hour with standard rate.
To compute:
The variable overhead rate and efficiency variances and its over or under applied variable overhead.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Managerial Accounting
- Kavallia Company set a standard cost for one item at 328,000; allowable deviation is 14,500. Actual costs for the past six months are as follows: Required: 1. Calculate the variance from standard for each month. Which months should be investigated? 2. What if the company uses a two-part rule for investigating variances? The allowable deviation is the lesser of 4 percent of the standard amount or 14,500. Now which months should be investigated?arrow_forwardFitzgerald Company manufactures sewing machines, and they produced 2,500 this past month. The standard variable manufacturing overhead (M0H) rate used by the company is $6.75 per machine hour. Each sewing machine requires 13.5 machine hours. Actual machine hours used last month were 33,500, and the actual variable MOH rate last month was $7.00. Calculate the variable overhead rate variance and the variable overhead efficiency variance.arrow_forwardA manufacturer planned to use $45 of variable overhead per unit produced, but in the most recent period, it actually used $47 of variable overhead per unit produced. During this same period, the company planned to produce 200 units but actually produced 220 units. What is the variable overhead spending variance?arrow_forward
- Case made 24,500 units during June, using 32,000 direct labor hours. They expected to use 31,450 hours per the standard cost card. Their employees were paid $15.75 per hour for the month of June. The standard cost card uses $15.50 as the standard hourly rate. A. Compute the direct labor rate and time variances for the month of June, and also calculate the total direct labor variance. B. If the standard rate per hour was $16.00, what would change?arrow_forwardMisterio Company uses a standard costing system. During the past quarter, the following variances were computed: Misterio applies variable overhead using a standard rate of 2 per direct labor hour allowed. Two direct labor hours are allowed per unit produced. (Only one type of product is manufactured.) During the quarter, Misterio used 30 percent more direct labor hours than should have been used. Required: 1. What were the actual direct labor hours worked? The total hours allowed? 2. What is the standard hourly rate for direct labor? The actual hourly rate? 3. How many actual units were produced?arrow_forwardThingOne Company has the following information available for the past year. They use machine hours to allocate overhead. What is the variable overhead efficiency variance?arrow_forward
- Direct materials and direct labor variance analysis Lenni Clothing Co. manufactures clothing in a small manufacturing facility. Manufacturing has 25 employees. Each employee presently provides 40 hours of productive labor per week. Information about a production week is as follows: Instructions Determine (A) the standard cost per unit for direct materials and direct labor; (B) the price variance, quantity variance, and total direct materials cost variance; and (C) the rate variance, time variance, and total direct labor cost variance.arrow_forwardDirect labor variances Bellingham Company produces a product that requires 4 standard direct labor hours per unit at a standard hourly rate of 20 per hour. If 15,000 units used 61,800 hours at an hourly rate of 1985 per hour, what is the direct labor (A) rate variance, (B) time variance, and (C) cost variance?arrow_forwardUse the following information to complete Brief Exercises 10-25 and 10-26: Tico Inc. produces plastic bottles. Each bottle has a standard labor requirement of 0.03 hour. During the month of April, 900,000 bottles were produced using 25,200 labor hours @ 15.00. The standard wage rate is 13.50 per hour. 10-26 Labor Rate and Efficiency Variances Refer to the information above for Tico Inc. on the previous page Required: Calculate the labor rate and efficiency variances using the columnar and formula approaches.arrow_forward
- Georgia Gasket Co. budgets 8,000 direct labor hours for the year. The total overhead budget is expected to amount to 20,000. The standard cost for a unit of the companys product estimates the variable overhead as follows: The actual data for the period follow: Using the four-variance method, calculate the overhead variances. (Hint: First compute the budgeted fixed overhead rate.)arrow_forwardThe normal capacity of a manufacturing plant is 30,000 direct labor hours or 20,000 units per month. Standard fixed costs are 6,000, and variable costs are 12,000. Data for two months follow: For each month, make a single journal entry to charge overhead to Work in Process, to close Factory Overhead, and to record variances. Indicate the types of variances and state whether each is favorable or unfavorable. (Hint: You must first compute the flexible-budget and production-volume variances.)arrow_forwardRefer to Cornerstone Exercise 8.13. In March, Nashler Company produced 163,200 units and had the following actual costs: Required: 1. Prepare a performance report for Nashler Company comparing actual costs with the flexible budget for actual units produced. 2. What if Nashler Companys actual direct materials cost were 1,175,040? How would that affect the variance for direct materials? The total cost variance?arrow_forward
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,