Traffic and Highway Engineering
Traffic and Highway Engineering
5th Edition
ISBN: 9781305156241
Author: Garber, Nicholas J.
Publisher: Cengage Learning
bartleby

Concept explainers

Question
Book Icon
Chapter 6, Problem 20P
To determine

(a)

The maximum queue length that will be formed, total delay, number of vehicles that will be affected by the incident, the average individual delay for the expected demand flow of 70%of the capacity of the highway.

Expert Solution
Check Mark

Answer to Problem 20P

For 70 % expected demand flow:

Themaximum queue length that will be formed is qmax=400Veh.

The total delay is dr=445hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 0.0412hr.

Explanation of Solution

Given:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering, Chapter 6, Problem 20P , additional homework tip  1

Calculation:

For the expected 70 % demand flow:

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 70 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 70%of6000)4000)2qmax=(( 6000× 70 100 )4000)2

  qmax=(( 60×70)4000)2qmax=(42004000)2qmax=400Veh.

The maximum queue length that will be formed is qmax=400Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=22( 70%of60004000)( 60004000)2( 600070%of6000)

  dr=4(42004000)(2000)2(60004200)

  dr=4( 100)( 2000)(1800)dr=40009

  dr=444.44=445hr.

The total delay is dr=445hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.=10800Veh.

The number of vehicles that will be affected by the incident is 10800Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =44510800.=0.0412hr.

The average individual delay is 0.0412hr.

Conclusion:

Therefore, for 70 % expected demand flow:

Themaximum queue length that will be formed is qmax=400Veh, the total delay is dr=445hr,

The number of vehicles that will be affected by the incident is 10800Veh and the average individual delay is 0.0412hr.

To determine

(b)

The maximum queue length that will be formed, total delay, number of vehicles that will be affected by the incident, the average individual delay for the expected demand flow of 75%of the capacity of the highway.

Expert Solution
Check Mark

Answer to Problem 20P

For 75 % expected demand flow:

Themaximum queue length that will be formed is qmax=1000Veh.

The total delay is dr=1334hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 0.1235hr.

Explanation of Solution

Given:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering, Chapter 6, Problem 20P , additional homework tip  2

Calculation:

For the expected 75 % demand flow:

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 75 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 75%of6000)4000)2qmax=(( 6000× 75 100 )4000)2qmax=(( 60×75)4000)2qmax=(45004000)2qmax=1000Veh.

Themaximum queue length that will be formed is qmax=1000Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=22( 75%of60004000)( 60004000)2( 600075%of6000)dr=4( 45004000)( 2000)2( 60004500)dr=4( 500)( 2000)3000dr=8( 500)3dr=1333.33=1334hr.

The total delay is dr=1334hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.=10800Veh.

The number of vehicles that will be affected by the incident is 10800Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =133410800.=0.1235hr.

The average individual delay is 0.1235hr.

Conclusion:

For 75 % expected demand flow:

Themaximum queue length that will be formed is qmax=1000Veh, the total delay is dr=1334hr, the number of vehicles that will be affected by the incident is 10800Veh and the average individual delay is 0.1235hr.

To determine

(c)

The maximum queue length that will be formed, total delay, number of vehicles that will be affected by the incident, the average individual delay for the expected demand flow of 80% of the capacity of the highway.

Expert Solution
Check Mark

Answer to Problem 20P

For 80 % expected demand flow:

Themaximum queue length that will be formed is qmax=1600Veh.

The total delay is dr=2667hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 0.247hr.

Explanation of Solution

Given:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering, Chapter 6, Problem 20P , additional homework tip  3

Calculation:

For the expected 80 % demand flow:

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 80 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 80%of6000)4000)2qmax=(( 6000× 80 100 )4000)2qmax=(( 60×80)4000)2qmax=(48004000)2qmax=1600Veh.

The maximum queue length that will be formed is qmax=1600Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=22( 48004000)( 60004000)2( 60004800)dr=4( 800)( 2000)2( 1200)dr=4( 800)( 20)24dr=2666.66hr.dr=2667hr.

The total delay is dr=2667hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.=10800Veh.

Therefore, the number of vehicles that will be affected by the incident is 10800Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =266710800.=0.247hr.

The average individual delay is 0.247hr.

Conclusion:

For 80 % expected demand flow:

Themaximum queue length that will be formed is qmax=1600Veh, the total delay is dr=2667hr, the number of vehicles that will be affected by the incident is 10800Veh and

the average individual delay is 0.247hr.

To determine

(d)

The maximum queue length that will be formed, total delay, number of vehicles that will be affected by the incident, the average individual delay for the expected demand flowof 85% of the capacity of the highway.

Expert Solution
Check Mark

Answer to Problem 20P

For 85 % expected demand flow:

Themaximum queue length that will be formed is qmax=2200Veh.

The total delay is dr=4889hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 0.453hr.

Explanation of Solution

Given:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering, Chapter 6, Problem 20P , additional homework tip  4

Calculation:

For the expected 85 % demand flow:

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 85 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 85%of6000)4000)2qmax=(( 6000× 85 100 )4000)2qmax=(( 60×85)4000)2qmax=(51004000)2qmax=2200Veh.

Therefore, the maximum queue length that will be formed is qmax=2200Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=22( 85%of60004000)( 60004000)2( 60005100)dr=4( 51004000)( 2000)2( 900)dr=4( 1100)( 20)18dr=4888.88hr.dr=4889hr.

Therefore, the total delay is dr=4889hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.00.=10800Veh.

The number of vehicles that will be affected by the incident is 10800Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =488910800.=0.453hr.

the average individual delay is 0.453hr.

The graph of average individual delay versus the expected demand flow is as follows:

  Traffic and Highway Engineering, Chapter 6, Problem 20P , additional homework tip  5

Conclusion:

For 85 % expected demand flow:

Themaximum queue length that will be formed is qmax=2200Veh, the total delay is dr=4889hr, the number of vehicles that will be affected by the incident is 10800Veh and

the average individual delay is 0.453hr.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
subject
In one of the construction projects, a bulldozer is used for a weekly rent of $150, with a work rate of 10 hours per day, 50 minutes per hour, and 6 days per week. If you know that the dimensions of the bulldozer blade are 3 lengths and 1 m height, the slope of the pushed soil is (1:1), its speed when loaded is 45 m/min and when returning is 80 m/min, and the time for loading, unloading, and changing is 0.35 minutes, the transported soil is sandy, weighing 1650 kg/m3 by Bank volume and 1300 kg/m3 by loose volume, the transport distance is 300 m. If you know that using a tractor shovel costs $0.5 per m3, ma a decision about choosing the economical equipment to use in the project.
/ An irrigation project requires digging and paving an irrigation canal with alength of (30 km) and a semi-circular section with a diameter of (8 m). The work mustmbe completed within one year, and in the event of delay, a fine delay of $200/day. You have two options for work: 1st Option: using standard equipment (excavators, graders and hand labor) had a cost of $10/m3, the job will be finish without delay. 2nd Option: Use a channel trimmer machine with the following specifications: Purchase price ($70,000), it can be sold after its economic life of (5 years) for ($30,000), its speed (10m/hr), engine diesel with (250 hp) and its work 48 minutes/hr, capacity of crankcase is (50 liters), the number of hours between changing the oil (100 hr), the maintenance cost is (80%) of its depreciation, the price of one liter of fuel ($0.5/liter) and of oil ($1/liter), the operators' wages ($15,000/year), annual operating hours (2000 hr), and the owner must pay taxes of 10% of the average value of…
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning