Question
Book Icon
Chapter 6, Problem 19P
To determine

The graph of average individual delay versus the repair period and use this graph to discuss the effect of the expected repair time on the average delay.

Expert Solution & Answer
Check Mark

Explanation of Solution

Given:

We have been given the following information:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering, Chapter 6, Problem 19P , additional homework tip  1

Calculation:For the expected repair period of 1 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Themaximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=12( 90%of60004000)( 60004000)2( 60005400)

  dr=(54004000)(2000)2(600)

  dr=( 1400)( 20)12dr=2333.33=2334hr.

The total delay is dr=2334hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be foundusing the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×1.=5400Veh.

The number of vehicles that will be affected by the incident is 5400Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =23345400.=0.432hr.

The average individual is 0.432hr.

For the expected repair period of 1.5 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Themaximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 1.52( 90%of60004000)( 60004000)2( 60005400)dr=2.25( 54004000)( 2000)2( 600)dr=2.25( 1400)( 20)12dr=5250hr.

The total delay is dr=5250hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×1.5.=8100Veh.

The number of vehicles that will be affected by the incident is 8100Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =52508100.=0.648hr.

Theaverage individualdelay is 0.648hr.

For the expected repair period of 2.5 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

The maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 2.52( 90%of60004000)( 60004000)2( 60005400)dr=6.25( 54004000)( 2000)2( 600)dr=6.25( 1400)( 20)12dr=14583.33hr.dr=14584hr.

The total delay is dr=14584hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.5.=13500Veh.

Therefore, the number of vehicles that will be affected by the incident is 13500Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =1458413500.=1.0803hr.

The average individualdelay is 1.0803hr.

For the expected repair period of 2.75 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Therefore, the maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 2.752( 90%of60004000)( 60004000)2( 60005400)dr=7.5625( 54004000)( 2000)2( 600)dr=7.5625( 1400)( 20)12dr=17645.83hr.dr=17646hr.

Therefore, the total delay is dr=17646hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.75.=14850Veh.

The number of vehicles that will be affected by the incident is 14850Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =1764614850.=1.188hr.

the average individual delay is 1.188hr.

For the expected repair period of 3.0 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

The maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 3.02( 90%of60004000)( 60004000)2( 60005400)dr=9.0( 54004000)( 2000)2( 600)dr=9.0( 1400)( 20)12dr=21000.00hr.

The total delay is dr=21000.00hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×3.00.=16200Veh.

The number of vehicles that will be affected by the incident is 16200Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =2100016200.=1.30hr.

The average individual delay is 1.30hr.

Plot the graph of average individual delay versus the repair period is as follows:

  Traffic and Highway Engineering, Chapter 6, Problem 19P , additional homework tip  2

Conclusion:

Therefore, for 1.0 hour : Themaximum queue length that will be formed is qmax=2800Veh, total delay is dr=2334hr ,number of vehicles that will be affected by the incident is 5400Veh and theaverage individual is 0.432hr.

For 1.5hour:

Themaximum queue length that will be formed is qmax=2800Veh ,total delay is dr=5250hr ,number of vehicles that will be affected by the incident is 8100Veh and the average individual is 0.648hr.

For 2.50hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=14584hr.

The number of vehicles that will be affected by the incident is 13500Veh.

The average individual delayis 1.0803hr.

For 2.75hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=9334hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 1.188hr.

For 3.0 hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=21000.00hr.

The number of vehicles that will be affected by the incident is 16200Veh.

The average individual delay is 1.30hr.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Example 5.2: Design Example of a Square Foundation for a Colum Figure A.3a shows a square column foundation with the followin conditions: Live load=L=675 kN Dead load D= 1125 kN Allowable gross soil-bearing capacity 145 kN/m² Column size-0.5 m x 0.5 m -20.68 MN/m² 1,413.7 MN/m² Let it be required to design the column foundation. 1.25m-D L-675 AN D-1125 AN (a) Column section- 05 m x 0.5m
Example 5.3: Design Example of a Rectangular Foundation for Column This section describes the design of a rectangular foundation to support a column having dimensions of 0.4 m x 0.4 m in cross section. Other details are as follows: Dead load D= 290 kN Live load L= 110 kN Depth from the ground surface to the top of the foundation = 1.2 m Allowable gross soil-bearing capacity = 120 kN/m² Maximum width of foundation = B = 1.5 m f, = 413.7 MN/m² f=20.68 MN/m² Unit weight of soil = y = 17.27 kN/m³ Unit weight of concrete = y₁ = 22.97 kN/m³ General Considerations For this design, let us assume a foundation thickness of 0.45 m (Figure A.4a). The weight of foundation/m² = 0.45 y = (0.45) (22.97) = 10.34 kN/m², and the weight of soil above the foundation/m² = (1.2)y = (1.2) (17.27) = 20.72 kN/m² Hence, the net allowable soil- bearing capacity Iqata] =120-10.34-20.72 = 88.94 kN/m² The required area of the foundation = (D+L)/4(all) = (290 + 110)/88.94 = 4.5 m². Hence, the length of the foundation…
Problem 1 You are in the process of designing a water supply system for the whole lligan City, and the design life of your system is to end in the year 2070. The population in the town has been measured every 10 years since 1980 by the Philippine Statistics Authority, and the reported populations are tabulated below. Estimate the population in the town using (a) arithmetic growth projection, (b) geometric growth projection (exponential formula), (c) declining growth projection (assuming a saturation concentration of 480,000 people), and (d) logistic curve projection. Year Population 1980 167,358 1990 226,568 2000 285,061 2010 322,821 2020 342,618
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning