a. AOA network diagram:

Explanation of Solution

Draw an Activity on Arrow (AOA) network diagram representing the project given in Table 6.2 of the book. To accomplish the network diagram, follow the following steps:-

1. Put the node numbers 1 to 9 in circles.

2. Find all of the activities that start at node 1. Draw arrows between node 1 and those finish nodes. Put the activity letter and duration estimate on the associated arrow. In this case, Draw an edge from node 1 to 2 and label it as A=2. Label A=2 means activity A has a duration of 2 days.

3. Continue drawing the project network diagram until all activities are included on the diagrams that have dependencies.

4. Label each arrow with the activity letter and estimated time. The below network diagram has 11 arrows corresponding to 11 rows in the table.

  • Draw second edge from node 2 to 3 and label it as B=2...

b. All paths on the network diagram:

Explanation of Solution

To identify all the paths on the network diagram, just follow the arrows to identify distinct routes from node 1 to node 9.

To find out length of each path, just add the duration for all activities on that path.

...
Path NoRouteLength / Total Duration

c. Critical path for this project

Explanation of Solution

The longest path in the network diagram is the critical path...

d. Shortest possible time needed to complete this project:

Explanation of Solution

The critical path represents the shortest time requir...

Blurred answer
Students have asked these similar questions
Hi, please solve this trying to follow this criteria. (use Keil) Abstract describing the requirements and goals of the assignment. List file with no errors or warnings. Brief description of your implementation design and code. Debugging screen shots for different scenarios with your reference and comments. Conclusion
Can you solve using iterative expansion
using r language
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Enhanced Discovering Computers 2017 (Shelly Cashm...
Computer Science
ISBN:9781305657458
Author:Misty E. Vermaat, Susan L. Sebok, Steven M. Freund, Mark Frydenberg, Jennifer T. Campbell
Publisher:Cengage Learning
Text book image
Systems Analysis and Design (Shelly Cashman Serie...
Computer Science
ISBN:9781305494602
Author:Scott Tilley, Harry J. Rosenblatt
Publisher:Cengage Learning
Text book image
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning