Operations Management: Processes And Supply Chains (12th Global Edition) - Does Not Include Mylab Operations Management
12th Edition
ISBN: 9780134890357
Author: Lee J. Krajewski, Manoj K. Malhotra
Publisher: Pearson Global Edition
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 22P
In Solved Problem 2, estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take 20 weeks or less.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Note: end of the question answer also given.
I want A&D only.
Onc aagain remember I want only A&D part
A. What is the probability that path A-B-D-F-G will take from 100 to 120 days to complete? Answer = 40.2%
B. What is the probability that path A-C-E-G will take less than 85 days to complete? Answer = 32.64%
C. If the contract for the above project is 120 days, what is the chance of meeting the schedule? Answer = 86.3%
D. What duration (number of full days) should be used to be at least 90% confident of finishing on time? Answer = 125 days - Probability of 93%
Construct the project network for this project and determine the following:
d) Expected project duration and variance
e) The probability that the mill will be fined $300,000
Please do not give solution in image formate thanku.
There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 4 weeks. The crashing cost (per week), for the first week (crashing first time), for activity A is: $400, E is $415 and all other activities is : $100 (per week per activity). The crashing cost, second week and onwards(crashing second time), for activity A is $1000 per week, E is $1200 per week and for all other activities is $200 per activity per week. You have a maximum crashing budget of $2505. The maximum possible reduction in the project duration will be:
a. 2 weeks
b. 3 weeks
c. 4 weeks
d. 5 weeks
e. 6 weeks
Chapter 7 Solutions
Operations Management: Processes And Supply Chains (12th Global Edition) - Does Not Include Mylab Operations Management
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Operations Management
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- In making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start time for activity T? Group of answer choices: - the LS of the following activity plus the activity time of T - the smallest EF for the three activities that are immediate predecessors for activity T - the LF of the following activity minus the activity time of T - the LS of the following activity minus the activity time of T - the largest EF for the three activities that are immediate predecessors for activity Tarrow_forwardThe Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safety regulations. The OSHA inspectors ordered the mill to alter some existing machinery to make it safer (add safety guards, etc.); purchase some new machinery to replace older, dangerous machinery; and relocate some machinery to make safer passages and unobstructed entrances and exits. OSHA gave the mill only 35 weeks to make the changes; if the changes were not made by then, the mill would be fined $300,000. The mill determined the activities in a CPM/PERT network that would have to be completed and then estimated the indicated activity times, as shown in the following table: Construct the project network for this project and determine the following: a. Expected activity times b. Earliest and latest activity times and activity slack c. Critical path d. Expected project duration and variance e. The probability that the mill will be fined $300,000arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre-decessors, and times appear in the accompanying table: A—2 B—5 C—1 D B 10 E A, D 3 FC6 G E, F 8 A) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time? Please answer A B C and show workarrow_forward
- Give typing answer with explanation and conclusionarrow_forwardNikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. Activity Predecessor Duration in Weeks A - 5 B - 3 C A, B 8 D C 3 E - 4 F E 10 G F 8 H E 18 I D 20 J D, G, I 7 K I 5 L H 10 6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation: the first pic: First: Draw the precedence diagram. Second: Using the notation given identify the duration of the project: you can type it. Third: identify the critical part and explain the critical path. Fourth: Explain your answer. This can be done by describing the process and the observations done once the answer has been found. 6B. Draw the project’s Gantt chart First: The…arrow_forwardProblem 9-14 (Algorithmic) Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion date requested by the owner. The Davison project manager prepared the following project network: B F H Start C G Finish D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows: Activity Optimistic Most Probable Pessimistic A 4 9 14 B 5 7 3 4 D 8 11 14 7 17arrow_forward
- Duration and requirement of workforce for each activity is tabulated below for a network Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2 3-6 2 1 5-6 6 6 4-6 5 5 (i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce (ii) Indicate the maximum crew size in each case (iii) Re-schedule the activities for smooth development (iv) Find the project schedule if only 4 men are availablearrow_forwardExample: Undertaking by a contractor to implement a contracting for excavation works according to the scheme below, undertaking to complete the work within a period of 36 weeks with a probability of 99% between in light of the contractor's probability. The actual time period for the completion of the project within the PERT technology? Act. a b te u C.P 1-2 7 8. 6.33 1 1 *1,2 2-3 6. 9 6.33 0.66 0.443 *2 2-4 3 7 8. 6.5 0.83 .693 *1 2-5 4 6. 0.33 3-6 9. 10 8.66 0.66 0.443 *2 4-7 6. 8 11 8.166 0.83 .693 *1 5-7 4 7 5.83 0.5 6-8 7 10 7.16 0.83 .693 *2 7-8 4 8 7.5 0.83 .693 *1 8-9 4 7 9 6.83 0.83 .693 *1,2arrow_forwardOn January 1, Jack signed a contract with AT &T for his mobile phone services. The contract includes three lines with a $120 fixed payment each month plus $15 per gigabit if the data usage is more than 9 gigabits. On March 1, Jack wants to add one more phone line to the existed contract, and the payment becomes $150 fixed payment each month plus $15 per gigabit if the data usage is more than 12 gigabits. Is this change a contract modification? Please use one sentence to explain why?arrow_forward
- illustrate unscaled activity bar type of early start and late startarrow_forwardFind the following: 1- The optimum period and the corresponding time 2- The network plan detailed in the table below, noting that the additional cost is $ 1500 per week Activity Normal duration Normal cost Crash duration Crash cost weeks 2$ 2000 weeks 2$ 1-2 11 9. 10000 1-3 17 3000 14 12000 2-3 8. 6. 3600 6. 6000 3-4 6000 4 11000arrow_forwardActivity E has an optimistic time of 9 days, a most likely time of 12 days, and a pessimistic time of 15 days. Estimate its expected time and standard deviation.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY