EBK FUNDAMENTALS OF GEOTECHNICAL ENGINE
EBK FUNDAMENTALS OF GEOTECHNICAL ENGINE
5th Edition
ISBN: 8220101425829
Author: SIVAKUGAN
Publisher: CENGAGE L
bartleby

Concept explainers

Question
Book Icon
Chapter 9, Problem 9.19CTP
To determine

Plot the consolidation settlement versus time for the clay layer.

Expert Solution & Answer
Check Mark

Explanation of Solution

Given information:

The thickness of the clay layer (H) is 6m.

The time (t) is 12months.

The final consolidation settlement (Sp) is 220mm.

The coefficient of consolidation of the clay (cv) is 3m2/year.

Calculation:

Consider the unit weight of water (γw) is 9.81kN/m3.

For the time (t) of 3months:

Calculate the maximum drainage path (Hdr) for two way drainage using the relation.

Hdr=H2

Substitute 6m for H.

Hdr=62=3m

Calculate the time factor (Tv) using the relation.

Tv=(cvtHdr2) (1)

Substitute 3m2/year for cv, 3months for t, and 3m for Hdr in Equation (1).

Tv=3m2/year×3months×1 year12months(3m)2=0.759=0.083

Refer Figure 9.33 “UTv relationships for ramp loading and instantaneous loading” in the Text Book.

Take the value of average degree of consolidation (U) as 21% for the value time factor (Tv) of 0.083.

Calculate the final consolidation settlement (Sp(f)) with 25% of the applied load using the relation.

Sp(f)=Percentageofloadapplied×Sp (2)

Substitute 25% for percentage of load applied and 220mm for Sp in Equation (2).

Sp(f)=25100×220=55mm

Calculate the consolidation settlement for 3months using the relation.

Consolidationsettlement=U×Sp(f) (3)

Substitute 21% for U and 55mm for Sp(f) in Equation (3).

Consolidationsettlement=21100×55=11.6mm

For the time (t) of 6months:

Calculate the time factor (Tv) as shown below.

Substitute 3.0m2/year for cv, 6months for t, and 3m for Hdr in Equation (1).

Tv=3m2/year×6months×1 year12months(3m)2=1.59=0.167

Refer Figure 9.33 “UTv relationships for ramp loading and instantaneous loading” in the Text Book.

Take the value of average degree of consolidation (U) as 31% for the value time factor (Tv) of 0.167.

Calculate the final consolidation settlement (Sp(f)) with 50% of the applied load as shown below.

Substitute 50% for percentage of load applied and 220mm for Sp in Equation (2).

Sp(f)=50100×220=110mm

Calculate the consolidation settlement for 6months using the relation.

Substitute 31% for U and 110mm for Sp in Equation (3).

Consolidationsettlement=31100×110=34.10mm

For the time (t) of 12months:

Calculate the time factor (Tv) as shown below.

Substitute 3.0m2/year for cv, 12months for t, and 3m for Hdr in Equation (1).

Tv=3m2/year×12months×1 year12months(3m)2=39=0.333

Refer Figure 9.33 “UTv relationships for ramp loading and instantaneous loading” in the Text Book.

Take the value of average degree of consolidation (U) as 43% for the value time factor (Tv) of 0.333.

Calculate the final consolidation settlement (Sp(f)) with 50% of the applied load as shown below.

Substitute 100% for percentage of load applied and 220mm for Sp in Equation (2).

Sp(f)=100100×220=220mm

Calculate the consolidation settlement for 12months using the relation.

Substitute 43% for U and 220mm for Sp in Equation (3).

Consolidationsettlement=43100×220=94.6mm

For the time (t) of 18months with t0 of 12months.

Calculate the time factor Tv using the relation.

Tv=cv(tt0)Hdr2 (4)

Substitute 3.0m2/year for cv, 18months for t,12months for t0,and 3m for Hdr in Equation (4).

Tv=3m2/year×(126)months×1 year12months(3m)2=1.59=0.167

Refer Table 9.5“ UTv Values for Non-Uniform Initial Pore Pressure Distributions” in the Text Book.

Take the value of Utt0 as 0.3377 for the value Tv of 0.167 for half-sine.

Calculate the average degree of consolidation (Ut) using the relation.

Ut=U0+(1U0)Utt0

Substitute 43% for U0 and 0.3377 for Utt0.

Ut=43100+(143100)×0.3377=0.43+0.1925=0.6225×100%=62.25%

Calculate the consolidation settlement for 18months using the relation.

Substitute 62.25% for U and 220mm for Sp in Equation (3).

Consolidationsettlement=62.25100×220=136.95mm

For the time (t) of 36months with t0 of 12months.

Calculate the time factor (Tv) as shown below.

Substitute 3.0m2/year for cv, 36months for t, 12months for t0, and 3m for Hdr in Equation (4).

Tv=3m2/year×(3612)months×1 year12months(3m)2=69=0.667

Refer Table 9.5 “ UTv Values for Non-Uniform Initial Pore Pressure Distributions” in the Text Book.

Take the value of Utt0 as 0.7725 for the value Tv of 0.600 for half-sine.

Take the value of Utt0 as 0.8222 for the value Tv of 0.700 for half-sine.

Calculate the value of Utt0 for the value Tv of 0.667 by interpolation as shown below.

0.7000.6670.7000.600=0.8222Utt00.82220.77250.33×0.0497=0.8222Utt00.0164=0.8222Utt0Utt0=0.806

Calculate the average degree of consolidation (Ut) using the relation.

Ut=U0+(1U0)Utt0

Substitute 43% for U0 and 0.806 for Utt0.

Ut=43100+(143100)0.806=0.43+0.4594=0.8894×100%=88.9%

Calculate the consolidation settlement for 36months using the relation.

Substitute 88.9% for U and 220mm for Sp in Equation (3).

Consolidationsettlement=88.9100×220=195.58mm

For the time (t) of 60months with t0 of 12months.

Calculate the time factor (Tv) as shown below.

Substitute 3.0m2/year for cv, 60months for t, 12months for t0, and 3m for Hdr in Equation (4).

Tv=3m2/year×(6012)months×1 year12months(3m)2=129.0=1.33

Refer Table 9.5 “ UTv Values for Non-Uniform Initial Pore Pressure Distributions” in the Text Book.

Take the value of Utt0 as 0.9152 for the value Tv of 1 for half-sine.

Take the value of Utt0 as 0.9753 for the value Tv of 1.5 for half-sine.

Calculate the value of Utt0 for the value Tv of 1.33 by interpolation as shown below.

1.51.331.51=0.9753Utt00.97530.91520.34×0.0601=0.9753Utt00.0204=0.9753Utt0Utt0=0.955

Calculate the average degree of consolidation (Ut) using the relation.

Ut=U0+(1U0)Utt0

Substitute 43% for U0 and 0.955for Utt0.

Ut=43100+(143100)0.955=0.43+0.5444=0.9744×100%=97.4%

Calculate the consolidation settlement for 60months using the relation.

Substitute 97.4% for U and 220mm for Sp in Equation (3).

Consolidationsettlement=97.4100×220=214.3mm

Show the values of time and consolidation settlement as in Table 1.

Time (months)Consolidation settlement (mm)
311.60
634.10
1294.60
18136.95
36195.58
60214.30

Table 1

Refer to Table 1.

Sketch the plot between consolidation settlement and time as in Figure 1.

EBK FUNDAMENTALS OF GEOTECHNICAL ENGINE, Chapter 9, Problem 9.19CTP

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A one-story building as shown in the plan, if the height of the concrete floor is 320 m, the width of the wall is 0.24 and the roof is made of reinforced concrete, the amount of iron for the roof is 100 kg m3 and there are downward depressions with a depth of 0.40 and a width of 0.25 along the wall and the amount of reinforcing iron is 89 kg m3 and there are 14 columns with dimensions of 0.500.30 and a height of 2.80, the amount of reinforcing iron is 120 kg m3 Find The amount of bricks used for construction The amount of mortar used for construction (cement + sand) -1 -2 The amount of plaster for the building from the inside is 2 cm thick (cement + sand) -3 Quantity of floor tiles for the room Quantity of concrete for the ceiling and beams. Ceiling thickness: 0.20 m. Total amount of reinforcing steel for the roof (tons) Quantity of reinforcing steel for columns (tons) Total amount of reinforcing steel for balls (tons) -4 -5 -6 -7 -8
K Course Code CE181303 Course Title Hours per week L-T-P Credit C Fluid Mechanics 3-1-0 MODULE 1: Fluid Properties: Fluid-definition, types; physical properties of fluid-density, specific weight, specific volume, specific gravity, viscosity- Newton's law of viscosity, surface tension, compressibility of fluids, capillarity. MODULE 2: Fluid Statics: Hydrostatic pressure, pressure height relationship, absolute and gauge pressure, measurement of pressure-manometer, pressure on submerged plane and curved surfaces, centre of pressure; buoyancy, equilibrium of floating bodies, metacentre; fluid mass subjected to accelerations. MODULE 3: Fluid Kinematics: Types of motion- steady and unsteady flow, uniform and no uniform flow, laminar and turbulent flow, and path lines, stream tube, stream function compressible and incompressible flow, one, two & three dimensional flow; stream lines, streak lines and velocity potential, flow net and its drawing: free and forced vortex. MODITE Q. A closed…
H.W: For the tank shown in figure below, Find The amount of salt in the tank at any time. Ans: x = 2(100+t) 1500000 (100 + t)² Qin = 3 L/min Cin = 2 N/L V = 100 L Xo=50N Qout = 2 L/min Cout? 33
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781305081550
Author:Braja M. Das
Publisher:Cengage Learning
Text book image
Principles of Geotechnical Engineering (MindTap C...
Civil Engineering
ISBN:9781305970939
Author:Braja M. Das, Khaled Sobhan
Publisher:Cengage Learning
Text book image
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Text book image
Fundamentals of Geotechnical Engineering (MindTap...
Civil Engineering
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning