Table 7.5 contains information about au environmental cleanup project in the township of Hiles. Shorten the project 3 weeks by finding the minimum—cost
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
MyLab Operations Management with Pearson eText -- Access Card -- for Operations Management: Processes and Supply Chains
Additional Business Textbook Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Business in Action (8th Edition)
Operations and Supply Chain Management 9th edition
- The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Normal Time Crash Time Cost to Crash Immediate Activity (weeks) (weeks) ($ per week) Predecessor(s) А 5 4 200 None В 9 8. 300 None C 4 200 А 4 2 250 A 3 3 В F 3 С, D G 3 1 150 D, E 7 350 F 4 4 G Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) Time according to schedule (weeks) Time according to schedule (weeks) Activity Activity A В G C H Earrow_forwardConnect HW Q1arrow_forwardChuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of workarrow_forward
- The following table shows the various activities of the development of a new product in your organization. Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 3 2 B A 1 2 3 2 3 C A 1 2.05 4 2.2 4 D B 4 5 6 5 5 E B 3 4 5 4 6 F C 2 3 4 3 7 G D 1.2 2 4 2.2 8 H E,F, G 3 4 6 4.167 9 I H 3 4 5 4 10 J I 2 1 3 1.5 Questions: Draw the PERT network from the given data. (arrow_forward3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…arrow_forwardIn project management why is float important?arrow_forward
- The following table shows the various activities of the development of a new product in your organization. Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 2 B A 1 2 ? 2 3 C A 1 ? 4 2.2 4 D B ? 5 6 5 5 E B 3 ? 5 4 6 F C 2 3 ? 3 7 G D ? 2 4 2.2 8 H E,F, G 3 4 6 ? 9 I H 3 ? 5 4 10 J I 2 1 3 ? Questions: Calculate ALL the missing (?) data points. Draw the PERT network from the given data. Determine ALL the paths, the critical path and its total duration in days. Explain the limitations…arrow_forwardWhat is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 9 7 7 6 5 4 6 4 9 6 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ NORMAL COST 200 800 600 1,100 1,200 CRASH COST 300 875 675 1,300 1,875 IMMEDIATE PREDECESSOR(S) (enter your response as a whole number). A, B Carrow_forwardalso determined that if there are no resource constraints, the project should be complete in 30 working days. Table Q6-1: Precedence Relations and Durations for a Nine Activity Project Activity Predecessor ID A B C D E F G H I DABCDEF ID Description Site clearing Removal of trees General excavation Grading general area Excavation for trenches G H I Placing formwork and reinforcement for concrete Installing sewer lines Installing other utilities Pouring concrete Required 2 2 2 2 2 2 2 2 4 0 0 None None A A B,C B,C D,E D,E F,G 4 4 12 12 21 21 24 Table Q6-2: Resources Required and Starting Times for a Nine Activity Project Activity Workers Earliest Start Time Latest Start Time 0 9 4 15 13 2222 12 25 24 Duration (days) 4 3 [Total 2000 w 8 7 9 12 2 5 6 Given that only four workers are available for the project, determine the shortest possible time in which you can undertake this project. Draw a Gantt chart to show how you have arrived at your final schedule.arrow_forward
- Describe Long Term High Priority Objectives.arrow_forwardThe table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. . Normal Time Crash Time Cost to Crash Immediate Activity (weeks) (weeks) Predecessor(s) (S per week) 300 A 4 None None B 4 50 C 6. 300 250 A E 1 B. C.D D, E 4 200 H. 4 2 200 2. Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as whole numbers.) 777arrow_forwardQ3.When we start a project how we know this project or program is feasible for our future? Explain with help of diagramarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.