Bundle: Managerial Economics: Applications, Strategies And Tactics, 14th + Mindtap Economics, 1 Term (6 Months) Printed Access Card
Bundle: Managerial Economics: Applications, Strategies And Tactics, 14th + Mindtap Economics, 1 Term (6 Months) Printed Access Card
14th Edition
ISBN: 9781337198196
Author: James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher: Cengage Learning
bartleby

Concept explainers

Question
Book Icon
Chapter 8, Problem 7E

a

To determine

To find:Average total cost schedules.

a

Expert Solution
Check Mark

Explanation of Solution

The annual capacity of plants A, B, and C are 75,000, 150,000, and 350,000 units, respectively. Production beyond annual capacities requires multiple plants of the same type. And hence, the fixed costs would increase by the same multiples too.

Unit variable costs are $9, $8 and $7 for plant A, B, and C, respectively.

The schedule below shoes the average total cost for Plant A for varying output levels.

    Q

    VC

    (1)

    FC

    (2)

    TC

    (1)+(2)

    ATC

    25,000

    $9(25,000)

    =$225,000

    $150,000

    $375,000

    $15

    50,000

    $9(50,000)

    =$450,000

    $150,000

    $600,000

    $12

    75,000

    $9(75,000)

    =$675,000

    $150,000

    $825,000

    $11

    100,000

    $9(100,000)

    =$900,000

    2($150,000)

    =$300,000

    $1,200,000

    $12

    125,000

    $9(125,000)

    =$1,125,000

    2($150,000)

    =$300,000

    $1,425,000

    $11.40

    150,000

    $9(150,000)

    =$1,350,000

    2($150,000)

    =$300,000

    $1,650,000

    $11

    175,000

    $9(175,000)

    =$1,575,000

    3($150,000)

    =$450,000

    $2,025,000

    $11.57

    200,000

    $9(200,000)

    =$1,800,000

    3($150,000)

    =$450,000

    $2,025,000

    $11.25

    225,000

    $9(225,000)

    =2,025,000

    3($150,000)

    =$450,000

    $2,475,000

    $11

    250,000

    $9(250,000)

    =$2,250,000

    4($150,000)

    =$600,000

    $2,850,000

    $11.40

    275,000

    $9(275,000)

    =$2,475,000

    4($150,000)

    =$600,000

    $3,075,000

    $11.18

    300,000

    $9(300,000)

    =$2,700,000

    4($150,000)

    =$600,000

    $3,300,000

    $11

    325,000

    $9(325,000)

    =$2,925,000

    5($150,000)

    =$750,000

    $3,675,000

    $11.31

    350,000

    $9(350,000)

    =$3,150,000

    5($150,000)

    =$750,000

    $3,900,000

    $11.14

The schedule below shows the average total cost for Plant B for varying output levels.

    QVC(1)FC(2)TC(1)+(2)ATC

    25,000

    $8(25,000)

    =$200,000

    $250,000

    $450,000

    $18

    50,000

    $8(50,000)

    =$400,000

    $250,000

    $650,000

    $12

    75,000

    $8(75,000)

    =$600,000

    $250,000

    $850,000

    $11.33

    100,000

    $8(100,000)

    =$800,000

    $250,000

    $1,050,000

    $10.50

    125,000

    $8(125,000)

    =$1,000,000

    $250,000

    $1,250,000

    $10

    150,000

    $8(150,000)

    =$1,200,000

    $250,000

    $1,450,000

    $9.67

    175,000

    $8(175,000)

    =$1,400,000

    2($250,000)

    =$500,000

    $1,900,000

    $10.86

    200,000

    $8(200,000)

    =$1,600,000

    2($250,000)

    =$500,000

    $2,100,000

    $10.50

    225,000

    $8(225,000)

    =$1,800,000

    2($250,000)

    =$500,000

    $2,300,000

    $10.22

    250,000

    $8(250,000)

    =$2,000,000

    2($250,000)

    =$500,000

    $2,500,000

    $10

    275,000

    $8(275,000)

    =$2,200,000

    2($250,000)

    =$500,000

    $2,700,000

    $9.82

    300,000

    $8(300,000)

    =$2,400,000

    2($250,000)

    =$500,000

    $2,900,000

    $9.67

    325,000

    $8(325,000)

    =$2,600,000

    3($250,000)

    =$750,000

    $3,350,000

    $10.31

    350,000

    $8(350,000)

    =$2,800,000

    3($250,000)

    =$750,000

    $3,550,000

    $10.14

The schedule below shows the average total cost for Plant C for varying output levels.

