
Concept explainers
Interpretation: The performance according to sequencing rules FCFS, SPT, EDD and CR in relation to minimizing average tardiness has to be evaluated.
Concept Introduction:
Optimal sequence: It is supposed to be sequence or series of jobs that has to take place to minimize the idle time and at the same time all the jobs are completed.

Answer to Problem 30AP
When all the 4 sequencing rules are compared, it is found that FCFS rule gives minimum value of average tardiness while CR rule give the highest value of average tardiness. The values given by SPD and EDD rules are less than values provided by CR rule and more than value given by FCFS rule.
Explanation of Solution
Given information:
The information given to us is as follows:
Cars | Repair time (days) | Promised date |
1 | 3 | 5 |
2 | 2 | 6 |
3 | 1 | 9 |
4 | 4 | 11 |
5 | 5 | 8 |
Let us know calculate the mean flow time and average tardiness.
An important fact to be kept in mind is that in a situation where the due time is greater than the completion time, the tardiness should be considered as 0.
Calculation of average tardiness and number of tardy jobs using FCFS rule:
FCFS rule states that the person or job coming first will be attended first.
Cars | Repair time (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
1 | 3 |
| 5 | 0 |
2 | 2 |
| 6 | 0 |
3 | 1 |
| 9 | 0 |
4 | 4 |
| 11 | 0 |
5 | 5 |
| 8 | 7 |
Total |
| 7 |
Completion time is calculated by considering the cumulative of repair time values.
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to FCFS rule of sequencing is 1.4 days and the total number of tardy jobs is 1.
Calculation of average tardiness and number of tardy jobs using SPT rule:
SPT when expanded becomes shortest processing time. In the rule, the jobs must be arranged in increasing order according to the processing time.
Cars | Repair time (days) | Ranking done in increasing order |
(1) | (2) | (3) |
1 | 3 | 3 |
2 | 2 | 2 |
3 | 1 | 1 |
4 | 4 | 4 |
5 | 5 | 5 |
Total |
After arranging the repair time in increasing order, the corresponding values in the Car column have to be considered for further calculations.
Cars | Repair time after ranking (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
3 | 1 |
| 9 | 0 |
2 | 2 |
| 6 | 0 |
1 | 3 |
| 5 | 1 |
4 | 4 |
| 11 | 0 |
5 | 5 |
| 8 | 7 |
Total | 35 | 8 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to SPT rule of sequencing is 1.6 days and the total number of tardy jobs is 2.
Calculation of average tardiness and number of tardy jobs using EDD rule:
EDD when expanded becomes Earliest due date. In the rule, the jobs must be arranged in increasing order according to the promised time.
Cars | Repair time (days) | Promised date | Ranking of promised date done in increasing order |
1 | 3 | 5 | 1 |
2 | 2 | 6 | 2 |
3 | 1 | 9 | 4 |
4 | 4 | 11 | 5 |
5 | 5 | 8 | 3 |
After arranging the repair time in increasing order, the corresponding values in the Car column have to be considered for further calculations.
Cars (corresponding values according to ranks) | Repair time (days)
(corresponding values according to ranks) | Completion time | Promised date after ranking | Tardiness |
(1) | (2) | (3) | (4) |
|
1 | 3 |
| 5 | 0 |
2 | 5 |
| 6 | 0 |
5 | 5 |
| 8 | 2 |
3 | 1 |
| 9 | 2 |
4 | 4 |
| 11 | 4 |
Total | 44 | 8 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to EDD rule of sequencing is 1.6 days and the total number of tardy jobs is 3.
Finally, let us calculate the average tardiness and total number of tardy jobs according to CR rule.
CR when expanded becomes Critical Ratio. The formula to be used is as follows:
Let us that the current time is 0.
Cars | Repair time (days) | Promised date | Critical ratio |
1 | 3 | 5 |
|
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
5 | 5 | 8 |
|
Hence, the job having a minimum critical ration should be considered first. In our case, the car 5 has the minimum critical ratio of 1.6. So, it should be considered first for repair. After repair, car 5 can be ignored for further calculations.
Now, the current time for next critical ratio can be calculated as below:
Using this new current time, the critical ratio can be calculated for the rest of the cars.
Cars | Repair time (days) | Promised date | Critical ratio |
1 | 3 | 5 |
|
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, the minimum critical ratio is 0 of Car 1. Hence car 1 should be considered for repair.
Further, a new current time has to be calculated.
By considering this value, we have to now calculate the critical ratio for the remaining 3 cars.
Cars | Repair time (days) | Promised date | Critical ratio |
2 | 2 | 6 |
|
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, car 2 has minimum critical ratio of -1. So, it has to be repaired after car1.
Further, a new current time has to be calculated for the remaining 2 cars
By considering this value, we have to now calculate the critical ratio for the remaining 3 cars.
Cars | Repair time (days) | Promised date | Critical ratio |
3 | 1 | 9 |
|
4 | 4 | 11 |
|
Hence, car 3 has minimum critical ratio of -1. So, it has to be repaired after car 2 and the remaining job i.e., repair of car 4 should be done last.
Therefore, the sequence we get using Critical ratio rule is
After deriving the sequence, we have to calculate the completion time and tardiness.
Calculation of completion time and tardiness:
Cars | Repair time (days) | Completion time | Promised date | Tardiness |
(1) | (2) | (3) | (4) |
|
5 | 5 |
| 8 | 0 |
1 | 3 |
| 5 | 3 |
2 | 2 |
| 6 | 4 |
3 | 1 |
| 9 | 2 |
4 | 4 |
| 11 | 4 |
Total | 49 | 13 |
Since, we have derived the tardiness value; let us now calculate the average tardiness.
Calculation of Average Tardiness:
Therefore, the average tardiness according to CR rule of sequencing is 2.6 days and the total number of tardy jobs is 4.
When all the 4 sequencing rules are compared, we find that FCFS rule gives minimum value of average tardiness while CR rule give the highest value of average tardiness. The values given by SPD and EDD rules are less than values provided by CR rule and more than value given by FCFS rule.
Want to see more full solutions like this?
Chapter 9 Solutions
EBK PRODUCTION AND OPERATIONS ANALYSIS
- 1) View the video Alton Bridge (12.16 mins, Ctrl + Click on the link), and please answer the following questions: https://meida.gaspar.mheducation.com/GASPARPlayer/play.html?id=24qHEm8aNZExFciJtZQbqli a) According to the video, what are the various steps involved in managing projects? b) What were the different phases of the Alton Bridge project? c) What are the two widely used scheduling techniques, and under what phase of the Alton Bridge project are they discussed? Note: As a rough guideline, please try to keep the written submission to a paragraph or so for each of the questions. 2) The following is a table of activities associated with a mining project at Lunar Industries, their durations, and what activities each must precede: Activity Duration (weeks) Precedes A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 - The AOM project diagram is as given below: a) What is the critical path (list all activities in the…arrow_forward1) View the video Alton Bridge (12.16 mins, Ctrl + Click on the link), and please answer the following questions: a) According to the video, what are the various steps involved in managing projects? b) What were the different phases of the Alton Bridge project? c) What are the two widely used scheduling techniques, and under what phase of the Alton Bridge project are they discussed? Note: As a rough guideline, please try to keep the written submission to a paragraph or so for each of the questions. 2) The following is a table of activities associated with a mining project at Lunar Industries, their durations, and what activities each must precede: Activity Duration (weeks) Precedes A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 - The AOM project diagram is as given below:arrow_forwardWith all the problems companies are currently facing, why do so many choose to expand into international markets? What are the advantages of expanding beyond the domestic market?arrow_forward
- Perform resource leveling. Assume that each task can be performed independently of the other tasks.arrow_forwardher psychological test and interview while Ms. Domingo got a good score and good psychological result. Ms. Sabado’s father is your godfather and a good friend of yours. Ms. Sabado asked you a favor to consider her daughter and if possible she will be hired. He also added that every job can be learned through training and mentoring. The situation bothers you since it’s your duty to recommend to the higher authority whom to hire.Questions:1. As a supervisor how will you diced on this situation?2. It’s time to decide, who among the two (2) will be hired? Why?arrow_forwardHelp me solve part C.arrow_forward
- Boreki Enterprise has the following 10 items in inventory. Theodore Boreki asks you, a recent OM graduate, to divide these items into ABC classifications. Fill in the blanks and then answer the following questions. (Round dollar volume to the nearest whole number and percentage of dollar volume to two decimal places.) Dollar Item Annual Demand Cost/Unit Volume % of Total Dollar Volume A2 10 120 B8 4000 12 48,000 5.65 C7 1500 45 67,500 7.94 D1 2000 44 E9 1000 20 20,000 2.35 F3 25 40 G2 200 1500 300,000 35.29 H2 600 20 12,000 1.41 15 1000 300 J8 2500 5 12,500 1.47arrow_forwardBobby Flay is responsible for assigning steel workers to a structural steel infrastructure construction task. Having taken Project Management at the University of Portland, he understands the importance of managing risk. To ensure that the task takes place as scheduled, Bobby must ensure that there are at least 8 steel workers available at the start of the task. Based on analysis of similar tasks, he estimates that steel workers will show up for the task with probability 0.9. If Bobby wants to be 97% sure that there are enough tasks to begin as scheduled, he should assign ______ steel workers to the task.arrow_forwardMarcela Valladolid needs to assign resources to a task on a new high-tech development project at Jonathon's Pool Supplies. According to her estimates, the task's work content (in hours) is 408. Marcela needs help in determining an appropriate number of resources to allocate to the task. Marcela read somewhere that, when it comes to project staffing, more is not always better. Assuming that the direct labor rate per hour is $93, the indirect and over head rate per unit time is $73.62, assigned resources are dedicated to the task full time, and that 0.02 hours of communication per coordination are required per link per hour worked, help Marcela by determining the following: What is the minimum total cost: What resource allocation minimizes the total cost: What is the minimum duration: What is the duration minimizing number of resources: If Marcela assigns 12 FTEs to the task, the task metrics would be: Total Cost: Total Duration: Note: enter durations to 1 decimal place and costs…arrow_forward
- 1 point) Market Fresh Foods is looking to develop a new strategic plan. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, normal task durations, and resource requirements. Guillermo has studied project management at the University of Portland and knows that the makespan of the project may be determined from the information in the table using the critical path method. Guillermo also learned a simple heuristic for evaluating resource sufficiency. Help Guillermo by answering the following related assuming 3 workers per week and a due date of 302.8: Project Work Content: Total Resource Capacity: Minimum due date for which 3 resources is sufficient: Minimum resource level that could make due date of 302.8 feasible:arrow_forwardHow an individual attending a university can help the development of a country?arrow_forwardWhat are the job description or role in Operations management? Please answer at your own easy words.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing
