Concept explainers
Introduction:
HC, the manager of the branch office of state department motor vechiles at city M, analyzed the driver’s license-renewal operations which involved accomplishment of several tasks which is shown in the table below.
HC found that the operations were perfomed by different clerks and in the same sequence. He found that the office can process 120 applications per hour. He also discovered that the works were unevenly distributed where checking applications for violations demanded more time and the clerks took shortcuts to match up their speed with other operations.
The manager also found that steps 1 to 4, the clerks were paid $12 per hour and step 5 was performed by photographer who was paid $16 per hour and the last step of performed by state for issuing temporary liscence which cost $18 per hour. The review showed that step 1 and step 6 cannot be changed and has to be performed in the same order. He was under high pressure to increase productivity and reduce cost. The data collected by HC was,
To suggest: A process to accommodate 120 applications per hour and determine the cost of new configuration.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description Time (hrs) Immediate Predecessor(s) A Find location; determine resource requirements 15 None B Requisition of lumber and sand 60 A C Dig and grade 100 A D Saw lumber into appropriate sizes 30 B E Position lumber in correct locations 20 D, C F Nail lumber together 5 E G Put sand in and under the equipment 25 F H Put dirt around the equipment 10 F I Put grass all over the garden, landscape, paint 35 G, H Refer to the legend Code Activity A Planning B Purchasing C Excavation D Sawing E…arrow_forwardThe Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been completed, activities B and C can be performed independently of each other; however, activity D can be started only if both activities B and C have been completed. Based on his inspection of the car, Jensen believes that the following time estimates (in days) are applicable: Activity Optimistic Most Probable Pessimistic A 3 4 8 B 3 4 5 C 5 7 9 D 4 5 12 Jensen estimates that the parts needed to restore the body will cost $4000…arrow_forwardThe Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been completed, activities B and C can be performed independently of each other; however, activity D can be started only if both activities B and C have been completed. Based on his inspection of the car, Jensen believes that the following time estimates (in days) are applicable: Activity Optimistic Most Probable Pessimistic A 3 4 8 B 3 4 5 C 5 7 9 D 4 5 12 Jensen estimates that the parts needed to restore the body will cost $4000…arrow_forward
- Define process management and discuss how it is vital in planning and managing projectsarrow_forwardUnder the ZY company’s current warehouse operation, warehouse clerk dispatch order-picking personnel to fill each order and have the goods moved to the warehouse shipping area. Because of the high labour costs and relatively low productivity of hand order-picking, management has decided to automate the warehouse operation by installing a computer-controlled order system, along with a conveyor system for moving goods from storage to the warehouse shipping area. ZY’s director of material management has been named the project manager in charge of automated warehouse system. After consulting with members of the engineering staff and warehouse management personnel, the director compiled a list of activities associated with the project. The optimistic, most likely, and pessimistic times (in weeks) have also been provided for each activity, as shown below. Activity A B C D E F G H I J K Description Determine equipment needs Obtained Vendor proposals Select Vendor Order system Design…arrow_forwardJamison Day Consultants has been entrusted with thetask of evaluating a business plan that has been divided into foursections—marketing, finance, operations, and human resources.Chris, Steve, Juana, and Rebecca form the evaluation team. Eachof them has expertise in a certain field and tends to finish thatsection faster. The estimated times taken by each team memberfor each section have been outlined in the table below. Furtherinformation states that each of these individuals is paid $60/hour.a) Assign each member to a different section such that JamisonConsultants’s overall cost is minimized.b) What is the total cost of these assignments?Times Taken by Team Members for Different Sections (minutes)MARKETING FINANCE OPERATIONS HRChris 80 120 125 140Steve 20 115 145 160Juana 40 100 85 45Rebecca 65 35 25 75arrow_forward
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A B C D E F G B A, D C E.F This exercise contains only parts b, c, and d b) The critical activities for the leadership training program development project are B-D-E-G c) The project length for the leadership training program development project 34 days d) Slack time for each of the activities is Activity A B Slack Time 15 7 1 10 5 6 12arrow_forwardBaha is a professional Chemical Engineer. He has been appointed as the department manager for an upcoming large chemical process plant that will be designed and constructed by the organization that he is currently attached to. Baha's responsibilities will include organizing the process unit staff and overseeing the project designers' sketch plans to ensure that the new plant will be designed safely, operable and maintainable. After the construction, he will then be responsible to start up the plant. From experience, Baha noted that a new type of valve sold by a newer supplier could be used in place of more common gate valves sold by established suppliers. In any case, the new valve was less expensive and often gave a tighter shut-off than the current gate valve used by his organization. Thus, Baha convinced the project designers to add more of these new valves to the design of the process unit. His decision improved safety because more flows could be shut off instantaneously in an…arrow_forward1. The activities involved in the construction of a certain project are given in Table 1. One resource type will be used during the contract. Determine minimum level of the resource required to complete the project. a) Draw the precedence network and perform the CPM calculations. b) Prepare the Bar chart, Resource load table and and resource histogram (for both Early start time and Late start time) c) Allocate the required resources, then level them so that the contractor does not use more than six laborers at any time. Preceded Duration Laborers by Activity |(Days) A B 7 4 C A 3 3 D А,В 5 3 E C,D 2 2.arrow_forward
- 1. The activities involved in the construction of a certain project are given in Table 1. One resource type will be used during the contract. Determine minimum level of the resource required to complete the project. a) Draw the precedence network and perform the CPM calculations. b) Prepare the Bar chart, Resource load table and and resource histogram (for both Early start time and Late start time) c) Allocate the required resources, then level them so that the contractor does not use more than six laborers at any time. Preceded Duration by Activity Laborers (Days) A 5 7 4 А D A,B 5 C,D 2 2. m3 3. 2. B.arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A- Time B- Code Description (hrs) Immediate Predecessor(s) C- A Find location; determine resource requirements 25 None Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes 55 A D- C 100 A E- 30 В E Position lumber in correct locations 20 D, C F- F Nail lumber together 10 E G- Put sand in and under the equipment Put dirt around the equipment G 25 F H F H- Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 20 40 60 80 100 120 140 160 180 200 220arrow_forwardTo complete an assembly line in a factory, the major steps and seven activities involved are shown in table below. These activities have been labeled "A" through "G" in the following table, which also shows their estimated completion times (in weeks) and immediate predecessors. (m is average time, a is best case, b is worst case) ACTIVITY A B C D E F G a 1 2 4 8 2 4 1 m 2 23 3 5 9 5 5 2 b 3 4 6 10 8 6 3 IMMEDIATE PREDECESSORS A B C, D B E a) Determine the critical path for the entire assembly factory as well as the expected completion time [You may use scratch paper to find the path then just type the critical path for the total project in the answer box] b) In addition, determine the earliest and latest start and finish times for all activities. c) What is the main difference between the standard CPM and the PERT method?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.