    QVC(1)FC(2)TC(1)+(2)ATC

    25,000

    $7(25,000)

    =$175,000

    $450,000

    $625,000

    $25

    50,000

    $7(50,000)

    =$350,000

    $450,000

    $800,000

    $16

    75,000

    $7(75,000)

    =$525,000

    $2450,000

    $975,000

    $13

    100,000

    $7(100,000)

    =$700,000

    $450,000

    $1,150,000

    $11.50

    125,000

    $7(125,000)

    =$875,000

    $450,000

    $1,325,000

    $10.60

    150,000

    $7(150,000)

    =$1,050,000

    $450,000

    $1,500,000

    $10

    175,000

    $7(175,000)

    =$1,225,000

    $450,000

    $1,675,000

    $9.57

    200,000

    $8(200,000)

    =$1,600,000

    $450,000

    $2,850,000

    $9.25

    225,000

    $7(225,000)

    =$1,575,000

    $450,000

    $2,025,000

    $9

    250,000

    $7(250,000)

    =$1,750,000

    $450,000

    $2,200,000

    $8.80

    275,000

    $7(275,000)

    =$1,925,000

    $450,000

    $2,375,000

    $8.64

    300,000

    $8(300,000)

    =$2,100,000

    $450,000

    $2,550,000

    $8.50

    325,000

    $7(325,000)

    =$2,275,000

    $450,000

    $3,725,000

    $8.38

    350,000

    $7(350,000)

    =$2,450,000

    $450,000

    $3,900,000

    $8.29

Economics Concept Introduction

Introduction:

Fixed costs (FC) are the costs that the firm has to incur irrespective of the level of output.

Variable costs (VC) are the costs that vary with the level of output, that is, increase as the output level increases, and vice versa.

Total cost (TC) is the total cost incurred by the firm in the production process. It is the sum of fixed cost and variable cost.

  TC=FC+VC

Average total cost (ATC) is the per unit total cost of the firm.

  ATC=TCQ

b)

To determine

To ascertain:Long run average total cost schedule.

b)

Expert Solution
Check Mark

Explanation of Solution

The combined long-run average cost schedule for three plants is as given below:

    Q

    Long Run ATC

    25,000$15
    50,000$12
    75,000$11
    100,000$10.50
    125,000$10
    150,000$9.67
    175,000$9.57
    200,000$9.25
    225,000$9
    250,000$8.80
    275,000$8.64
    300,000$8.50
    325,000$8.38
    350,000$8.29

For output level beyond 75,000 units (production capacity of plant A), average total cost is lower for plant B. Similarly, for output level beyond 150,000 units (production capacity of plant B), average total cost is lower for plant C.

Economics Concept Introduction

Introduction:

Fixed costs (FC) are the costs that the firm has to incur irrespective of the level of output.

Variable costs (VC) are the costs that vary with the level of output, that is, increase as the output level increases, and vice versa.

Total cost (TC) is the total cost incurred by the firm in the production process. It is the sum of fixed cost and variable cost.

  TC=FC+VC

Average total cost (ATC) is the per unit total cost of the firm.

  ATC=TCQ

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Section III: Empirical Findings: Descriptive Statistics and inferential statistics………………..40%   Descriptive statistics provide details about the Y variable, based on the sample for the 10-year period. Here, you use Excell or manually compute Mean or the average income per capita. Interpret the meaning of average income per capita. Draw the line chart showing the educational performance over the time-period of your study. Label the Vertical axis as Y performance and X axis as the explanatory variable (X1) . Do the same thing between Y and X2   Empirical/ Inferential Statistics: Here, use the sample information to perform the following: Draw the Scatter plot and impose the trend line: showing the Y variable and explanatory variables ( X1). Draw the scatter plot and impose the tend line: Showing Y and X2.   Does your evidence (data) support your theory? Refer to the trend line:  Is the relationship positive or negative as expected? Based on the data sheet below: Years Y ( per…
Section III: Empirical Findings: Descriptive Statistics and inferential statistics………………..40%   Descriptive statistics provide details about the Y variable, based on the sample for the 10-year period. Here, you use Excell or manually compute Mean or the average income per capita. Interpret the meaning of average income per capita. Draw the line chart showing the educational performance over the time-period of your study. Label the Vertical axis as Y performance and X axis as the explanatory variable (X1) . Do the same thing between Y and X2   Empirical/ Inferential Statistics: Here, use the sample information to perform the following: Draw the Scatter plot and impose the trend line: showing the Y variable and explanatory variables ( X1). Draw the scatter plot and impose the tend line: Showing Y and X2.   Does your evidence (data) support your theory? Refer to the trend line:  Is the relationship positive or negative as expected? Create graphs based on table below; Years Y ( per…
Please help me with this Accounting question
Knowledge Booster
Background pattern image
Economics
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Managerial Economics: Applications, Strategies an...
Economics
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Micro Economics For Today
Economics
ISBN:9781337613064
Author:Tucker, Irvin B.
Publisher:Cengage,
Text book image
Economics For Today
Economics
ISBN:9781337613040
Author:Tucker
Publisher:Cengage Learning
Text book image
Survey Of Economics
Economics
ISBN:9781337111522
Author:Tucker, Irvin B.
Publisher:Cengage,
Text book image
Microeconomics: Private and Public Choice (MindTa...
Economics
ISBN:9781305506893
Author:James D. Gwartney, Richard L. Stroup, Russell S. Sobel, David A. Macpherson
Publisher:Cengage Learning