Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8.8, Problem 17P
Summary Introduction
To determine: The optimal sequencing of jobs using evolutionary solver.
Introduction: The variation between the present value of the
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A furniture factory makes two types of wooden tables,large and small. See the flowchart below .Small tables are made in batches of 100, and large tables are made in batches of 50. A batch includes a fixed setup time for the entire batch at each process step and a run time for each piece in the batch. Both large and small tables have the same processing times. The capacities of each process step are given, and apply to production of either type of table, as shown in the flowchart. a. What is the capacity of the system, and what is thebottleneck? b. What are the throughput times for batches of large and small tables? c. When producing at a rate of six small tables per hour on average, how many tables will be in the system?
Consider a manufacturing process depicted by the following flowchart.
A1
B: 4 minutes
A2
A3
B
Either of C1 and C2: 2 minutes.
C1
Station A has 3 parallel operators, A1, A2, and A3. Station C has 2 parallel operators,
C1 and C2. Each unit only needs to be processed by one of the operators A1, A2 and
A3. After being processed at Station B, a unit then needs to be processed by either
C1 or C2. The process time of the individual operators are given as follows.
Each of A1, A2, and A3: 20 minutes
C2
What is the capacity (in units/hour) of the whole process? Round your final answer
to 2 decimal places if it is not a whole number.
Mr. Elf owns a show store. Currently, he has 10 pairs of shoes that require resoling and polishing. He has a machine that can resole one pair of shoes at a time, and the time required for
the operation varies with the type and condition of the shoe and the type of sole that is used. Shoes are polished on a machine dedicated to this purpose as well, and polishing is always
done after resoling. His assistant generally does the polishing while Mr. Elf does the resoling. The resoling and polishing times (in minutes) are:
Shoes
1
Resoling Time
14
Polishing Time
3
2
28
1
3
12
2
4
6
5
5
10
10
6
14
6
7
4
12
8
25
8
9
10
15
10
5
5
Determine the sequence in which these shoes should be repaired to minimize the total makespan for these 10 jobs, and answer the following questions.
Based on the optimal sequence: (Enter integer only)
1. The first job to be processed is Job
2. The third job to be processed is Job
3. The fourth job to be processed is Job
4. The fifth job to be processed is Job
5. The…
Chapter 8 Solutions
Practical Management Science
Ch. 8.3 - Prob. 1PCh. 8.3 - Prob. 2PCh. 8.4 - Prob. 3PCh. 8.4 - Prob. 4PCh. 8.4 - Prob. 5PCh. 8.5 - Prob. 6PCh. 8.5 - Prob. 7PCh. 8.5 - In the lawn mower production problem in Example...Ch. 8.6 - Prob. 9PCh. 8.6 - Prob. 10P
Ch. 8.6 - Prob. 11PCh. 8.6 - Prob. 12PCh. 8.7 - Prob. 13PCh. 8.7 - Prob. 14PCh. 8.8 - Prob. 15PCh. 8.8 - Prob. 16PCh. 8.8 - Prob. 17PCh. 8.8 - Prob. 18PCh. 8.8 - Prob. 19PCh. 8 - Prob. 20PCh. 8 - Prob. 21PCh. 8 - Prob. 22PCh. 8 - Prob. 23PCh. 8 - Prob. 24PCh. 8 - Prob. 25PCh. 8 - Prob. 26PCh. 8 - Prob. 27PCh. 8 - Prob. 28PCh. 8 - Prob. 29PCh. 8 - Prob. 30PCh. 8 - Prob. 31PCh. 8 - Prob. 32PCh. 8 - Prob. 33PCh. 8 - Prob. 34PCh. 8 - Prob. 35PCh. 8 - Prob. 36PCh. 8 - Prob. 37PCh. 8 - Prob. 38PCh. 8 - Prob. 39PCh. 8 - Prob. 1CCh. 8 - Prob. 2C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The single machine-scheduling problem consists of: Select one: None is correct n jobs with the same single operation on each of the jobs. n jobs with m operations on each of the jobs. n jobs with different operations on each of the jobs.arrow_forwardI need a b c pleasearrow_forwardOne possible solution method for the machine-to job assignment problem is the following heuristic procedure. Assign the machine to job 1 that completes job 1 quickest. Then assign the machine to job 2 that, among all machines that still have some capacity, completes job 2 quickest. Keep going until a machine has been assigned to all jobs. Does this heuristic procedure yield the optimal solution for this problem? If it does, see whether you can change the job times so that the heuristic does not yield the optimal solution.arrow_forward
- At the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the beginning of the day 1 (today, which is a work day). All of the jobs are due at various times today. Your job is to evaluate four common sequencing rules. JOB DUE (IN HOURS) DURATION (HOURS REQUIRED) A 8 (this job is due in 8 hours) 1.65 B 5.5 (this job is due in 5.5 hours) 1.20 C 4.5 (this job is due after lunch in 4.5 hours) 0.85 D 6 (this job is due in 6…arrow_forwardA serial process has 5 steps – A (4), B(5), C(2), D(6), and E(3) – that have to be performed in this order. The numbers in parentheses are the times (in minutes) needed to process a unit. For each unit produced by this process, the process has a total idle time of: Group of answer choices 1 min 10 mins 6 mins 3 minsarrow_forwardbama pie company's assembly line operations (the assembly line operates for six hundred minutes per day) comprise of eleven tasks, with the longest task time being 2.4 minutes and the shortest task time being 0.4 minutes; the sum of the task times is eighteen minutes. the firm is working on balancing its assembly line operations. the firm needs to produce 200 pies per day; to achieve this, the firm calculates the required cycle time as ---- minutes?arrow_forward
- Your team has been assigned to complete 10 client projects over the next two months. These projects and their processing times (time taken to complete a project once started, in days) are described in the table below. In addition, each project has a due-date that has been set by your internal marketing team so that the customers will be delighted with your service if you complete the project by the due-date. However, your team has only enough resources to pursue exactly one project at any given time. Once started, a project is worked through its completion and is not interrupted. As a result of the sequence in which you choose to handle projects, each project will either be on time, or late if it is completed past the due date. If a project is late, the amount of time by which it misses its due-date is called its tardiness. The objective is to pick the sequence in which to complete the projects so as to minimize the total tardiness in the schedule. What is the minimum total tardiness…arrow_forwardA key part of work center scheduling is job sequencing—deciding in what order jobs are scheduled to start/complete. What is the term for the simple rules used to aid this process using a single piece of data about the jobs?arrow_forwardA book binder has one printing press, one binding machine and manuscripts of 7 different books. The times required for performing printing and binding operations for different books are shown below. Book 1 2 3 4 5 6 7 Printing time (hours) 20 90 80 20 120 15 65 Binding time (hours) 25 60 75 30 90 35 50 Decide the optimum sequence of processing of books in order to minimize the total time required to bring out all the books.arrow_forward
- Currently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. The customers are ready to be scheduled today, which is the start of day 190. Customer Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Upper AA 6 18 66 Upper BB 3 24 58 Upper CC 2 32 100 Upper DD 10 22 26 Upper EE 8 12 50 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Part 2 Using the FCFS (first come, first served) decision rule for sequencing the customers, the order is: Sequence 1 2 3 4 5 Customer D E A B C Part 3 Using…arrow_forwardPlease answer this. C,D,Earrow_forwardUsing the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) : hours (enter your response as a whole number). = G Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Cut and Sew 3 5 6 Suit 1 2 7 3 Deliver 4 2 ∞ N 8 Assume that orders for suits have been listed in the above table in the order in which they were received.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.