PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
11th Edition
ISBN: 9780135226742
Author: HEIZER
Publisher: PEARSON
Question
Book Icon
Chapter 9, Problem 20P

a)

Summary Introduction

To draw: The precedence diagram.

a)

Expert Solution
Check Mark

Answer to Problem 20P

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 9, Problem 20P , additional homework tip  1

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 3 -
B 6 -
C 7 A
D 5 A, B
E 2 B
F 4 C
G 5 F
H 7 D, E
I 1 H
J 6 E
K 4 G, I, J
Total 50  
  • Number of hours / day is 24
  • Output is 96 instruments / day.

Precedence diagram:

PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB, Chapter 9, Problem 20P , additional homework tip  2

b)

Summary Introduction

To determine: The cycle time.

Introduction:

Cycle time:

Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.

b)

Expert Solution
Check Mark

Answer to Problem 20P

The  cycle time is 15 minutes / unit.

Explanation of Solution

Formula to calculate cycle time:

Cycle time=Number of hours per dayDaily production× Number of minutes / hour

Calculation of cycle time:

Cycle time=2496×60=1,44096=15 minutes / unit

The  cycle time is 15 minutes / unit.

c)

Summary Introduction

To determine: The production rate.

c)

Expert Solution
Check Mark

Answer to Problem 20P

The  production rate is 144 units / day.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Formula to calculate production rate:

Cycle time=Number of hours per dayCycle time× Number of minutes / hour

Calculation of cycle time:

Cycle time=2410×60=1,44010=144 units / day

The  production rate is 144 units / day.

d)

Summary Introduction

To determine: The theoretical minimum number of workstations.

d)

Expert Solution
Check Mark

Answer to Problem 20P

The theoretical minimum number of workstations is 5 workstations.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Formula to calculate theoretical minimum number of workstations:

Workstations=Total task timeCycle time

Calculation of theoretical minimum number of workstations:

Workstations=5010=5 workstations

The theoretical minimum number of workstations is 5 workstations.

e)

Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

e)

Expert Solution
Check Mark

Answer to Problem 20P

The efficiency is 83.3%.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Number of workstations = 6

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=506×10×100=50060=83.3%

The efficiency is 83.3%.

f)

Summary Introduction

To determine: The total idle time per cycle.

f)

Expert Solution
Check Mark

Answer to Problem 20P

The  idle time is 10 minutes / cycle.

Explanation of Solution

Given information:

Number of workstations = 6

Cycle time = 10

Calculation of total idle time per cycle:

Total idle time=(Number of workstations×Cycle time)-Total task time=(6×10)-50=60-50=10 minutes / cycle

The  total idle time is 10 minutes / cycle.

g)

Summary Introduction

To assign: The different tasks to different workstations and identify the efficiency.

g)

Expert Solution
Check Mark

Explanation of Solution

Assignment of different tasks to different workstations:

Workstation Elligible tasks Selected tasks Task time (minutes) Available cycle time (minutes)
1 10
A, B A 3 7
B B 6 1
1 (Idle time)
2 10
C, D, E C 7 3
3 (Idle time)
3 10
D, E, F D 5 5
E, F E 2 3
3 (Idle time)
4 10
F, G, H, I F 4 6
G, H, I G 5 1
1 (Idle time)
5 10
J, H, I, K H 7 3
H, I, K I 1 2
2 (Idle time)
6 10
K, J J 6 4
K K 4 0
Workstation Task assigned Idle time
1 A, B 1
2 C, D 3
3 D, E 3
4 F, G 1
5 H, I 2
6 J, K 0
Total 10

Efficiency:

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=506×10×100=50060=83.3%

The efficiency is 83.3%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Question 3 i. Using the Center of Gravity method, determine the optimal location (X, Y) for the new distribution center. [7 marks] [TOTAL 25 MARKS] Time (sec.) Power steering assembly firm wants to set up an assembly line which must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 2: Table 1 Work Element Immediate Predecessor(s) A 30 NONE B 26 A C 50 A D 44 B E 10 с F 20 с G 15 D.E H 30 E,G,F Required: a. Draw the precedence diagram showing the task precedence and their times b. Determine the cycle time associated with the rate of output required. [3 marks] c. What is the theoretical number of work stations required to satisfy this output rate? [3 marks] [4 marks] d. Allocate the tasks to work stations taking into consideration the precedence requirements and using the LOT rule to break ties between feasible tasks. e. Calculate the total idle time [8 marks] [3 marks] f. What is the efficiency of the line and the…
Question 2 MGMT2026 Production and Operations Management Semester II 2024-2025 a. Aman ltd. desires to locate a new facility. Based on preliminary analysis, the choice has been reduced to four locations: A, B, C, and D. These four locations were rated on a scale from 1 (worst) to 10 (best) on each of four criteria. Each criterion was also weighted to indicate its importance (i.e., the higher the weight, the more important). The list of ratings and weights follows in the Table 2 below: Table 2 Factor Score Evaluation by Location Criterion Weights A B с D Wages 25 4 5 3 4 Government Policies 30 8 7 6 5 Unionisation Weather 15 6 4 3 2 30 3 4 6 5 i. Based on weighted scores, where should Acme locate its new facility? [6 marks] b. An operations manager has narrowed down the search for a new factory to three locations. The fixed and variable costs associated with each location is given in the table below. i. Table 3 Location Fixed Cost Variable Cost A $100,000 $10 B $150,000 $7 с $200,000 $5…
The University of the West Indies GLOBAL CAMPUS MGMT 2026 Production and Operations Management - Problem Sheet Assignment Semester II 2024/2025 Note: Although this assignment is being currently assessed out of 100 marks it would be prorated to Contribute a maximum of 40% towards your final course marks. M&H company ltd. sells television sets and has collected monthly sales data (in units) for the past 12 months as shown in table 1below: TABLE 1 Month Sales (Units) 1 120 2 135 3 150 165 5 180 200 7 195 8 210 225 10 240 11 255 12 270 This Assignment is comprised of four (4) Questions - All questions must be attempted Using the data provided, answer the following questions: a. Using a 3-month weighted moving average with weights 0.5, 0.3, and 0.2 (most recent month having the highest weight), calculate the forecast for month 13. [2 marks] Screens 5-7 of 7
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
  • Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
    Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College