EBK CORPORATE FINANCE
4th Edition
ISBN: 9780134202785
Author: DeMarzo
Publisher: VST
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 15P
You have 3 projects with the following cash flows:
- a. For which of these projects is the IRR rule reliable?
- b. Estimate the IRR for each project (to the nearest 1%).
- c. What is the
NPV of each project if the cost of capital is 5%? 20%? 50%?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
You are considering the following two projects and can take only one. Your cost of capital is 10.6%. The cash flows for the two projects a
as follows ($ million):
a. What is the IRR of each project?
b. What is the NPV of each project at your cost of capital?
c. At what cost of capital are you indifferent between the two projects?
d. What should you do?
Data table
(Click on the following icon in order to copy its contents into a spreadsheet.)
Project
Year 0
Year 1
Year 2
A
- $100
$24
$30
B
- $100
$48
$41
Year 3
$41
$30
Year 4
$48
$18
—
X
You are considering the following two projects and can take only one. Your cost of capital is 11.2%. The cash flows for the
two projects are as follows ($ million):
Project Year 0 Year 1 Year 2 Year 3 Year 4
A -100 26 28 42 48
B-100 48 42 28 19
a. What is the IRR of each project?
b. What is the NPV of each project at your cost of capital?
c. At what cost of capital are you indifferent between the two projects?
d. What should you do?
You are considering the following two projects and can take only one. Your cost of capital is 10.7%. The cash flows for the two projects are as follows ($ million):
a. What is the IRR of each project?
b. What is the NPV of each project at your cost of capital?
c. At what cost of capital are you indifferent between the two projects?
d. What should you do?
Data table
(Click on the following icon in order to copy its contents into a spreadsheet.)
a. What is the IRR of each project?
Year 0
Year 1
Year 2
Year 3
Project
A
The IRR for project A is %. (Round to one decimal place.)
$24
$31
$38
- $102
- $102
B
$49
$38
$31
The IRR for project B is%. (Round to one decimal place.)
b. What is the NPV of each project at your cost of capital?
The NPV for project A is $
million. (Round to two decimal places.)
Done
The NPV for project B is $
million. (Round to two decimal places.)
c. At what cost of capital are you indifferent between the two projects?
You will be indifferent if the cost of capital is%.…
Chapter 7 Solutions
EBK CORPORATE FINANCE
Ch. 7.1 - Explain the NPV rule for stand-alone projects.Ch. 7.1 - What does the difference between the cost of...Ch. 7.2 - Prob. 1CCCh. 7.2 - If the IRR rule and the NPV rule lead to different...Ch. 7.3 - Can the payback rule reject projects that have...Ch. 7.3 - Prob. 2CCCh. 7.4 - For mutually exclusive projects, explain why...Ch. 7.4 - What is the incremental RR and what are its...Ch. 7.5 - Prob. 1CCCh. 7.5 - Prob. 2CC
Ch. 7 - Your brother wants to borrow 10,000 from you. He...Ch. 7 - You are considering investing in a start-up...Ch. 7 - You are considering opening a new plant. The plant...Ch. 7 - Your firm is considering the launch of a new...Ch. 7 - Bill Clinton reportedly was paid 15 million to...Ch. 7 - FastTrack Bikes, Inc. is thinking of developing a...Ch. 7 - OpenSeas, Inc. is evaluating the purchase of a new...Ch. 7 - You are CEO of Rivet Networks, maker of ultra-high...Ch. 7 - You are considering an investment in a clothes...Ch. 7 - You have been offered a very long term investment...Ch. 7 - You are considering opening a new plant. The plant...Ch. 7 - Bill Clinton reportedly was paid 15 million to...Ch. 7 - Prob. 13PCh. 7 - Innovation Company is thinking about marketing a...Ch. 7 - You have 3 projects with the following cash flows:...Ch. 7 - You own a coal mining company and are considering...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - You are a real estate agent thinking of placing a...Ch. 7 - Prob. 22PCh. 7 - You are deciding between two mutually exclusive...Ch. 7 - You have just started your summer Internship, and...Ch. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 33PCh. 7 - Orchid Biotech Company is evaluating several...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,000 3 1 900 4 2 1,300 5 3 1,606 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3. What should you do? Check all that apply: Accept the project based on its IRR Accept the project based on its NPV Reject the project based on its IRR Reject the project based on its NPVarrow_forwardYou are considering the following two projects and can take only one. Your cost of capital is 10.7%. The cash flows for the two projects are as follows ($ million) a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital are you indifferent between the two projects? d. What should you do? a. What is the IRR of each project? The IRR for project A is %. (Round to one decimal place.) Data table D (Click on the following icon in order to copy its contents into a spreadsheet) Project A Year 0 -$100 B -$100 Year 1 $22 $49 Year 2 $31 $39 Print Done Year 3 Year 4 $39 $49 $31 $21 -arrow_forwardIf the cash flows for Project M are C0 = -1,000; C1 = +800; C2 = +700 and C3= -200. Calculate the IRR for the project. For what range of discount rates does the project have a positive NPV?arrow_forward
- Consider an investment project with the cash flows given in the table below. Compute the IRR for this investment. Is the project acceptable at MARR = 10%? The IRR for this project is %. (Round to one decimal place.) n 0 1 2 3 Cash Flow -$35,000 15,000 14,520 13,990arrow_forwardYou are considering the following two projects and can take only one. Your cost of capital is 10.6%. The cash flows for the two projects are as follows ($ million): a. What is the NPV of each project at your cost of capital? b. What is the IRR of each project? c. At what cost of capital are you indifferent between the two projects? d. What should you do? a. What is the NPV of each project at your cost of capital? The NPV for project A is $ Data table million. (Round to two decimal places.) (Click on the following icon in order to copy its contents into a spreadsheet.) Year 1 Project A $22 B $48 Year 0 - $100 - $100 Year 2 $28 $42 Year 3 $42 $28 Year 4 $48 $20 - Xarrow_forward3. You are considering a project that has an initial outlay of $1million. The profitability index of the project is 2.24. What is the NPV of the project?arrow_forward
- Project Y has following cash flows: C0 = -800, C1 = +6,000, and C2 = -6,000. Calculate the IRRs for the project: For what range of discount rates does the project have positive NPV (Plot a graph with NPV on the vertical axis and discount rate on the horizontal axis).arrow_forwardYou are considering the following two projects and can only take one. Your cost of capital is 11.3%. The cash flows for the two projects are as follows ($ million): Year 2 Year 3 Year 4 Year 0 - $100 Year 1 $23 $29 $39 $51 - $100 $51 $39 $29 $21 Project A B a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital are you indifferent between the two projects? d. What should you do?arrow_forwardConsider the following cash flow profile and assume MARR is 10%/yr. Solve, a. What does Descartes’ rule of signs tell us about the IRR(s) of this project? b. What does Norstrom’s criterion tell us about the IRR(s) of this project? c. Determine the IRR(s) for this project. d. Is this project economically attractive?arrow_forward
- Suppose we have a project with the following cash flows;Outgoing: $150,000 at t=0 and $250,000 at t=1Income: $1,000,000 at t=2Find the IRR of the project.arrow_forwardWhich of the following comes closest to the net present value (NPV) of a project whose initial investment is $5 and which produces two cash flows: the first at the end of year 2 of $3 and the second at the end of year 4 of $7? The required rate of return is 13%? Select one: a. $1.84 b. $0 c. $1.64 d. $2.05 e. $2.26arrow_forwardplease solve using excel formulaarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage Learning
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License