Chapter 5, Problem 2E

Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the house sits high on a hill with a beautiful view of the Appalachian Mountains. The plans show the size of the house to be 2,900 square feet. The average price for a lot and house similar to this one has been $120 per square foot. Fortunately, Serge is a retired plumber and feels he can save money by installing the plumbing himself. Mrs. Tolstoy feels she can take care of the interior decorating.

The following average cost information is available from a local bank that makes loans to local contractors and dispenses progress payments to contractors when specific tasks are verified as complete.

24% Excavation and framing complete

Roof and fireplace complete

Wiring roughed in

Plumbing roughed in

Siding on

17% Windows, insulation, walks, plaster, and garage complete

Furnace installed

Plumbing fixtures installed

10% Exterior paint, light fixtures installed, finish hardware installed

Carpet and trim installed

Interior decorating

Floors laid and finished

a. What is the estimated cost for the Tolstoys’ house if they use contractors to complete all of the house?

b. Estimate what the cost of the house would be if the Tolstoys’ use their talents to do some of the work themselves.

Blurred answer
Students have asked these similar questions
Financial Misconduct: Enron Scandal Outline and discuss what “triggered” the regulatory body to intervene? How effective do you think the response was to such a crisis? Outline and discuss two ways that could be used to strengthen the current regulatory environment?
5:06 one REPORT WRITING Cover page - Table of contents Executive summary Introduction Conclusion References Appendix 11 Question 1 Ivan Institute has secured funds to construct an oval-like lecture hall at their new campus at a cost of 3 million United States Dollar As a consultant of the project, you have a mandate to package the project for the most qualified contractor. Carry out the procurement process from advertisement to award ப
Question 2 Your company has been awarded a contract to erect 124 pylons for an electricity company. The table below shows the sequential activities involved in the construction of each pylon together with the estimated labour hours and optimum number of operatives for each activity. The handover rate specified is six pylons per week and this can be taken as the target rate of build. Prepare a line of balance schedule assuming that each gang works at its natural rate. State clearly the contract duration. Assume a five-day working week, eight hours per day, and a minimum buffer time of two days Activity Description Labour-hours Optimum number of operatives per activity 55 A Excavate 4 B Concrete foundations 64 4 145 C Erect tower D Fix cantilever cable arms 90 E Fix insulators 25 885
Knowledge Booster
Background pattern image
Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
  • Text book image
    Practical Management Science
    Operations Management
    ISBN:9781337406659
    Author:WINSTON, Wayne L.
    Publisher:Cengage,
    Text book image
    Marketing
    Marketing
    ISBN:9780357033791
    Author:Pride, William M
    Publisher:South Western Educational Publishing
    Text book image
    Purchasing and Supply Chain Management
    Operations Management
    ISBN:9781285869681
    Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
    Publisher:Cengage Learning
  • Text book image
    MARKETING 2018
    Marketing
    ISBN:9780357033753
    Author:Pride
    Publisher:CENGAGE L
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY