Summary Introduction

To determine: How to select the best decision based on Expected Monetary Value (EMV) criterion.

Introduction: Expected Monetary Value (EMV) is a system for calculating expected returns for certain decision made by a company.

Expert Solution & Answer
Check Mark

Answer to Problem 18P

The low-technology approach can be selected with a cost of $145,000.

Explanation of Solution

Given information:

Marketforecast=200,000units

Strategies used:

Low-tech
Fixed cost Probability Variable cost
$45,000.00 0.3 $0.55
0.4 $0.50
0.3 $0.45
Sub-contract
Fixed cost Probability Variable cost
$65,000.00 0.7 $0.45
0.2 $0.40
0.1 $0.35
High-tech
Fixed cost Probability Variable cost
$75,000.00 0.9 $0.40
0.1 $0.35
0 $0.00

Principles Of Operations Management, Chapter 5, Problem 18P , additional homework tip  1

Market forecast 200,000 Total
Low-tech
Fixed cost Probability Variable cost
$45,000.00 0.3 $0.55 $155,000.00
0.4 $0.50 $145,000.00
0.3 $0.45 $135,000.00
Sub-contract Total
Fixed cost Probability Variable cost
$65,000.00 0.7 $0.45 $155,000.00
0.2 $0.40 $145,000.00
0.1 $0.35 $135,000.00
High-tech Total
Fixed cost Probability Variable cost
$75,000.00 0.9 $0.40 $155,000.00
0.1 $0.35 $145,000.00
0 $0.00 $0.00

Principles Of Operations Management, Chapter 5, Problem 18P , additional homework tip  2

Calculation of total cost:

Low technology:

  • Probability 0.3

Totalcost=Fixedcost+Variablecost=$45,000+(200,000×$0.55)=$155,000

With a probability of 0.3, the variable cost is calculated by multiplying the total market forecast of 200,000 with the variable cost $0.55. The product is added with the fixed cost, which is $45,000. The resultant total cost is $155,000.

  • Probability 0.4

Totalcost=Fixedcost+Variablecost=$45,000+(200,000×$0.50)=$145,000

With a probability of 0.4, the variable cost is calculated by multiplying the total market forecast of 200,000 with the variable cost $0.50. The product is added with the fixed cost, which is $45,000. The resultant total cost is $145,000.

  • Probability 0.3

Totalcost=Fixedcost+Variablecost=$45,000+(200,000×$0.45)=$135,000

With a probability of 0.3, the variable cost is calculated by multiplying the total market forecast of 200,000 with the variable cost $0.45. The product is added with the fixed cost, which is $45,000. The resultant total cost is $135,000.

Sub-contract:

  • Probability 0.7

Totalcost=Fixedcost+Variablecost=$65,000+(200,000×$0.45)=$155,000

With a probability of 0.7, the variable cost is calculated by multiplying the total market forecast of 200,000 with the variable cost $0.45. The product is added with the fixed cost, which is $65,000. The resultant total cost is $155,000.

  • Probability 0.2

Totalcost=Fixedcost+Variablecost=$65,000+(200,000×$0.40)=$145,000

With a probability of 0.2, the variable cost is calculated by multiplying the total market forecast of 200,000 with the variable cost $0.40. The product is added with the fixed cost which is $65,000. The resultant total cost is $145,000.

  • Probability 0.1

Totalcost=Fixedcost+Variablecost=$65,000+(200,000×$0.35)=$135,000

With a probability of 0.1, the variable cost is calculated by multiplying the total market forecast of 200,000 with the variable cost $0.35. The product is added with the fixed cost which is $65,000. The resultant total cost is $135,000.

High-tech:

  • Probability 0.9

Totalcost=Fixedcost+Variablecost=$75,000+(200,000×$0.40)=$155,000

With a probability of 0.9, the variable cost is calculated by multiplying the total market forecast of 200,000 with the variable cost $0.40. The product is added with the fixed cost which is $75,000. The resultant total cost is $155,000.

  • Probability 0.1

Totalcost=Fixedcost+Variablecost=$75,000+(200,000×$0.35)=$145,000

With a probability of 0.1, the variable cost is calculated by multiplying the total market forecast of 200,000 with the variable cost $0.35. The product is added with the fixed cost which is $75,000. The resultant total cost is $145,000.

Hence, from the above calculations, it can be inferred that market forecast for low-technology (which consists of hiring several new junior engineers)at the cost of $145,000 can be selected.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Government's new plan to shift cargo from roads back to rail 26TH JANUARY 2024 Government is seeking to finalise a plan aimed at improving its rail network and move cargo away from a billion rand per day to its logistics crises, government has said an urgentturnaround is needed to improve its 31 000km locomotive network as more and more cargo moves from rail to trucks. The Department of Transport (DoT) hosted a discussion with industry stakeholders regarding the Freight Road to Rail Migration Plan on Thursday - the latest development in the wake of President Cyril Ramphosa forming the National Logistics Crisis Committee last year. Transnet, the South African National Roads Agency (Sanral) and private sector companies were all in attendance. The Freight Road to Rail Migration Plan is part of government's strategies to improve the country's ongoing logistics crises. In October last year, the government unveiled its Freight Logistics Roadmap to improve the ports and rail networks and…
Assess what led to such logistical inefficiencies / collapse of a previously world class freight network
Which of the following statements concerning the evaluation of training programs is true?   Most companies thoroughly evaluate the return on investment of their training programs   It is relatively easy to establish a control group and a treatment group for evaluation   Results level of evaluation measures how well participants liked the program   Behavior level criteria measure whether skills learned in training result in behavior changes back on the job

Chapter 5 Solutions

Principles Of Operations Management

Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - Prob. 6PCh. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - Prob. 10PCh. 5.S - A Southern Georgia school district is considering...Ch. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Prob. 15PCh. 5.S - Prob. 16PCh. 5.S - Prob. 17PCh. 5.S - Prob. 18PCh. 5.S - Prob. 19PCh. 5.S - Prob. 1.1VCCh. 5.S - Prob. 1.2VCCh. 5.S - Prob. 1.3VCCh. 5.S - Prob. 2.1VCCh. 5.S - Prob. 2.2VCCh. 5.S - Prob. 2.3VCCh. 5.S - Prob. 3.1VCCh. 5.S - Prob. 3.2VCCh. 5.S - Prob. 3.3VCCh. 5.S - Prob. 3.4VCCh. 5 - Prob. 1EDCh. 5 - Prob. 1DQCh. 5 - What techniques do we use to define a product? ...Ch. 5 - Prob. 3DQCh. 5 - Prob. 4DQCh. 5 - Prob. 5DQCh. 5 - Prob. 6DQCh. 5 - Describe four organizational approaches to product...Ch. 5 - Explain what is meant by robust design.Ch. 5 - Prob. 9DQCh. 5 - What information is contained in a bill of...Ch. 5 - What information is contained in an engineering...Ch. 5 - What information is contained in an assembly...Ch. 5 - Prob. 13DQCh. 5 - Explain how the house of quality translates...Ch. 5 - Prob. 15DQCh. 5 - Prob. 16DQCh. 5 - Why are the direct interaction and surrogate...Ch. 5 - Prob. 18DQCh. 5 - Prob. 1PCh. 5 - Prob. 2PCh. 5 - Prob. 3PCh. 5 - Construct a house of quality matrix for a...Ch. 5 - Prob. 5PCh. 5 - Prob. 6PCh. 5 - Prob. 7PCh. 5 - Prob. 8PCh. 5 - Prepare a bill of material for (a) a pair of...Ch. 5 - Prob. 10PCh. 5 - Prepare a script for telephone callers at the...Ch. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Prob. 19PCh. 5 - Residents of Mill River have fond memories of ice...Ch. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 1CSCh. 5 - Prob. 2CSCh. 5 - Prob. 3CSCh. 5 - Prob. 1VCCh. 5 - Prob. 2VCCh. 5 - Prob. 3VCCh. 5 - Prob. 4VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning