a)
To determine: The theoretical minimum number of workstations.
a)

Answer to Problem 23P
The theoretical minimum number of workstations is 5 workstations.
Explanation of Solution
Given information:
Task | Time (seconds) | Immediate predecessors |
A | 40 | - |
B | 30 | A |
C | 50 | A |
D | 40 | B |
E | 6 | B |
F | 25 | C |
G | 15 | C |
H | 20 | D, E |
I | 18 | F, G |
J | 30 | H, I |
Total | 274 |
- Output is 60 iStars / hour
Calculation of cycle time:
The requirement is to produce 60 iStars / hour. Hence, the cycle time for one iStar will be:
Formula to calculate theoretical minimum number of workstations:
Calculation of theoretical minimum number of workstations:
The theoretical minimum number of workstations is 5 workstations.
b)
To balance: The assembly line.
b)

Explanation of Solution
Precedence diagram:
List of most following tasks:
Tasks | Following tasks |
A | 9 |
B | 4 |
C | 4 |
D | 2 |
E | 2 |
F | 2 |
G | 2 |
H | 1 |
I | 1 |
J | 0 |
Assignment of different tasks to different workstations:
Workstation | Elligible tasks | Selected tasks | Task time (seconds) | Available cycle time (seconds) | Remarks |
1 | 60 | ||||
A | A | 40 | 20 | ||
B,C | 20 (Idle time) | Cycle time is less than task time | |||
2 | 60 | ||||
B, C | C | 7 | 50 | Tie broken randomnly | |
B, F, G | 10 (Idle time) | Cycle time is less than task time | |||
3 | 60 | ||||
B, F, G | B | 30 | 30 | Task B has most following tasks. | |
D, E, F, G | F | 25 | 24 | Tie broken randomnly | |
D, E, G | 1 (Idle time) | Cycle time is less than task time | |||
4 | 60 | ||||
D, E, G | D | 40 | 20 | Tie broken randomnly | |
E, G | G | 15 | 5 | Tie broken randomnly | |
E,I | 5 (Idle time) | Cycle time is less than task time | |||
5 | 60 | ||||
E, I | E | 6 | 54 | Task E has most following tasks. | |
I, H | H | 20 | 34 | Tie broken randomnly | |
I | I | 18 | 2 | Task I is only elligible task | |
2 (Idle time) | |||||
6 | 60 | ||||
J | J | 30 | 30 | Task J is the remaining task | |
30 (Idle time) |
Workstation | Task assigned | Idle time |
1 | A | 20 |
2 | C | 10 |
3 | B, F | 1 |
4 | D, G | 5 |
5 | E, H, I | 2 |
6 | J | 30 |
Total | 68 |
c)
To determine: The actual number of workstations.
c)

Answer to Problem 23P
The actual number of workstations is 6.
Explanation of Solution
Workstation | Task assigned | Idle time |
1 | A | 20 |
2 | C | 10 |
3 | B, F | 1 |
4 | D, G | 5 |
5 | E, H, I | 2 |
6 | J | 30 |
Total | 68 |
The actual number of workstations is 6.
d)
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
d)

Answer to Problem 23P
The efficiency is 76.11%.
Explanation of Solution
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 76.11%.
Want to see more full solutions like this?
Chapter 9 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardPepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardThe deaths are included in the discharges; this includes deaths occurring in less than 48 hours and postoperative deaths. Rehabilitation had 362 discharges, 22 deaths, 1<48 hours, 0 Postoperative. what is the gross death rate for the rehabilitation service?arrow_forward
- A copy machine is available 24 hours a day. On a typical day, the machine produces 100 jobs. Each job takes about 3 minutes on the machine, 2 minutes of which is processing time and 1 minute is setup time (logging in, defining the job). About 20 percent of the jobs need to be reworked, in which case the setup time and the processing time have to be repeated. The remainder of the time, the equipment is idle. What is the OEE of the equipment?arrow_forwardHow do you think we can keep updating Toyota's ideas as new technologies come out and what customers want keeps changing?arrow_forwardGiven how TPS has helped change things in so many fields, do you think there are parts of it that might be hard to use in areas that aren’t about making things, like in healthcare or services? If so, why do you think that might be?arrow_forward
- Do you feel there is anything positive about rework?arrow_forwardDo you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forwardIn your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forward
- Have you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forwardResearch a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forwardSetup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing