A Total variable
Mosaic Company applies overhead using machine hours and reports the following information. Compute the total variable overhead cost variance and classify it as favorable or unfavorable.
Actual machine hours used | 4,700 hours |
Standard machine hours (for actual production) | 5,000 hours |
Actual variable overhead rate per hour | $4.15 |
Standard variable overhead rate per hour | $4.00 |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Please do not give solution in image format thanku
Question 3
DRS Company showed the following information for the year:
Standard variable overhead rate (SVOR) per direct labor hour
Standard hours (SH) allowed per unit
Actual production in units
Actual variable overhead costs
| Actual direct labor hours
RM3.75
4
15,000
RM222,816
57,200
a) Calculate the standard direct labor hours for actual production.
b) Calculate the applied variable overhead.
c) Calculate the total variable overhead variance.
Relevant information for product A follows:
Actual variable overhead cost per hour
Standards variable overhead cost per hour
Actual hours
Standard hours
$8,00
$7.50
O $2,250 unfavorable.
O $4,000 unfavorable.
O $2,250 favorable.
O $4,000 favorable.
4,500
5,000
What was the variable overhead spending variance for product A?
Chapter 8 Solutions
Managerial Accounting
Ch. 8 - Prob. 1MCQCh. 8 - Prob. 2MCQCh. 8 - Prob. 3MCQCh. 8 - A Company’s standard for a unit of its single...Ch. 8 - Prob. 5MCQCh. 8 - Prob. 1DQCh. 8 - Prob. 2DQCh. 8 - Prob. 3DQCh. 8 - Prob. 4DQCh. 8 - Prob. 5DQ
Ch. 8 - Prob. 6DQCh. 8 - Prob. 7DQCh. 8 - Prob. 8DQCh. 8 - Prob. 9DQCh. 8 - Prob. 10DQCh. 8 - Prob. 11DQCh. 8 - Prob. 12DQCh. 8 - Prob. 13DQCh. 8 - Prob. 14DQCh. 8 - Prob. 15DQCh. 8 - Prob. 16DQCh. 8 - Prob. 17DQCh. 8 - Prob. 18DQCh. 8 - Prob. 1QSCh. 8 - Prob. 2QSCh. 8 - Prob. 3QSCh. 8 - Prob. 4QSCh. 8 - Prob. 5QSCh. 8 - Prob. 6QSCh. 8 - Prob. 7QSCh. 8 - Prob. 8QSCh. 8 - Prob. 9QSCh. 8 - Materials cost variances P2 Juan Company’s output...Ch. 8 - Prob. 11QSCh. 8 - Prob. 12QSCh. 8 - Prob. 13QSCh. 8 - Prob. 14QSCh. 8 - Prob. 15QSCh. 8 - Prob. 16QSCh. 8 - A Preparing overhead entries P5 Refer to the...Ch. 8 - A Total variable overhead cost variance P4 Mosaic...Ch. 8 - A Overhead spending and efficiency variances P4...Ch. 8 - Computing sales price and volume variances A1...Ch. 8 - Sales variances A1 In a recent year, BMW sold...Ch. 8 - Prob. 22QSCh. 8 - Prob. 23QSCh. 8 - Prob. 24QSCh. 8 - Prob. 1ECh. 8 - Prob. 2ECh. 8 - Prob. 3ECh. 8 - Prob. 4ECh. 8 - Prob. 5ECh. 8 - Prob. 6ECh. 8 - Prob. 7ECh. 8 - Exercise 21-8 Standard unit cost; total variance...Ch. 8 - Prob. 9ECh. 8 - Prob. 10ECh. 8 - Prob. 11ECh. 8 - Prob. 12ECh. 8 - Prob. 13ECh. 8 - Exercise 21-14A Materials variances recorded and...Ch. 8 - Prob. 15ECh. 8 - Prob. 16ECh. 8 - Prob. 17ECh. 8 - Prob. 18ECh. 8 - Exercise 21-19 Computation of total overhead rate...Ch. 8 - Exercise 21-20 Computation of volume and...Ch. 8 - Exercise 21-21 Overhead controllable and volume...Ch. 8 - Prob. 22ECh. 8 - Exercise 21-23 Computing and interpreting sales...Ch. 8 - Prob. 1PSACh. 8 - Prob. 2PSACh. 8 - Prob. 3PSACh. 8 - Prob. 4PSACh. 8 - Prob. 5PSACh. 8 - Problem 21-6AA Materials, labor, and overhead...Ch. 8 - Prob. 1PSBCh. 8 - Prob. 2PSBCh. 8 - Prob. 3PSBCh. 8 - Prob. 4PSBCh. 8 - Prob. 5PSBCh. 8 - Problem 21-6BA Materials, labor, and overhead...Ch. 8 - Prob. 8SPCh. 8 - Flexible budgets and standard costs emphasize the...Ch. 8 - Prob. 2AACh. 8 - Prob. 3AACh. 8 - Prob. 1BTNCh. 8 - The reason we use the words favorable when...Ch. 8 - Prob. 3BTNCh. 8 - Prob. 4BTNCh. 8 - Prob. 5BTNCh. 8 - Prob. 6BTN
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Calculating amount of factory overhead applied to work in process The overhead application rate for a company is 2.50 per unit, made up of 1.00 for fixed overhead and 1.50 for variable overhead. Normal capacity is 10,000 units. In one month, there was an unfavorable flexible budget variance of 200. Actual overhead for the month was 27,000. What was the amount of the budgeted overhead for the actual level of production?arrow_forwardWhat is the standard quantityarrow_forwardSolve this problem not use chatgptarrow_forward
- Standard Costingarrow_forwardA company reports the following information for its direct labor. Actual hours of direct labor used Actual rate of direct labor per hour Standard rate of direct labor per hour Standard hours of direct labor for units produced AH = Actual Hours SH Standard Hours AR = Actual Rate SR Standard Rate Compute the direct labor rate and efficiency variances and identify each as favorable or unfavorable. Actual Cost $ 0 $ 74,000 $15 $14 75, 200 0 0 $ 0 Standard Costarrow_forwardPlease do not give solution in image format thankuarrow_forward
- A company reports the following information for its direct labor. Actual hours of direct labor used Actual rate of direct labor per hour Standard rate of direct labor per hour Standard hours of direct labor for units produced ! AH = Actual Hours SH= Standard Hours AR= Actual Rate SR Standard Rate Compute the direct labor rate and efficiency variances and identify each as favorable or unfavorable. Q F1 Actual Cost @ 2 W F2 # 3 E 80 F3 $ $ 4 0 Ơ F4 R $ % 5 0 0 * DII 8 F8 Standard Cost ( 9 F9 ) U I O F1arrow_forwardRequired information (The following information applies to the questions displayed below.] Mosaic Company applies overhead using machine hours and shows the following information. Actual hours of machine use Standard hours of machine use (for actual production) Actual variable overhead rate per machine hour Standard variable overhead rate per machine hour 5,500 hours 6,000 hours $5.10 Compute the variable overhead variance and identify it as favorable or unfavorable. Actual Cost Standard Costarrow_forwardDengerarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegePrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY