Concept explainers
a)1
Determine the total materials cost variance, price and usage variance, the cause of variance and responsible management position.
a)1
Explanation of Solution
Compute the total variance:
Hence, the total variances are $336,200 which is an unfavorable variance.
Compute the total materials price variance:
Hence, the total materials price variances are $172,200 which is an unfavorable variance.
Compute the total materials usage variance:
Hence, the total materials usage variances are $164,000 which is unfavorable variance.
K Company paid more than the budgeted for planks of wood.
The purchasing agent is responsible for the price variance. The variances are occurred because of factors like lumber shortage, and inflation.
K Company used more materials than planned which leads to unfavorable usage variance.
The production supervisor is the responsible party. The variances are occurred because of factors like lack of physically control over inventory and lack of motivation to workers.
2)
Determine the labor cost, price, and usage variance and the cause of variance and responsible management position.
2)
Explanation of Solution
Compute the total labor cost variance:
Hence, the labor variance is $49,200 which is an unfavorable variance.
Compute the labor price variance:
Hence, the labor price variance is $118,900 which is an unfavorable variance.
Compute the labor usage variance:
Hence, the labor usage variance is $69,700 which is a favorable variance.
K Company paid more than the budgeted.
The personnel manager and production supervisors are responsible for the variance. The variances are occurred because of factors like the minimum wages could have been raised by the government.
K Company used less labor than planned which leads to favorable usage variance.
The production supervisor or personal managers are the responsible party. These people motivate the employees and hired more competent people.
3)
Determine the fixed cost spending and variance and the cause of variance and refer whether the actual fixed cost per unit is lower or higher than the budgeted fixed cost per unit.
3)
Explanation of Solution
Compute the fixed cost spending variance:
Table (1)
Hence, the spending variance is $48,400 which is unfavorable variance.
Compute the fixed cost volume variance:
Table (2)
Hence, the volume variance is $32,000 which is favorable variance.
Working note:
Calculate the the predetermined overhead rate:
Hence, the predetermined overhead rate is $16 per table.
The Company K has paid more than the planned with respect to fixed cost. The plant manager is responsible for the rent on manufacturing equipment. The personnel manager is responsible for the salaries paid to the company supervisor.
More units were produced and sold which leads to favorable volume variance. This reduces the fixed cost per unit.
b)
Indicate that the total of material, labor, and overheads variance are equal to the total flexible
b)
Explanation of Solution
Note:
Refer the above part for the calculated values.
Table (3)
c)
Discuss the reaction of Person D reacts to the variance information
c)
Explanation of Solution
Discuss the reaction of Person D reacts to the variance information:
Person D should make an impartible and fair investigation on the responsible parties and causes.
Monitoring the performance is sufficient for the improvement and in the circumstances of intentional disregard and consistent incompetence the disciplinary actions can be taken.
Want to see more full solutions like this?
Chapter 8 Solutions
Fundamental Managerial Accounting Concepts
- Calculate the amount of gross profitarrow_forwardAnjali Brewery has estimated budgeted costs of $72,600, $78,900, and $85,200 for the manufacture of 4,000, 5,000, and 6,000 gallons of beer, respectively, next quarter. What are the variable and fixed manufacturing costs in the flexible budget for Anjali Brewery?arrow_forwardDetermine the depreciationarrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education