Concept explainers
At the beginning of the month, Arthur’s Olde Consulting Corporation had two jobs in process that had the following costs assigned from previous months:
During the month, Jobs SY-400 and SY-403 were completed but not billed to customers. The completion costs for SY-400 required $25,200 in direct labor. For SY-403, $72,000 in labor was used.
During the month, the only new job, SY-404, was started but not finished. Total direct labor costs for all jobs amounted to $148,320 for the month.
Required
- a. What are the costs of Jobs SY-400 and SY-403 at (1) the beginning of the month and (2) when completed?
- b. What is the cost of Job SY-404 at the end of the month?
- c. How much was under- or overapplied service overhead for the month?
a.
Find the costs of jobs SY-400 and SY-403 at the beginning of the month and when completed.
Answer to Problem 40E
The costs of jobs SY-400 and SY-403 at the beginning of the month and when completed are as follows:
Costs of jobs SY-400 and SY-403 at the beginning of the month | |
Particulars | Amount |
SY-400 | $ 36,864 |
SY-403 | $ 24,192 |
Table: (1)
Costs of jobs SY-400 and SY-403 during the month | |
Particulars | Amount |
SY-400 | $ 77,184 |
SY-403 | $ 139,392 |
Table: (2)
Explanation of Solution
Job costing: Job costing is a method of tracking and allocating costs to different jobs in the manufacturing process. This method of costing is used in entities where different jobs are incurred in each period.
The costs of jobs SY-400 and SY-403 at the beginning of the month and when completed are as follows:
Costs of jobs SY-400 and SY-403 at the beginning of the month | |
Particulars | Amount |
SY-400 | $ 36,864 (1) |
SY-403 | $ 24,192 (2) |
Table: (3)
Costs of jobs SY-400 and SY-403 during the month | |
Particulars | Amount |
SY-400 | $ 77,184 (3) |
SY-403 | $ 139,392 (4) |
Table: (4)
Working Note 1:
Compute the cost of job SY- 400 at the beginning of the month:
Working Note 2:
Compute the cost of job SY- 403 at the beginning of the month:
Working note 3:
Compute the cost of job SY- 400 during the month:
Working note 4:
Compute the cost of job SY- 403 during the month:
b.
Find the cost of job SY-404 at the end of the month.
Answer to Problem 40E
The cost of job SY-404 at the end of the month is $81,792.
Explanation of Solution
Job costing: Job costing is a method of tracking and allocating costs to different jobs in the manufacturing process. This method of costing is used in entities where different jobs are incurred in each period.
Compute the cost of job SY- 404 at the end of the month:
Thus, the value of the cost of job SY-404 at the end of the month is $81,792.
Working note 5:
Compute the direct labor of job SY-404:
c.
Find the under or over-applied service overhead for the month.
Answer to Problem 40E
The value of under-applied overhead is $1,008.
Explanation of Solution
Over-applied overheads: This is the amount of overhead which arises when the amount of actual overheads is less than the amount of overheads applied.
Compute the under or over-applied service overhead for the month:
Thus, the value of under-applied overhead is $1,008.
Working note 6:
Applied overheads are 60% of actual direct labor.
Hence,
Compute the overhead applied during the month:
Want to see more full solutions like this?
Chapter 7 Solutions
COST ACCOUNTING W/CONNECT
Additional Business Textbook Solutions
Essentials of MIS (13th Edition)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Financial Accounting, Student Value Edition (5th Edition)
Business Essentials (12th Edition) (What's New in Intro to Business)
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
- During August, Skyler Company worked on three jobs. Data relating to these three jobs follow: Overhead is assigned on the basis of direct labor hours at a rate of 2.30 per direct labor hour. During August, Jobs 39 and 40 were completed and transferred to Finished Goods Inventory. Job 40 was sold by the end of the month. Job 41 was the only unfinished job at the end of the month. Required: 1. Calculate the per-unit cost of Jobs 39 and 40. (Round unit costs to nearest cent.) 2. Compute the ending balance in the work-in-process inventory account. 3. Prepare the journal entries reflecting the completion of Jobs 39 and 40 and the sale of Job 40. The selling price is 140 percent of cost.arrow_forwardLuna Manufacturing Inc. completed Job 2525 on May 31, and there were no jobs in process in the plant. Prior to June 1, the predetermined overhead application rate for June was computed from the following data, based on an estimate of 5,000 direct labor hours: The factory has one production department and uses the direct labor hour method to apply factory overhead. Three jobs are started during the month, and postings are made daily to the job cost sheets from the materials requisitions and labor-time records. The following schedule shows the jobs and amounts posted to the job cost sheets: The factory overhead control account was debited during the month for actual factory overhead expenses of 27,000. On June 11, Job 2526 was completed and delivered to the customer using a mark-on percentage of 50% on manufacturing cost. On June 24, Job 2527 was completed and transferred to Finished Goods. On June 30, Job 2528 was still in process. Required: 1. Prepare job cost sheets for Jobs 2526, 2527, and 2528, including factory overhead applied when the job was completed or at the end of the month for partially completed jobs. 2. Prepare journal entries as of June 30 for the following: a. Applying factory overhead to production. b. Closing the applied factory overhead account. c. Closing the factory overhead account. d. Transferring the cost of the completed jobs to finished goods. e. Recording the cost of the sale and the sale of Job 2526.arrow_forwardAbbey Products Company is studying the results of applying factory overhead to production. The following data have been used: estimated factory overhead, 60,000; estimated materials costs, 50,000; estimated direct labor costs, 60,000; estimated direct labor hours, 10,000; estimated machine hours, 20,000; work in process at the beginning of the month, none. The actual factory overhead incurred for November was 80,000, and the production statistics on November 30 are as follows: Required: 1. Compute the predetermined rate, based on the following: a. Direct labor cost b. Direct labor hours c. Machine hours 2. Using each of the methods, compute the estimated total cost of each job at the end of the month. 3. Determine the under-or overapplied factory overhead, in total, at the end of the month under each of the methods. 4. Which method would you recommend? Why?arrow_forward
- Collegiate Publishing Inc. began printing operations on March 1. Jobs 301 and 302 were completed during the month, and all costs applicable to them were recorded on the related cost sheets. Jobs 303 and 304 are still in process at the end of the month, and all applicable costs except factory overhead have been recorded on the related cost sheets. In addition to the materials and labor charged directly to the jobs, 4,500 of indirect materials and 8,200 of indirect labor were used during the month. The cost sheets for the four jobs entering production during the month are as follows, in summary form: Journalize the summary entry to record each of the following operations for March (one entry for each operation): a. Direct and indirect materials used. b. Direct and indirect labor used. c. Factory overhead applied to all four jobs (a single overhead rate is used based on direct labor cost). d. Completion of Jobs 301 and 302.arrow_forwardEntry for factory labor costs The weekly time tickets indicate the following distribution of labor hours for three direct labor employees: The direct labor rate earned per hour by the three employees is as follows: The process improvement category includes training, quality improvement, and other indirect tasks. A. Journalize the entry to record the factory labor costs for the week. B. Assume that Jobs 301 and 302 were completed but not sold during the week and that Job 303 remained incomplete at the end of the week. How would the direct labor costs for all three jobs be reflected on the financial statements at the end of the week?arrow_forwardChannel Products Inc. uses the job order cost system of accounting. The following is a list of the jobs completed during March, showing the charges for materials issued to production and for direct labor. Assume that factory overhead is applied on the basis of direct labor costs and that the predetermined rate is 200%. Required: Compute the amount of overhead to be added to the cost of each job completed during the month. Compute the total cost of each job completed during the month. Compute the total cost of producing all the jobs finished during the month.arrow_forward
- Lucy Sportswear manufactures a specialty line of T-shirts using a job order cost system. During March, the following costs were incurred in completing Job ICU2: direct materials, 13,700; direct labor, 4,800; administrative, 1,400; and selling, 5,600. Factory overhead was applied at the rate of 25 per machine hour, and Job ICU2 required 800 machine hours. If Job ICU2 resulted in 7,000 good shirts, the cost of goods sold per unit would be: a. 5.70. b. 6.50. c. 5.50. d. 6.30.arrow_forwardThe cost accountant for River Rock Beverage Co. estimated that total factory overhead cost for the Blending Department for the coming fiscal year beginning February 1 would be 3,150,000, and total direct labor costs would be 1,800,000. During February, the actual direct labor cost totalled 160,000, and factory overhead cost incurred totaled 283,900. a. What is the predetermined factory overhead rate based on direct labor cost? b. Journalize the entry to apply factory overhead to production for February. c. What is the February 28 balance of the account Factory OverheadBlending Department? d. Does the balance in part (c) represent over- or underapplied factory overhead?arrow_forwardDuring the month, a company with no departmentalization incurred costs of 45,000 for materials, 36,000 for labor, and 22,500 for factory overhead. There were no units in process at the beginning or at the end of the month, and 20,000 units were completed. Determine the unit cost for the month for materials, labor, factory overhead, and the total unit cost. (Round unit costs to three decimal places.)arrow_forward
- Potomac Automotive Co. manufactures engines that are made only on customers orders and to their specifications. During January, the company worked on Jobs 007, 008, 009, and 010. The following figures summarize the cost records for the month: Jobs 007 and 008 have been completed and delivered to the customer at a total selling price of 426,000, on account. Job 009 is finished but has not yet been delivered. Job 010 is still in process. There were no materials or work in process inventories at the beginning of the month. Material purchases were 115,000, and there were no indirect materials used during the month. Required: 1. Prepare a summary showing the total cost of each job completed during the month or in process at the end of the month. 2. Prepare the summary journal entries for the month to record the distribution of materials, labor, and overhead costs. 3. Determine the cost of the inventories of completed engines and engines in process at the end of the month. 4. Prepare the journal entries to record the completion of the jobs and the sale of the jobs. 5. Prepare a statement of cost of goods manufactured.arrow_forwardRulers Company is a neon sign company that estimated overhead will be $60,000, consisting of 1,500 machine hours. The cost to make Job 416 is $95 in neon, 15 hours of labor at $13 per hour, and five machine hours. During the month, it incurs $95 in indirect material cost, $130 in administrative labor, $320 in utilities, and $350 in depreciation expense. What is the predetermined overhead rate if machine hours are considered the cost driver? What is the cost of Job 416? What is the overhead incurred during the month?arrow_forwardLorrimer Company has a job-order cost system. The following debits (credits) appeared in the Work-in-Process account for the month of June. During the month of June, direct labor totaled 30,000 and 24,000 of overhead was applied to production. Finished Goods was debited 100,000 during June. Lorrimer Company applies overhead at a predetermined rate of 80% of direct labor cost. Job number 83, the only job still in process at the end of June, has been charged with manufacturing overhead of 3,400. What was the amount of direct materials charged to Job number 83? a. 3,400 b. 4,250 c. 8,350 d. 7,580arrow_forward
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubExcel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage Learning