(a)
Which of the two alternatives should be selected assuming a 10% rate of interest.

Answer to Problem 31P
The Option to be implemented is Option 2, since it results in a lower
Explanation of Solution
Given information:
Option 1:
Install one cable now for 4000 lines. Installation cost $20,000 and annual maintenance costs would be $1,500.
Option 2:
Install one cable for 2000 lines now and one cable for 2000 lines after 10 years. Installation cost $15,000 and annual maintenance costs would be $1,000.
Rate of interest for calculation: 10%.
Based on the above information, the following tables outlines the
Option 1:
Year | Particulars | Cash flow | Present value Factor @10% | Present value |
0 | Installation Cost | $20,000.00 | 1 | $20,000.00 |
1 | Operating costs | $1,500.00 | 0.9091 | $1,363.64 |
2 | Operating costs | $1,500.00 | 0.8264 | $1,239.67 |
3 | Operating costs | $1,500.00 | 0.7513 | $1,126.97 |
4 | Operating costs | $1,500.00 | 0.6830 | $1,024.52 |
5 | Operating costs | $1,500.00 | 0.6209 | $931.38 |
5 | Operating costs | $1,500.00 | 0.6209 | $931.38 |
6 | Operating costs | $1,500.00 | 0.5645 | $846.71 |
7 | Operating costs | $1,500.00 | 0.5132 | $769.74 |
8 | Operating costs | $1,500.00 | 0.4665 | $699.76 |
9 | Operating costs | $1,500.00 | 0.4241 | $636.15 |
10 | Operating costs | $1,500.00 | 0.3855 | $578.31 |
11 | Operating costs | $1,500.00 | 0.3505 | $525.74 |
12 | Operating costs | $1,500.00 | 0.3186 | $477.95 |
13 | Operating costs | $1,500.00 | 0.2897 | $434.50 |
14 | Operating costs | $1,500.00 | 0.2633 | $395.00 |
15 | Operating costs | $1,500.00 | 0.2394 | $359.09 |
16 | Operating costs | $1,500.00 | 0.2176 | $326.44 |
17 | Operating costs | $1,500.00 | 0.1978 | $296.77 |
18 | Operating costs | $1,500.00 | 0.1799 | $269.79 |
19 | Operating costs | $1,500.00 | 0.1635 | $245.26 |
20 | Operating costs | $1,500.00 | 0.1486 | $222.97 |
21 | Operating costs | $1,500.00 | 0.1351 | $202.70 |
22 | Operating costs | $1,500.00 | 0.1228 | $184.27 |
23 | Operating costs | $1,500.00 | 0.1117 | $167.52 |
24 | Operating costs | $1,500.00 | 0.1015 | $152.25 |
25 | Operating costs | $1,500.00 | 0.0923 | $138.44 |
26 | Operating costs | $1,500.00 | 0.0839 | $125.86 |
27 | Operating costs | $1,500.00 | 0.0763 | $114.42 |
28 | Operating costs | $1,500.00 | 0.0693 | $104.02 |
29 | Operating costs | $1,500.00 | 0.0630 | $94.56 |
30 | Operating costs | $1,500.00 | 0.0573 | $85.96 |
Net cash outflow | $35,071.75 |
Option 2:
Year | Particulars | Cash flow | Present value Factor @10% | Present value |
0 | Installation Cost | $15,000.00 | 1 | $15,000.00 |
1 | Operating costs | $1,000.00 | 0.9091 | $909.09 |
2 | Operating costs | $1,000.00 | 0.8264 | $826.45 |
3 | Operating costs | $1,000.00 | 0.7513 | $751.31 |
4 | Operating costs | $1,000.00 | 0.6830 | $683.01 |
5 | Operating costs | $1,000.00 | 0.6209 | $620.92 |
5 | Operating costs | $1,000.00 | 0.6209 | $620.92 |
6 | Operating costs | $1,000.00 | 0.5645 | $564.47 |
7 | Operating costs | $1,000.00 | 0.5132 | $513.16 |
8 | Operating costs | $1,000.00 | 0.4665 | $466.51 |
9 | Operating costs | $1,000.00 | 0.4241 | $424.10 |
10 | Operating costs | $1,000.00 | 0.3855 | $385.54 |
10 | Installation Cost | $15,000.00 | 0.3855 | $5,783.15 |
11 | Operating costs | $2,000.00 | 0.3505 | $700.99 |
12 | Operating costs | $2,000.00 | 0.3186 | $637.26 |
13 | Operating costs | $2,000.00 | 0.2897 | $579.33 |
14 | Operating costs | $2,000.00 | 0.2633 | $526.66 |
15 | Operating costs | $2,000.00 | 0.2394 | $478.78 |
16 | Operating costs | $2,000.00 | 0.2176 | $435.26 |
17 | Operating costs | $2,000.00 | 0.1978 | $395.69 |
18 | Operating costs | $2,000.00 | 0.1799 | $359.72 |
19 | Operating costs | $2,000.00 | 0.1635 | $327.02 |
20 | Operating costs | $2,000.00 | 0.1486 | $297.29 |
21 | Operating costs | $2,000.00 | 0.1351 | $270.26 |
22 | Operating costs | $2,000.00 | 0.1228 | $245.69 |
23 | Operating costs | $2,000.00 | 0.1117 | $223.36 |
24 | Operating costs | $2,000.00 | 0.1015 | $203.05 |
25 | Operating costs | $2,000.00 | 0.0923 | $184.59 |
26 | Operating costs | $2,000.00 | 0.0839 | $167.81 |
27 | Operating costs | $2,000.00 | 0.0763 | $152.56 |
28 | Operating costs | $2,000.00 | 0.0693 | $138.69 |
29 | Operating costs | $2,000.00 | 0.0630 | $126.08 |
30 | Operating costs | $2,000.00 | 0.0573 | $114.62 |
Net cash outflow | $34,113.33 |
Net present value is the difference of Sum of Present values of cash inflows and Sum of Present values of cash outflows. If the value is positive then the project may be accepted. While evaluation of two or more alternatives takes place, then the proposal with the higher net present value may be selected since it results in a greater
In the given scenario, Present values are calculated by calculating the present values of cash outflows such as installation cost and operating cost.
Present value factor is calculated as 1/1.10 ^ N where N is the year of operation of the refrigerator.
Deferment of capital expenditure to Year 10 in case of Option 2 results in a lower overall cash outflow despite increase in the annual operating costs from years 11-30. This is owing to the present value factor.
Conclusion:
Hence the Option to be implemented is Option 2 since it results in lower overall cash outflow.
(b)
Which of the two alternatives should be selected.

Answer to Problem 31P
The Option to be implemented is Option 1, since it results in a lower cash outflow for a period of 30 years.
Explanation of Solution
Given information:
Option 1:
Install one cable now for 4000 lines. Installation cost $20,000 and annual maintenance costs would be $1,500.
Option 2:
Install one cable for 2000 lines now and one cable for 2000 lines after 5 years. Installation cost $15,000 and annual maintenance costs would be $1,000.
Rate of interest for calculation: 10%.
Based on the above information, the following tables outlines the net present value calculation of the two options.
Option 1:
Year | Particulars | Cash flow | Present value Factor @10% | Present value |
0 | Installation Cost | $ 20,000.00 | 1.00 | $ 20,000.00 |
1 | Operating costs | $ 1,500.00 | 0.91 | $ 1,363.64 |
2 | Operating costs | $ 1,500.00 | 0.83 | $ 1,239.67 |
3 | Operating costs | $ 1,500.00 | 0.75 | $ 1,126.97 |
4 | Operating costs | $ 1,500.00 | 0.68 | $ 1,024.52 |
5 | Operating costs | $ 1,500.00 | 0.62 | $ 931.38 |
5 | Operating costs | $ 1,500.00 | 0.62 | $ 931.38 |
6 | Operating costs | $ 1,500.00 | 0.56 | $ 846.71 |
7 | Operating costs | $ 1,500.00 | 0.51 | $ 769.74 |
8 | Operating costs | $ 1,500.00 | 0.47 | $ 699.76 |
9 | Operating costs | $ 1,500.00 | 0.42 | $ 636.15 |
10 | Operating costs | $ 1,500.00 | 0.39 | $ 578.31 |
11 | Operating costs | $ 1,500.00 | 0.35 | $ 525.74 |
12 | Operating costs | $ 1,500.00 | 0.32 | $ 477.95 |
13 | Operating costs | $ 1,500.00 | 0.29 | $ 434.50 |
14 | Operating costs | $ 1,500.00 | 0.26 | $ 395.00 |
15 | Operating costs | $ 1,500.00 | 0.24 | $ 359.09 |
16 | Operating costs | $ 1,500.00 | 0.22 | $ 326.44 |
17 | Operating costs | $ 1,500.00 | 0.20 | $ 296.77 |
18 | Operating costs | $ 1,500.00 | 0.18 | $ 269.79 |
19 | Operating costs | $ 1,500.00 | 0.16 | $ 245.26 |
20 | Operating costs | $ 1,500.00 | 0.15 | $ 222.97 |
21 | Operating costs | $ 1,500.00 | 0.14 | $ 202.70 |
22 | Operating costs | $ 1,500.00 | 0.12 | $ 184.27 |
23 | Operating costs | $ 1,500.00 | 0.11 | $ 167.52 |
24 | Operating costs | $ 1,500.00 | 0.10 | $ 152.29 |
25 | Operating costs | $ 1,500.00 | 0.09 | $ 138.44 |
26 | Operating costs | $ 1,500.00 | 0.08 | $ 125.86 |
27 | Operating costs | $ 1,500.00 | 0.08 | $ 114.42 |
28 | Operating costs | $ 1,500.00 | 0.07 | $ 104.02 |
29 | Operating costs | $ 1,500.00 | 0.06 | $ 94.56 |
30 | Operating costs | $ 1,500.00 | 0.06 | $ 85.96 |
Net cash outflow | 35,071.75 |
Option 2:
Year | Particulars | Cash flow | Present value Factor @10% | Present value |
0 | Installation Cost | $ 15,000.00 | 1.00 | $ 15,000.00 |
1 | Operating costs | $ 1,000.00 | 0.91 | $ 909.09 |
2 | Operating costs | $ 1,000.00 | 0.83 | $ 826.45 |
3 | Operating costs | $ 1,000.00 | 0.75 | $ 751.31 |
4 | Operating costs | $ 1,000.00 | 0.68 | $ 683.01 |
5 | Operating costs | $ 1,000.00 | 0.62 | $ 620.92 |
5 | Operating costs | $ 1,000.00 | 0.62 | $ 620.92 |
5 | Installation Cost | $ 15,000.00 | 0.62 | $ 9,313.82 |
6 | Operating costs | $ 2,000.00 | 0.56 | $ 1,128.95 |
7 | Operating costs | $ 2,000.00 | 0.51 | $ 1,026.32 |
8 | Operating costs | $ 2,000.00 | 0.47 | $ 933.01 |
9 | Operating costs | $ 2,000.00 | 0.42 | $ 848.20 |
10 | Operating costs | $ 2,000.00 | 0.39 | $ 771.09 |
11 | Operating costs | $ 2,000.00 | 0.35 | $ 700.99 |
12 | Operating costs | $ 2,000.00 | 0.32 | $ 637.26 |
13 | Operating costs | $ 2,000.00 | 0.29 | $ 579.33 |
14 | Operating costs | $ 2,000.00 | 0.26 | $ 526.66 |
15 | Operating costs | $ 2,000.00 | 0.24 | $ 478.78 |
16 | Operating costs | $ 2,000.00 | 0.22 | $ 435.26 |
17 | Operating costs | $ 2,000.00 | 0.20 | $ 395.69 |
18 | Operating costs | $ 2,000.00 | 0.18 | $ 359.72 |
19 | Operating costs | $ 2,000.00 | 0.16 | $ 327.02 |
20 | Operating costs | $ 2,000.00 | 0.15 | $ 297.29 |
21 | Operating costs | $ 2,000.00 | 0.14 | $ 270.26 |
22 | Operating costs | $ 2,000.00 | 0.12 | $ 245.69 |
23 | Operating costs | $ 2,000.00 | 0.11 | $ 223.36 |
24 | Operating costs | $ 2,000.00 | 0.10 | $ 203.05 |
25 | Operating costs | $ 2,000.00 | 0.09 | $ 184.59 |
26 | Operating costs | $ 2,000.00 | 0.08 | $ 167.81 |
27 | Operating costs | $ 2,000.00 | 0.08 | $ 152.56 |
