Question
Book Icon
Chapter 5, Problem 4VC
Summary Introduction

Case summary:

Company RM runs a boat manufacturing business which has differentiation with its business strategy compared to other companies. With constant innovation and seeking customer inputs, dealers and consultants in the design stage, the firm has successfully managed to provide unique products to its customers.

The development phase of the product is speeded up by immediately taking the product from design stage to styling studio. Having released various products like water-skier, the production personnel are put under pressure to respond to the new product. The lifecycle time is 3 to 5 years.

The firm found that the product development part can be fastened by involving suppliers in the design phase. The CAD provides product specification after the product had completed the concept and styling phase.

A plug is formed by foam based carving which is drove by the specifications from CAD system. The new design required permanent molds which take about 4 to 8 weeks. Boats are made by joining the molds.

To determine: The likely benefits of using CAD technology.

Blurred answer
Students have asked these similar questions
Item Prepared: Work with one or more cold food production workers to learn job descriptions, flow of work, how the menu items are prepared and served, and needs for further training or process improvement. Document a specific menu item you prepared. Record the temperature of a product when it goes into the refrigerator or blast chiller. Record how long it took for the product to cool to the appropriate temperature. Evaluate the menu item you were involved in preparing. Follow the product and process to completion and utilize resources to correct any wrong procedures you observe. Take your notes and write a brief report of the actual experience based on the following criteria: 1. Pre-preparation 2. Preparation 3. Compare menu item to diets it is used for by completing a nutritional analysis 4. Temperatures during and after preparation. 5. Tray service to patient or guest (how it looks, holds up, appropriate temperature maintained from production through delivery) 6. Waste disposal (what…
Work with one or more hot food production workers to learn job descriptions, flow of work, how the menu items are prepared and served, and needs for further training or process improvement. Document a specific menu item you prepared. Record the temperature of a product when it is done. If it is to be chilled and reheated later, systematically measure the temperature every 30 minutes and record how long it takes the product to reach a safe temperature for storage. Evaluate the menu item you were involved in preparing. Follow the product and process to completion and utilize resources to correct any wrong procedures you observe. Take notes and write a brief report of the actual experience based on the following criteria: 1. Pre-preparation 2. Preparation 3. Compare menu item to diets it is used for by completing a nutritional analysis 4. Temperatures during and after preparation. 5. Tray service to patient or guest (how it looks, holds up, appropriate temperature maintained from…
Refrigerated/Freezer- Dietary Mangement (Nursing Home) Describe the refrigerated/freezer storage area and procedures.  Are any of the refrigerated/ frozen areas locked? Who has access? What kind of shelving is used? Are there any products stored on the floor? Are the items dated as received? How is the stock rotated to ensure that the oldest items are used first? Are temperature and humidity monitored? If yes, how? Has mold ever been a problem? Are there any regular procedures in place to control it? How often are the refrigerated/freezer storage areas cleaned?

Chapter 5 Solutions

Principles Of Operations Management

Ch. 5.S - Prob. 4PCh. 5.S - Prob. 5PCh. 5.S - Prob. 6PCh. 5.S - Prob. 7PCh. 5.S - Prob. 8PCh. 5.S - Prob. 9PCh. 5.S - Prob. 10PCh. 5.S - A Southern Georgia school district is considering...Ch. 5.S - Prob. 12PCh. 5.S - Prob. 13PCh. 5.S - Prob. 14PCh. 5.S - Prob. 15PCh. 5.S - Prob. 16PCh. 5.S - Prob. 17PCh. 5.S - Prob. 18PCh. 5.S - Prob. 19PCh. 5.S - Prob. 1.1VCCh. 5.S - Prob. 1.2VCCh. 5.S - Prob. 1.3VCCh. 5.S - Prob. 2.1VCCh. 5.S - Prob. 2.2VCCh. 5.S - Prob. 2.3VCCh. 5.S - Prob. 3.1VCCh. 5.S - Prob. 3.2VCCh. 5.S - Prob. 3.3VCCh. 5.S - Prob. 3.4VCCh. 5 - Prob. 1EDCh. 5 - Prob. 1DQCh. 5 - What techniques do we use to define a product? ...Ch. 5 - Prob. 3DQCh. 5 - Prob. 4DQCh. 5 - Prob. 5DQCh. 5 - Prob. 6DQCh. 5 - Describe four organizational approaches to product...Ch. 5 - Explain what is meant by robust design.Ch. 5 - Prob. 9DQCh. 5 - What information is contained in a bill of...Ch. 5 - What information is contained in an engineering...Ch. 5 - What information is contained in an assembly...Ch. 5 - Prob. 13DQCh. 5 - Explain how the house of quality translates...Ch. 5 - Prob. 15DQCh. 5 - Prob. 16DQCh. 5 - Why are the direct interaction and surrogate...Ch. 5 - Prob. 18DQCh. 5 - Prob. 1PCh. 5 - Prob. 2PCh. 5 - Prob. 3PCh. 5 - Construct a house of quality matrix for a...Ch. 5 - Prob. 5PCh. 5 - Prob. 6PCh. 5 - Prob. 7PCh. 5 - Prob. 8PCh. 5 - Prepare a bill of material for (a) a pair of...Ch. 5 - Prob. 10PCh. 5 - Prepare a script for telephone callers at the...Ch. 5 - Prob. 12PCh. 5 - Prob. 13PCh. 5 - Prob. 14PCh. 5 - Prob. 15PCh. 5 - Prob. 16PCh. 5 - Prob. 17PCh. 5 - Prob. 18PCh. 5 - Prob. 19PCh. 5 - Residents of Mill River have fond memories of ice...Ch. 5 - Prob. 21PCh. 5 - Prob. 22PCh. 5 - Prob. 23PCh. 5 - Prob. 24PCh. 5 - Prob. 25PCh. 5 - Prob. 1CSCh. 5 - Prob. 2CSCh. 5 - Prob. 3CSCh. 5 - Prob. 1VCCh. 5 - Prob. 2VCCh. 5 - Prob. 3VCCh. 5 - Prob. 4VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Marketing
Marketing
ISBN:9780357033791
Author:Pride, William M
Publisher:South Western Educational Publishing
Text book image
MARKETING 2018
Marketing
ISBN:9780357033753
Author:Pride
Publisher:CENGAGE L
Text book image
Management, Loose-Leaf Version
Management
ISBN:9781305969308
Author:Richard L. Daft
Publisher:South-Western College Pub
Text book image
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Introduction to Forecasting; Author: Ekeeda;https://www.youtube.com/watch?v=5eIbVXrJL7k;License: Standard YouTube License, CC-BY