Operations Management: Processes And Supply Chains (12th Edition) (what's New In Operations Management)
12th Edition
ISBN: 9780134742205
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Question
Chapter 6, Problem 6P
a.
Summary Introduction
Interpretation:The number of containers required for holding gadjits needs to be determined.
Concept Introduction:Just in time is an inventory management system used to maintain the inventory levels by reducing the holding cost or any other costs associated with it.
b.
Summary Introduction
Interpretation: The number of containers required for holding widjits needs to be determined.
Concept Introduction: Just in time is an inventory management system used to maintain the inventory levels through reducing the holding cost or any other costs associated with it.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Harvey Motorcycle Company produces three models:the Tiger, a sure-footed dirt bike; the LX2000, a nimble café racer; and the Golden, a large interstate tourer. This month’s master production schedule calls for the production of 54 Goldens, 42 LX2000s, and 30 Tigers per 7-hour shift.a. What average cycle time is required for the assembly line to achieve the production quota in 7 hours?b. If mixed-model scheduling is used, how many of each model will be produced before the production cycle is repeated?c. Determine a satisfactory production sequence for the ultimate in small-lot production: one unit.d. The design of a new model, the Cheetah, includes features from the Tiger, LX2000, and Golden models. The resulting blended design has an indecisive character and is expected to attract some sales from the other models. Determine a mixed-model schedule resulting in 52 Goldens,39 LX2000s, 26 Tigers, and 13 Cheetahs per 7-hour shift. Although the total number of motorcycles produced per…
The Harvey Motorcycle Company produces three models:the Tiger, a sure-footed dirt bike; the LX2000, a nimble caféracer; and the Golden, a large interstate tourer. This month’smaster production schedule calls for the production of 54Goldens, 42 LX2000s, and 30 Tigers per 7-hour shift.a. What average cycle time is required for the assembly lineto achieve the production quota in 7 hours?b. If mixed-model scheduling is used, how many of eachmodel will be produced before the production cycle isrepeated?c. Determine a satisfactory production sequence for the ulti-mate in small-lot production: one unit.
The Harvey Motorcycle Company produces three models: the Tiger,
a sure-footed dirt bike; the LX2000, a nimble cafe racer; and the Golden, a
large interstate tourer. The month's master production schedule calls for the
production of 36 Goldens, 26 LX2000s, and 34 Tigers per 10-hour shift.
What average cycle time is required for the assembly line to achieve the
production quota in 10 hours? hours per motorcycle. (Enter your response
rounded to three decimal places.)
Chapter 6 Solutions
Operations Management: Processes And Supply Chains (12th Edition) (what's New In Operations Management)
Knowledge Booster
Similar questions
- The following information describes a manufacturing system: Daily demand is 1,025 units. Replenishment lead time is 1.5 days. A 2.5 day safety stock is desired. Products are stored in containers that hold 940 units. How many kanban containers are needed for this system?arrow_forwardIt takes Aaron 15 minutes to produce 10 widgets to fill acontainer and 5 minutes to transport the container to thenext station, where Maria works. Maria’s process takesabout 30 minutes. The factory uses a safety factor of 20%.Currently, five kanbans rotate between Aaron and Maria’sstations. What is the approximate demand for widgets?arrow_forwardThe welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data: The daily demand is 2000 units. The production lead time is 4 days (this includes processing time, transport time, and waiting time). Management has decided to have 1 day of safety stock. One container fits 400 units. How many kanban containers will be needed to support this system?arrow_forward
- In what type of environment is lean production mostsuccessful?arrow_forwardOperations Management Hinge Manufacturing Company employs a Kanban system for a component part. The daily demand is 900 hinges. Each container has a wait time of 0.05/day and a processing time of 0.37 days. The Container size is 60 hinges and the safety factor (a) is 10%. A: How many Kanban card sets should be authorized? B: What is the maximum inventory of this hinge in the system?arrow_forwardCarol Cagle has a repetitive manufacturing plant producing trailer hitches in Arlington, Texas. The plant has an average inventory turnover of only 12 times per year. He has therefore determined that he will reduce his component lot sizes. He has developed the following data for one component, the safety chain clip: Setup labor cost Annual holding cost Daily production Annual demand Desired lot size To obtain the desired lot size, the set-up time that should be achieved = $25 per hour $15 per unit 960 units/8 hour day 30,000 (250 days each x daily demand of 120 units) 120 units (one hour of production) minutes (round your response to two decimal places).arrow_forward
- Why would a lean production manufacturer schedule 7 hours of work in an 8-hour shift?arrow_forwardHow can lot sizes and inventories be reduced in a lean production system? Discuss specific approaches.arrow_forwardWhat term refers to a schedule that pulls material into i nal assembly at a constant rate?arrow_forward
- Operations Management Lean production is a sociotechnical system (Shah & Ward, 2007) that is viewed as a philosophy that takes care of both technical and cultural aspects (Bhasin & Burch, 2006). Evaluate this statement in detail, and how it can be successfully applied in a manufacturing environment Researchers have noted that the use of JIT enables companies to be more efficient, effective, and more responsive to customer needs as JIT is based on the philosophy of demand-pull and lean manufacturing (Olhager, 2002; Isa & Keong, 2008a). In some cases, companies following JIT principles have been recognized for outstanding performance (Spear, 2002) which is usually achieved by improving the company’s operational performance. Explain this statement in detail including the purpose of JIT. How it can be successfully applied in a manufacturing environment. Relevant recent examples should be provided.arrow_forwardSuppose a final assembly is produced by assembling two components. THE The first component, A, is produced internally and goes through three process steps, which are stamping, forging and machining, with scrap estimates of 10%, 15% and 25%, respectively. For every three produced units of component A, two are used in the final assembly and one is separate to meet spare parts needs. The second component, B, which is used exclusively in final assembly, is purchased from a supplier external and inspected on arrival; 2% do not pass inspection. A unit of the component purchased is required for each final assembly. The final assembly process produces 5% of scraps. Spare parts demands for component A and final Su assembly match to 1,000 and 5,000 units, respectively. How many input units are needed for produce component A, and how many units of component B should the firm buy?arrow_forwardPauline Found Manufacturing, Inc., is moving to kanbans to support its telephone switching-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost Annual holding cost Daily production Annual usage $30 $120 per subassembly 20 subassemblies 4,500 (50 weeks x5 days each x daily usage of 18 subassemblies) 10 days Lead time: Safety stock 3 days' production Kanban container size = 150 units (round your response to the nearest whole number). Number of kanbans needed = 2 kanbans (round your response to the nearest whole number)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.