28 | Operating costs | $ 2,000.00 | 0.07 | $ 138.69 |
29 | Operating costs | $ 2,000.00 | 0.06 | $ 126.08 |
30 | Operating costs | $ 2,000.00 | 0.06 | $ 114.62 |
Net cash outflow | 39,997.78 |
Net present value is the difference of Sum of Present values of cash inflows and Sum of Present values of cash outflows. If the value is positive then the project may be accepted. While evaluation of two or more alternatives takes place, then the proposal with the higher net present value may be selected since it results in a greater cash inflow over the duration of the project.
In the given scenario, Present values are calculated by calculating the present values of cash outflows such as installation cost and operating cost.
Present value factor is calculated as 1/1.10 ^ N where N is the year of operation of the refrigerator.
Deferment of capital expenditure to Year 5 in case of Option 2 results in a higher overall cash outflow due to increase in the annual operating costs from years 6-30. This is owing to the present value factor.
Conclusion:
Hence the Option to be implemented is Option 1 since it results in lower overall cash outflow.
Want to see more full solutions like this?
Chapter 5 Solutions
ENGR.ECONOMIC ANALYSIS W/DASHBOARD
- Use a game tree to illustrate why an aircraft manufacturer may price below the current marginal cost in the short run if it has a steep learning curve. (Hint: Show that learning by doing lowers its cost in the second period.) Part 2 Assume for simplicity the game tree is illustrated in the figure to the right. Pricing below marginal cost reduces profits but gives the incumbent a cost advantage over potential rivals. What is the subgame perfect Nash equilibrium?arrow_forwardAnswerarrow_forwardM” method Given the following model, solve by the method of “M”. (see image)arrow_forward
- As indicated in the attached image, U.S. earnings for high- and low-skill workers as measured by educational attainment began diverging in the 1980s. The remaining questions in this problem set use the model for the labor market developed in class to walk through potential explanations for this trend. 1. Assume that there are just two types of workers, low- and high-skill. As a result, there are two labor markets: supply and demand for low-skill workers and supply and demand for high-skill workers. Using two carefully drawn labor-market figures, show that an increase in the demand for high skill workers can explain an increase in the relative wage of high-skill workers. 2. Using the same assumptions as in the previous question, use two carefully drawn labor-market figures to show that an increase in the supply of low-skill workers can explain an increase in the relative wage of high-skill workers.arrow_forwardPublished in 1980, the book Free to Choose discusses how economists Milton Friedman and Rose Friedman proposed a one-sided view of the benefits of a voucher system. However, there are other economists who disagree about the potential effects of a voucher system.arrow_forwardThe following diagram illustrates the demand and marginal revenue curves facing a monopoly in an industry with no economies or diseconomies of scale. In the short and long run, MC = ATC. a. Calculate the values of profit, consumer surplus, and deadweight loss, and illustrate these on the graph. b. Repeat the calculations in part a, but now assume the monopoly is able to practice perfect price discrimination.arrow_forward
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education