Traffic and Highway Engineering
Traffic and Highway Engineering
5th Edition
ISBN: 9781305156241
Author: Garber, Nicholas J.
Publisher: Cengage Learning
Question
Book Icon
Chapter 6, Problem 19P
To determine

The graph of average individual delay versus the repair period and use this graph to discuss the effect of the expected repair time on the average delay.

Expert Solution & Answer
Check Mark

Explanation of Solution

Given:

We have been given the following information:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering, Chapter 6, Problem 19P , additional homework tip  1

Calculation:For the expected repair period of 1 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Themaximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=12( 90%of60004000)( 60004000)2( 60005400)

  dr=(54004000)(2000)2(600)

  dr=( 1400)( 20)12dr=2333.33=2334hr.

The total delay is dr=2334hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be foundusing the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×1.=5400Veh.

The number of vehicles that will be affected by the incident is 5400Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =23345400.=0.432hr.

The average individual is 0.432hr.

For the expected repair period of 1.5 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Themaximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 1.52( 90%of60004000)( 60004000)2( 60005400)dr=2.25( 54004000)( 2000)2( 600)dr=2.25( 1400)( 20)12dr=5250hr.

The total delay is dr=5250hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×1.5.=8100Veh.

The number of vehicles that will be affected by the incident is 8100Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =52508100.=0.648hr.

Theaverage individualdelay is 0.648hr.

For the expected repair period of 2.5 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

The maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 2.52( 90%of60004000)( 60004000)2( 60005400)dr=6.25( 54004000)( 2000)2( 600)dr=6.25( 1400)( 20)12dr=14583.33hr.dr=14584hr.

The total delay is dr=14584hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.5.=13500Veh.

Therefore, the number of vehicles that will be affected by the incident is 13500Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =1458413500.=1.0803hr.

The average individualdelay is 1.0803hr.

For the expected repair period of 2.75 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

Therefore, the maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 2.752( 90%of60004000)( 60004000)2( 60005400)dr=7.5625( 54004000)( 2000)2( 600)dr=7.5625( 1400)( 20)12dr=17645.83hr.dr=17646hr.

Therefore, the total delay is dr=17646hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.75.=14850Veh.

The number of vehicles that will be affected by the incident is 14850Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =1764614850.=1.188hr.

the average individual delay is 1.188hr.

For the expected repair period of 3.0 hour.

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity and,

  tinc is the duration of the incident.

Considering 90 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 90%of6000)4000)2qmax=(( 6000× 90 100 )4000)2qmax=(( 60×90)4000)2qmax=(54004000)2qmax=2800Veh.

The maximum queue length that will be formed is qmax=2800Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr= 3.02( 90%of60004000)( 60004000)2( 60005400)dr=9.0( 54004000)( 2000)2( 600)dr=9.0( 1400)( 20)12dr=21000.00hr.

The total delay is dr=21000.00hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×3.00.=16200Veh.

The number of vehicles that will be affected by the incident is 16200Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =2100016200.=1.30hr.

The average individual delay is 1.30hr.

Plot the graph of average individual delay versus the repair period is as follows:

  Traffic and Highway Engineering, Chapter 6, Problem 19P , additional homework tip  2

Conclusion:

Therefore, for 1.0 hour : Themaximum queue length that will be formed is qmax=2800Veh, total delay is dr=2334hr ,number of vehicles that will be affected by the incident is 5400Veh and theaverage individual is 0.432hr.

For 1.5hour:

Themaximum queue length that will be formed is qmax=2800Veh ,total delay is dr=5250hr ,number of vehicles that will be affected by the incident is 8100Veh and the average individual is 0.648hr.

For 2.50hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=14584hr.

The number of vehicles that will be affected by the incident is 13500Veh.

The average individual delayis 1.0803hr.

For 2.75hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=9334hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 1.188hr.

For 3.0 hour:

Themaximum queue length that will be formed is qmax=2800Veh.

The total delay is dr=21000.00hr.

The number of vehicles that will be affected by the incident is 16200Veh.

The average individual delay is 1.30hr.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
2.21 A small truck is to be driven down a 4% grade at 70 mi/h. The coefficient of road adhesion is 0.95, and it is known that the braking efficiency is 80% when the truck is empty and decreases by one percentage point for every 100 lb of cargo added. Ignoring aerodynamic resistance, if the driver wants the truck to be able to achieve a minimum theoretical stopping distance of 275 ft from the point of brake application, what is the maximum amount of cargo (in pounds) that can be carried?
An observer standing beside a one-lane road counted in 5 minutes 20 cars traveling at 30 mph, 30 cars traveling at 50 mph and 10 cars traveling at 60 mph. (a) What is the space and time-mean speeds of the observed cars? (b) What is the average headway of the cars? [
2.20 A driver is traveling at 90 mi/h down a 3% grade on good, wet pavement. An accident investigation team noted that braking skid marks started 410 ft before a parked car was hit at an estimated 45 mi/h. Ignoring air resistance, and using theoretical stopping distance, what was the braking efficiency of the car?
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning
Text book image
Solid Waste Engineering
Civil Engineering
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Cengage Learning,
Text book image
Residential Construction Academy: House Wiring (M...
Civil Engineering
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Cengage Learning