a)
To draw: The precedence diagram.
a)
Answer to Problem 20P
Explanation of Solution
Given information:
Task | Time (minutes) | Immediate predecessors |
A | 3 | - |
B | 6 | - |
C | 7 | A |
D | 5 | A, B |
E | 2 | B |
F | 4 | C |
G | 5 | F |
H | 7 | D, E |
I | 1 | H |
J | 6 | E |
K | 4 | G, I, J |
Total | 50 |
- Number of hours / day is 24
- Output is 96 instruments / day.
Precedence diagram:
b)
To determine: The cycle time.
Introduction:
Cycle time:
Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.
b)
Answer to Problem 20P
The cycle time is 15 minutes / unit.
Explanation of Solution
Formula to calculate cycle time:
Calculation of cycle time:
The cycle time is 15 minutes / unit.
c)
To determine: The production rate.
c)
Answer to Problem 20P
The production rate is 144 units / day.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Formula to calculate production rate:
Calculation of cycle time:
The production rate is 144 units / day.
d)
To determine: The theoretical minimum number of workstations.
d)
Answer to Problem 20P
The theoretical minimum number of workstations is 5 workstations.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Formula to calculate theoretical minimum number of workstations:
Calculation of theoretical minimum number of workstations:
The theoretical minimum number of workstations is 5 workstations.
e)
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
e)
Answer to Problem 20P
The efficiency is 83.3%.
Explanation of Solution
Given information:
Cycle time = 10 minutes
Number of workstations = 6
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 83.3%.
f)
To determine: The total idle time per cycle.
f)
Answer to Problem 20P
The idle time is 10 minutes / cycle.
Explanation of Solution
Given information:
Number of workstations = 6
Cycle time = 10
Calculation of total idle time per cycle:
The total idle time is 10 minutes / cycle.
g)
To assign: The different tasks to different workstations and identify the efficiency.
g)
Explanation of Solution
Assignment of different tasks to different workstations:
Workstation | Elligible tasks | Selected tasks | Task time (minutes) | Available cycle time (minutes) |
1 | 10 | |||
A, B | A | 3 | 7 | |
B | B | 6 | 1 | |
1 (Idle time) | ||||
2 | 10 | |||
C, D, E | C | 7 | 3 | |
3 (Idle time) | ||||
3 | 10 | |||
D, E, F | D | 5 | 5 | |
E, F | E | 2 | 3 | |
3 (Idle time) | ||||
4 | 10 | |||
F, G, H, I | F | 4 | 6 | |
G, H, I | G | 5 | 1 | |
1 (Idle time) | ||||
5 | 10 | |||
J, H, I, K | H | 7 | 3 | |
H, I, K | I | 1 | 2 | |
2 (Idle time) | ||||
6 | 10 | |||
K, J | J | 6 | 4 | |
K | K | 4 | 0 |
Workstation | Task assigned | Idle time |
1 | A, B | 1 |
2 | C, D | 3 |
3 | D, E | 3 |
4 | F, G | 1 |
5 | H, I | 2 |
6 | J, K | 0 |
Total | 10 |
Efficiency:
Formula to calculate efficiency:
Calculation of efficiency:
The efficiency is 83.3%.
Want to see more full solutions like this?
Chapter 9 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- SITUATION: A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production run, at the cost of $300. Inventory holding costs will be $10 a year. QUESTION: Suppose the manager decides to increase the run size of the new product. How many additional units would be needed just to accommodate the other job? How much will that increase the total annual cost?arrow_forwardpart Darrow_forward.A paced assembly line has been devised to manufacture calculators, as the following data show: Station S1 S2 S3 S4 S5 S6 Work Element Assigned A D, E с B, F, G H, I, J K Work Element Time (min) 2.7 0.6, 0.9 3.0 0.7, 0.7, 0.9 0.7, 0.3, 1.2 2.4 . What is the maximum hourly output rate from this line? (Hint: The line can go only as fast as its slowest workstation.) ». What cycle time corresponds to this maximum output rate? c. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each 10-hour shift? H. What is the line's efficiency?arrow_forward
- The following tasks are to be performed on an assembly line: TASK ABCDEFGH SECONDS 30 Cycle time 16 21 15 17 14 20 9 Number of workstations. TASKS THAT MUST PRECEDE The workday is 8 hours long. Demand for completed product is 900 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) 51.0 seconds per unit Work Station A B b. What is the theoretical number of workstations required to meet the desired output rate? (Round up yo number.) Task C D E, F d. Balance the line using sequential restrictions and the longest-operating-time rule. (Leave no cells blar wherever required. Round your answers to 1 decimal place.) Idle Timearrow_forwardAccording to Appendix E, the answer is 80 units/hour. How? .arrow_forwardDr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly line balancing. She has been told that the firm needs to complete 96 instruments per 24-hour day. The assembly-line tasks for the production of the instrument are: Task Time (minutes) Predecessors A 3 ---- B 6 ---- C 7 A D 5 A, B E 2 B F 4 C G 5 F H 7 D, E I 1 H J 6 E K 4 G, I, J Draw the precedence diagram If the daily production (24-hour) production rate is 96 units, what is the highest allowable cycle time? If the cycle time after allowances is given as 12 minutes, what is the daily (24-hour) production rate? With a 12-minute cycle time, what is the theoretical minimum number of stations with which the line can be balanced? Assign task to workstations. Use the following decision rules (heuristics): longest task first, break ties by assigning the task with the most followers. What are the efficiency and the balance delay of the assembly line? Show detil of…arrow_forward
- An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times: TASK PRECEDINGTASKS PERFORMANCE TIME (SECONDS) TASK PRECEDINGTASKS PERFORMANCETIME (SECONDS) a — 48 g d 43 b — 58 h e 38 c — 73 i f 23 d a 63 j g 33 e b 88 k h, i 53 f c 23 l j, k 67 A) What is the efficiency of your line balance? B) Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 13 hours per day in regular time. (Round your answers to the nearest whole number.)arrow_forward5. Make a check sheet and then a Pareto diagram for the following car repair shop data: Ticket No. Work Ticket No. Work Ticket No. Work Tires 11 Brakes 21 Lube & oil Lube & oil 12 Lube & oil 22 Brakes Tires 13 Battery 23 Transmission 14 Lube & oil 24 Brakes 4. Battery 15 Lube & oil 25 Lube & oil Lube & oil 16 Tires 26 Battery Lube & oil 17 Lube & oil 27 Lube & oil Lube & oil 28 Battery 18 Brakes Brakes 29 Brakes 19 Tires Lube & oil 30 Tires 20 Brakes 10 Tiresarrow_forwardThe Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Task A BCDEF C Performance Time (seconds) 22 30 12 15 12 27 Predecessors A A A B, C D, E This exercise only contains part a. a) The correct precedence diagram for the assembly line is presented in C Fig. 1 Fig. 2 Fig. 3 B Earrow_forward
- sniparrow_forwardUse the process flow diagram below for an assembly line. Station C Station A Station B Station D Daily capacity of 120 units/24 Hourly capacity: Processing time: 10 minutes/unit Hourly capacity: 8 units 10 units hours 1) Find the bottleneck of the process. 2) How many items can the assembly line produce for one hour?arrow_forwardA manufacturing plant has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three one of the three assembly operations (the assembly operations are ‘parallel’). Use diagram titled "q3" attached as an image a) What is the bottleneck operation? b) What is the throughput time for the overall system? c) If the firm operates 10 hours a day, 21 days a month, what is the monthly and yearly capacity of the manufacturing process? d) Supposed that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new bottleneck time of the system? e) What is the new throughput time if the second drilling machine is added? f) What is the new hourly capacity if the second drilling machine is added?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.