Textbook Question
Chapter 8, Problem 21E
Exercise 21-21
James Corp. applies overhead on the basis of direct labor hours. For the month of May, the company planned production of 8,000 units (80% of its production capacity of 10,000 units) and prepared the following overhead budget.
Overhead Budget | Operating Level |
80%
During May, the company operated at 90% capacity (9,000 units) and incurred the following actual overhead costs.
Overhead costs(actual) | |
Indirect materials…………………………………………… | $15,000 |
Indirect labor………………………………………………… | 26,500 |
Power………………………………………………………… | 6,750 |
Maintenance…………………………………………………. | 4,000 |
Rent of factory building……………………………………... | 15,000 |
Depreciation—Machinery…………………………………… | 10,000 |
Supervisory salaries…………………………………………. | 22,000 |
Total actual overhead costs…………………………………. | $99,250 |
- Compute the overhead controllable variance and classify it as favorable or unfavorable.
- Compute the overhead volume variance and classify it as favorable or unfavorable.
- Prepare an overhead variance report at the actual activity level of 9,000 units.
Expert Solution & Answer

Want to see the full answer?
Check out a sample textbook solution
Students have asked these similar questions
Can you solve this general accounting problem using appropriate accounting principles?
Please provide the correct answer to this financial accounting problem using valid calculations.
A company identifies two activities: material handling and machine setup. The cost drivers are number of parts (10,000) and number of setups (200), with cost pools of $250,000 and $180,000 respectively. Product A uses 2,500 parts and 50 setups. Calculate the activity-based overhead allocated to Product A.
Chapter 8 Solutions
Managerial Accounting
Ch. 8 - Prob. 1MCQCh. 8 - Prob. 2MCQCh. 8 - Prob. 3MCQCh. 8 - A Company’s standard for a unit of its single...Ch. 8 - Prob. 5MCQCh. 8 - Prob. 1DQCh. 8 - Prob. 2DQCh. 8 - Prob. 3DQCh. 8 - Prob. 4DQCh. 8 - Prob. 5DQ
Ch. 8 - Prob. 6DQCh. 8 - Prob. 7DQCh. 8 - Prob. 8DQCh. 8 - Prob. 9DQCh. 8 - Prob. 10DQCh. 8 - Prob. 11DQCh. 8 - Prob. 12DQCh. 8 - Prob. 13DQCh. 8 - Prob. 14DQCh. 8 - Prob. 15DQCh. 8 - Prob. 16DQCh. 8 - Prob. 17DQCh. 8 - Prob. 18DQCh. 8 - Prob. 1QSCh. 8 - Prob. 2QSCh. 8 - Prob. 3QSCh. 8 - Prob. 4QSCh. 8 - Prob. 5QSCh. 8 - Prob. 6QSCh. 8 - Prob. 7QSCh. 8 - Prob. 8QSCh. 8 - Prob. 9QSCh. 8 - Materials cost variances P2 Juan Company’s output...Ch. 8 - Prob. 11QSCh. 8 - Prob. 12QSCh. 8 - Prob. 13QSCh. 8 - Prob. 14QSCh. 8 - Prob. 15QSCh. 8 - Prob. 16QSCh. 8 - A Preparing overhead entries P5 Refer to the...Ch. 8 - A Total variable overhead cost variance P4 Mosaic...Ch. 8 - A Overhead spending and efficiency variances P4...Ch. 8 - Computing sales price and volume variances A1...Ch. 8 - Sales variances A1 In a recent year, BMW sold...Ch. 8 - Prob. 22QSCh. 8 - Prob. 23QSCh. 8 - Prob. 24QSCh. 8 - Prob. 1ECh. 8 - Prob. 2ECh. 8 - Prob. 3ECh. 8 - Prob. 4ECh. 8 - Prob. 5ECh. 8 - Prob. 6ECh. 8 - Prob. 7ECh. 8 - Exercise 21-8 Standard unit cost; total variance...Ch. 8 - Prob. 9ECh. 8 - Prob. 10ECh. 8 - Prob. 11ECh. 8 - Prob. 12ECh. 8 - Prob. 13ECh. 8 - Exercise 21-14A Materials variances recorded and...Ch. 8 - Prob. 15ECh. 8 - Prob. 16ECh. 8 - Prob. 17ECh. 8 - Prob. 18ECh. 8 - Exercise 21-19 Computation of total overhead rate...Ch. 8 - Exercise 21-20 Computation of volume and...Ch. 8 - Exercise 21-21 Overhead controllable and volume...Ch. 8 - Prob. 22ECh. 8 - Exercise 21-23 Computing and interpreting sales...Ch. 8 - Prob. 1PSACh. 8 - Prob. 2PSACh. 8 - Prob. 3PSACh. 8 - Prob. 4PSACh. 8 - Prob. 5PSACh. 8 - Problem 21-6AA Materials, labor, and overhead...Ch. 8 - Prob. 1PSBCh. 8 - Prob. 2PSBCh. 8 - Prob. 3PSBCh. 8 - Prob. 4PSBCh. 8 - Prob. 5PSBCh. 8 - Problem 21-6BA Materials, labor, and overhead...Ch. 8 - Prob. 8SPCh. 8 - Flexible budgets and standard costs emphasize the...Ch. 8 - Prob. 2AACh. 8 - Prob. 3AACh. 8 - Prob. 1BTNCh. 8 - The reason we use the words favorable when...Ch. 8 - Prob. 3BTNCh. 8 - Prob. 4BTNCh. 8 - Prob. 5BTNCh. 8 - Prob. 6BTN
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningAccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Financial & Managerial AccountingAccountingISBN:9781337119207Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningFinancial & Managerial AccountingAccountingISBN:9781285866307Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning

Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning

Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,

Financial & Managerial Accounting
Accounting
ISBN:9781337119207
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning

Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning

Financial & Managerial Accounting
Accounting
ISBN:9781285866307
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY