OPERATIONS+SUPPLY CHAIN...:CORE >INTL<
OPERATIONS+SUPPLY CHAIN...:CORE >INTL<
5th Edition
ISBN: 9781260547627
Author: Jacobs
Publisher: MCG
bartleby

Concept explainers

Question
Book Icon
Chapter 6, Problem 6OQ

a)

Summary Introduction

To determine: The estimate of the learning rate.

Introduction: It is the rate to measure the performance of the person in the new skills and in gaining experiences.

a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS+SUPPLY CHAIN...:CORE >INTL<, Chapter 6, Problem 6OQ , additional homework tip  1

Estimate the learning rate for Unit 1 to Unit 2:

It is calculated by dividing the time taken to complete the second unit and first unit.

Learning percentage=Time taken to complete second unitTime taken to complete first unit=1012=83.33%

Hence, the learning percentage is 83.33%.

Estimate the learning rate for Unit 2 to Unit 4:

It is calculated by dividing the time taken to complete the fourth unit and second unit.

Learning percentage=Time taken to complete fourth unitTime taken to complete second unit=6.510=65%

Hence, the learning percentage is 65%.

Estimate the learning rate for Unit 4 to Unit 8:

It is calculated by dividing the time taken to complete the eighth unit and fourth unit.

Learning percentage=Time taken to complete eighth unitTime taken to complete fourth unit=3.66.5=55.38%

Hence, the learning percentage is 55.38%.

Estimate the learning rate for Unit 8 to Unit 16:

It is calculated by dividing the time taken to complete the eighth unit and fourth unit.

Learning percentage=Time taken to complete sixteenth unitTime taken to complete eighth unit=2.73.6=75%

Hence, the learning percentage is 75%.

Determine the average learning rate:

Average learning rate=83.33%+65%+55.38%+75%4=278.714=69.68%70%

Hence, the average learning rate is 70%.

b)

Summary Introduction

To determine: The bid that Company L should submit for the total order of 100 units.

Introduction: It is the rate to measure the performance of the person in the new skills and in gaining experiences.

b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS+SUPPLY CHAIN...:CORE >INTL<, Chapter 6, Problem 6OQ , additional homework tip  2

Determine the average learning rate:

Average learning rate=83.33%+65%+55.38%+75%4=278.714=69.68%70%

Hence, the average learning rate is 70%.

Determine the bid that Company L should submit for the total order of 100 units:

It is computed by subtracting the cumulative value for 20 units from cumulative value for 120 units and multiplying it with the cost to produce the first unit.

Cost to produce100 more units}=(Cumulative value for 120 unitsCumulative value for 20 units)×(Cost to producefirst unit)=(19.5707.407)×$12 million=12.163×$12 million=$145,956,000

The cumulative values can be determined using the table of cumulative values. For example, 19.570 is the cumulative value for 120 units and 70% learning rate.

Hence, the bid that Company L should submit for the total order of 100 units is $145,956,000.

c)

Summary Introduction

To determine: The expected cost for the last unit under the learning rate.

Introduction: It is the rate to measure the performance of the person in the new skills and in gaining experiences.

c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

OPERATIONS+SUPPLY CHAIN...:CORE >INTL<, Chapter 6, Problem 6OQ , additional homework tip  3

Determine the average learning rate:

Average learning rate=83.33%+65%+55.38%+75%4=278.714=69.68%70%

Hence, the average learning rate is 70%.

Determine the expected cost for the last unit under the learning rate:

It is computed by multiplying the cumulative value for 120 units with the cost to produce one unit.

Cost to produce120th unit}=Cumulative value for 120 units×(Cost to producefirst unit)=0.0851×$12 million=$1,021,200

The cumulative values can be determined using the table of cumulative values. For example, .0062 is the cumulative value for 120 units and 70% learning rate.

Hence, the expected cost to produce 120th units is $1,021,200.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Simulation To start the simulation, review all communication and documents. You will find key information to assist your success in the simulation. Actual Demand in Previous Months 15K MAPE: 0% Demand 10K 5K Regular Midgrade 0% 0% 0 January 2025 (24 Month Remaining) ՈՐ AUG o Make a Forecast Current Decision Past Decision Forecast for January 2025 Sept Month Range 00 Oct Nov Dec Use Al REGULAR ↓ 0 t Gallons (3 chances) MIDGRADE 1 Gallons Forecast demand can not be less than 100! Answer Price Prediction: M Possible increase in January 2025 Regular + Midgrade
A company operates a manufacturing plant that produces two products, A and B. The plant has the following capacity data: Design Capacity: 15,000 machine hours per month Effective Capacity: 12,000 machine hours per month Actual Output (Utilized Capacity): 10,000 machine hours per month Additionally, the plant produces Product A and Product B, with the following production data: Product          Demand (Units)       Processing Time (hours per unit)                  Contribution Margin ($ per unit)   A                      3,000                                2.5                                                                   40     B                  4,000                                 1.5                                                                     30 Calculate the plant’si.Capacity Utilization ii. Effective Capacity Utilization iii. Efficiency. Interpret the results. Compute the total machine hours required to meet full demand for both products. Determine whether the…
while making reference to the cartesian method demonstrate how being skepital has helped you transcend cultural, societal and social conditioning. Use practical example from your life as a kenya and student at university to demonstrate your answer?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.