OPERATIONS MANAGEMENT W/ CNCT+
OPERATIONS MANAGEMENT W/ CNCT+
12th Edition
ISBN: 9781259574931
Author: Stevenson
Publisher: MCG CUSTOM
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 6, Problem 8P

A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following:

a. Construct the precedence diagram.

b. Assign tasks according to the most following tasks rule. Break ties with the greatest positional weight rule.

c. Assign tasks according to the greatest positional weight rule. Break ties with the most following tasks rule.

d. Compute the balance delay for each rule. Which one yields the better set of assignments in this instance?

Chapter 6, Problem 8P, A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the

a)

Expert Solution
Check Mark
Summary Introduction

To draw: The precedence diagram.

Introduction:

Process selection:

It is the tactical choices made by a firm in picking the kind of production procedure to be followed in the process of production. The process is selected after reviewing many numbers of criteria and constraints.

Answer to Problem 8P

Precedence diagram:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 6, Problem 8P , additional homework tip  1

Explanation of Solution

Given information:

Task Task time (Minutes) Immediate predecessor
a 0.5 Nil
b 1.4 a
c 1.2 a
d 0.7 a
e 0.5 b, c
f 1 d
g 0.4 e
h 0.3 g
i 0.5 f
j 0.8 e, i
k 0.9 h, j
m 0.3 k

Number of minutes per day = 400

Desired output per day = 200 units

Precedence diagram:

OPERATIONS MANAGEMENT W/ CNCT+, Chapter 6, Problem 8P , additional homework tip  2

The precedence diagram is drawn circles and arrows. The tasks are represented in circles and weights for each task are represented outside the circle. The arrows are represented to show which task is preceding the other task and so on.

b)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks on the basis of most following tasks.

Introduction:

Process selection:

It is the tactical choices made by a firm in picking the kind of production procedure to be followed in the process of production. The process is selected after reviewing many numbers of criteria and constraints.

Explanation of Solution

Given information:

Task Task time (Minutes) Immediate predecessor
a 0.5 Nil
b 1.4 a
c 1.2 a
d 0.7 a
e 0.5 b, c
f 1 d
g 0.4 e
h 0.3 g
i 0.5 f
j 0.8 e, i
k 0.9 h, j
m 0.3 k

Number of minutes per day = 400

Desired output per day = 200 units

Calculation of cycle time:

The cycle time is calculated by dividing the operating time per day by the desired output per day.

Cycle time=400200=2 minutes / unit

The number of following tasks, calculation of positional weight for each task is shown below.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight
a b, c, d, e, f, g, h, i, j, k, m 11 0.5 + 1.4 + 1.2 + 0.7 + 0.5 + 1 + 0.4 + 0.3 + 0.5 + 0.8 + 0.9 + 0.3 8.5
b e, g, h, j, k, m 6 1.4 + 0.5 + 0.4 + 0.3 + 0.8 + 0.9 + 0.3 4.6
c e, g, h, j, k, m 6 1.2 + 0.5 + 0.4 + 0.3 + 0.8 + 0.9 + 0.3 4.4
d f, i, j, k, m 5 0.7 + 1 + 0.5 + 0.8 + 0.9 + 0.3 4.2
e g, h, j, k, m 5 0.5 + 0.4 + 0.3 + 0.8+ 0.9 + 0.3 3.2
f i, j, k, m 4 1 + 0.5 + 0.8 + 0.9 + 0.3 3.5
g h, k, m 3 0.4 + 0.3 + 0.9 + 0.3 1.9
h  k, m 2 0.3 + 0.9 + 0.3 1.5
i j, k, m 3 0.5 + 0.8 0.9 + 0.3 2.5
j  k, m 2 0.8 + 0.9 + 0.3 2
k m 1 0.9 + 0.3 1.2
m Nil 0 0.3 0.3

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
2
1 a a 0.5 1.5 Task 'a' is the only eligible task available
b, c, d b 1.4 0.1 Task 'b' has the highest positional weight
c, d None 0.1 (Idle time) The task time is greater than the unassigned cycle time.
2
2 c, d c 1.2 0.8 Task 'c' has more following tasks
d, e d 0.7 0.1 Task 'd' has the highest positional weight
e, f None 0.1 (Idle time) The task time is greater than the unassigned cycle time.
2
3 e, f e 0.5 1.5 Task 'e' has more following tasks
f, g f 1 0.5 Task 'f' has more following tasks
g, i i 0.5 0 Task 'i' has the highest positional weight
2
4 g, j g 0.4 1.6 Task 'g' has more following tasks
h, j j 0.8 0.8 Task 'j' has the highest positional weight
h h 0.3 0.5 Task 'h' is the only eligible task available
k None 0.5 (Idle time) The task time is greater than the unassigned cycle time.
2
5 k k 0.9 1.1 Task 'k' is the only eligible task available
m m 0.3 0.8 Task 'm' is the only task remaining
0.8 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b 1.9 0.1
2 c, d 1.9 0.1
3 e, f, i 2 0
4 g, j, h 1.5 0.5
5 k, m 1.2 0.8

c)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks on the basis of greatest positional weight.

Introduction:

Process selection:

It is the tactical choices made by a firm in picking the kind of production procedure to be followed in the process of production. The process is selected after reviewing many numbers of criteria and constraints.

Explanation of Solution

Given information:

Task Task time (Minutes) Immediate predecessor
a 0.5 Nil
b 1.4 a
c 1.2 a
d 0.7 a
e 0.5 b, c
f 1 d
g 0.4 e
h 0.3 g
i 0.5 f
j 0.8 e, i
k 0.9 h, j
m 0.3 k

Number of minutes per day = 400

Desired output per day = 200 units

Calculation of cycle time:

The cycle time is calculated by dividing the operating time per day by the desired output per day.

Cycle time=400200=2 minutes / unit

The number of following tasks, calculation of positional weight for each task is shown below.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight
a b, c, d, e, f, g, h, i, j, k, m 11 0.5 + 1.4 + 1.2 + 0.7 + 0.5 + 1 + 0.4 + 0.3 + 0.5 + 0.8 + 0.9 + 0.3 8.5
b e, g, h, j, k, m 6 1.4 + 0.5 + 0.4 + 0.3 + 0.8 + 0.9 + 0.3 4.6
c e, g, h, j, k, m 6 1.2 + 0.5 + 0.4 + 0.3 + 0.8 + 0.9 + 0.3 4.4
d f, i, j, k, m 5 0.7 + 1 + 0.5 + 0.8 + 0.9 + 0.3 4.2
e g, h, j, k, m 5 0.5 + 0.4 + 0.3 + 0.8+ 0.9 + 0.3 3.2
f i, j, k, m 4 1 + 0.5 + 0.8 + 0.9 + 0.3 3.5
g h, k, m 3 0.4 + 0.3 + 0.9 + 0.3 1.9
h  k, m 2 0.3 + 0.9 + 0.3 1.5
i j, k, m 3 0.5 + 0.8 0.9 + 0.3 2.5
j  k, m 2 0.8 + 0.9 + 0.3 2
k m 1 0.9 + 0.3 1.2
m Nil 0 0.3 0.3

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
2
1 a a 0.5 1.5 Task 'a' is the only eligible task available
b, c, d b 1.4 0.1 Task 'b' has the highest positional weight
c, d None 0.1 (Idle time) The task time is greater than the unassigned cycle time.
2
2 c, d c 1.2 0.8 Task 'c' has the highest positional weight
d, e d 0.7 0.1 Task 'd' has the highest positional weight
e, f None 0.1 (Idle time) The task time is greater than the unassigned cycle time.
2
3 e, f f 1 1 Task 'f' has the highest positional weight
e, i e 0.5 0.5 Task 'e' has the highest positional weight
g, i i 0.5 0 Task 'g' has the highest positional weight
2
4 g, j j 0.8 1.2 Task 'j' has the highest positional weight
g g 0.4 0.8 Task 'g' is the only eligible task available
h h 0.3 0.5 Task 'h' is the only eligible task available
k None 0.5 (Idle time) The task time is greater than the unassigned cycle time.
2
5 k k 0.9 1.1 Task 'k' is the only eligible task available
m m 0.3 0.8 Task 'm' is the only task remaining
0.8 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b 1.9 0.1
2 c, d 1.9 0.1
3 f, e, i 2 0
4 j, g, h 1.5 0.5
5 k, m 1.2 0.8

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The balance delay.

Introduction:

Process selection:

It is the tactical choices made by a firm in picking the kind of production procedure to be followed in the process of production. The process is selected after reviewing many numbers of criteria and constraints.

Answer to Problem 8P

The balance delay for most following tasks and greatest positional weight rule is 15%.

Explanation of Solution

The balance delay is also known as the percentage of idle time.

Formula to calculate percentage of idle time:

Idle time=Total idle timeNumber of workstations×Cycle time×100

Calculation of percentage of idle time:

Most following tasks:

Idle time=0.1+0.1+0+0.5+0.85×2×100=1.510×100=0.15×100=15%

The percentage of idle time is 15%.

Greatest positional weight:

Idle time=0.1+0.1+0+0.5+0.85×2×100=1.510×100=0.15×100=15%

The percentage of idle time is 15%.

The balance delay for most following tasks and greatest positional weight rule is 15%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Produce a 3000 report with references on one international organization of your choice and Address the following: Provide a brief introduction of the organisation and sector it operates in, including its mission and vision statements, its core values, a summary of its financial performance and a general overview of the business’s operational activities. From the relevant literature explain the Total Quality Management (TQM) processes the chosen organization follows and identify one quality challenge/issue that the organization faced or is currently facing. Explain how the organization managed/or still managing the particular quality challenge/issue. Critically analyze whether the organization failed or succeeded in achieving and maintaining quality performance. Provide a few critical recommendations for business managers in order to highlight the importance of Total Quality Management (TQM) within an organization.
問題2 Production system design involves determining the arrangement of workstations and the... O allocation of resources to workstations design of the process O production schedule all of the above
Elaborate on the need for and the benefits of an effective supply chain management (SCM) system in the context of a globalized and networked economy. In your answer, explain how organizations like Dell and Hewlett-Packard leverage supply chain networks to maintain competitiveness, and analyse the impact of globalization, technological advancements, and business environment changes on supply chain structures. Additionally, evaluate the key components of SCM, including distribution network configuration, inventory management, and cash-flow management, and discuss how these components contribute to creating an effective and integrated supply chain. (15) 3.2. Critically evaluate the requirements for effective inventory management within an organization. In your answer, discuss the importance of inventory accounting systems, the role of cost information (holding, ordering, and shortage costs), and the significance of classification systems like ABC analysis. Additionally, analyse how…

Chapter 6 Solutions

OPERATIONS MANAGEMENT W/ CNCT+

Ch. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
  • Text book image
    Principles of Management
    Management
    ISBN:9780998625768
    Author:OpenStax
    Publisher:OpenStax College
    Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Principles of Management
Management
ISBN:9780998625768
Author:OpenStax
Publisher:OpenStax College
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY