UPENN: LOOSE LEAF CORP.FIN W/CONNECT
17th Edition
ISBN: 9781260361278
Author: Ross
Publisher: McGraw-Hill Publishing Co.
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 5, Problem 13CQ
- a. Calculate the
future value (as of the end of the project) of all the cash flows other than the initial outlay assuming they are reinvested at the required return, producing a single future value figure for the project. - b. Calculate the NPV of the project using the single future value calculated in the previous step and the initial outlay. It is easy to verify that you will get the same NPV as in your original calculation only if you use the required return as the reinvestment rate in the previous step.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Mathematically, we can determine the rate of return for a given project’s cash flow series by identifying an interest rate that equates the present worth of its cash flows to zero.
Select one:
True
False
and explain
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.
O a. If a project's IRR is positive, then its NPV must also be positive.
O b. A project's regular IRR is found by compounding the cash inflows at the WACC to find the present value (PV), then discounting the TV to find the IRR.
O c. A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost.
O d. If a project's IRR is smaller than the WACC, then its NPV will be positive.
O e. A project's regular IRR is found by compounding the initial cost at the WACC to find the terminal value (TV), then discounting the TV at the WACC.
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.
a. If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
b. If a project has normal cash flows and its IRR exceeds its cost of capital, then the project's NPV must be positive.
c. The IRR calculation implicitly assumes that all cash flows are reinvested at the cost of capital.
d. If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
e. The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
Chapter 5 Solutions
UPENN: LOOSE LEAF CORP.FIN W/CONNECT
Ch. 5 - Payback Period and Net Present Value If a project...Ch. 5 - Net Present Value Suppose a project has...Ch. 5 - Comparing Investment Criteria Define each of the...Ch. 5 - Payback and Internal Rate of Return A project has...Ch. 5 - International Investment Projects In March 2014,...Ch. 5 - Capital Budgeting Problems What are some of the...Ch. 5 - Prob. 7CQCh. 5 - Prob. 8CQCh. 5 - Net Present Value versus Profitability Index...Ch. 5 - Internal Rate of Return Projects A and B have the...
Ch. 5 - Net Present Value You are evaluating Project A and...Ch. 5 - Modified Internal Rate of Return One of the less...Ch. 5 - Net Present Value It is sometimes stated that the...Ch. 5 - Prob. 14CQCh. 5 - Calculating Payback Period and NPV Maxwell...Ch. 5 - Calculating Payback An investment project provides...Ch. 5 - Calculating Discounted Payback An investment...Ch. 5 - Calculating Discounted Payback An investment...Ch. 5 - Prob. 5QPCh. 5 - Calculating IRR Compute the internal rate of...Ch. 5 - Calculating Profitability Index Bill plans to open...Ch. 5 - Calculating Profitability Index Suppose the...Ch. 5 - Cash Flow Intuition A project has an initial cost...Ch. 5 - Prob. 10QPCh. 5 - NPV versus IRR Consider the following cash flows...Ch. 5 - Problems with Profitability Index The Coris...Ch. 5 - Prob. 13QPCh. 5 - Comparing Investment Criteria Wii Brothers, a game...Ch. 5 - Profitability Index versus NPV Hanmi Group, a...Ch. 5 - Comparing Investment Criteria Consider the...Ch. 5 - Comparing Investment Criteria The treasurer of...Ch. 5 - Comparing Investment Criteria Consider the...Ch. 5 - Prob. 19QPCh. 5 - NPV and Multiple IRRs You are evaluating a project...Ch. 5 - Payback and NPV An investment under consideration...Ch. 5 - Multiple IRRs This problem is useful for testing...Ch. 5 - NPV Valuation The Yurdone Corporation wants to set...Ch. 5 - Calculating IRR The Utah Mining Corporation is set...Ch. 5 - Prob. 25QPCh. 5 - Calculating IRR Consider two streams of cash...Ch. 5 - Calculating Incremental Cash Flows Darin Clay, the...Ch. 5 - Prob. 28QPCh. 5 - Prob. 1MCCh. 5 - Seth Bullock, the owner of Bullock Gold Mining, is...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one cash outflow at t = o followed by a series of positive cash flows. a. To find a project's MIRR, we compound cash inflows at the regular IRR and then find the discount rate that causes the PV of the terminal value to equal the initial cost. b. To find a project's MIRR, the textbook procedure compounds cash inflows at the WACC and then finds the discount rate that causes the PV of the terminal value to equal the initial cost. c. A project's MIRR is always greater than its regular IRR. d. If a project's IRR is greater than its WACC, then its MIRR will be greater than the IRR. e. A project's MIRR is always less than its regular IRR.arrow_forward1. Which of the following is not true? Group of answer choices The method in which we calculate a project’s Internal Rate of Return (IRR) is called the Discounted Cash Flow approach. The Payback period can be calculated using the discounted (present) values of future cash inflows. The Payback period calculated using this method is what's called the Discounted Payback Period. The Net Present Value is calculated using the present value of the investments and future cash inflows. None of the above (all of the above are correct)arrow_forwardWhich of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV), then discounting the TV at the WACC. b. The NPV of a relatively low-risk project should be found using a relatively high WACC. c. If a project's NPV is less than zero, then its IRR must be less than the WACC. d. The lower the WACC used to calculate it, the lower the calculated NPV will be. e. If a project's NPV is greater than zero, then its IRR must be less than zero.arrow_forward
- Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. If a project's IRR is greater than its WACC, then the MIRR will be greater than the IRR. b. If a project's IRR is greater than its WACC, then the MIRR will be less than the IRR. c. A project's MIRR is always greater than its regular IRR. d. To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC. e. A project's MIRR is always less than its regular IRR.arrow_forwardIf a project has a positive net present value, then which of the following statements are correct? I. The present value of all cash inflows must equal the costs of the project. The IRR is equal to the required rate of return. II. A increase in the project's initial cost will cause the project to have a higher positive NPV. III. Any delay in receiving the projected cash inflows will cause the project to have a higher positive NPV. IV. IRR must equal zero. Only II Only III All None of themarrow_forwardTo calculate net present value of a project with normal cash flows, find the present value of the expected cash flows, and subtract A) retained earnings. B) the cost of the investment. C) the factor loading. D) the payback period.arrow_forward
- Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. The lower the WACC used to calculate a project's NPV, the lower the calculated NPV will be. If a project's NPV is less than zero, then its IRR must be less than the WACC. If a project's NPV is greater than zero, then its IRR must be less than zero. The NPV of a relatively low-risk project should be found using a relatively high WACC. A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV), then discounting the TV at the WACC. 000oarrow_forwardWhat is the Modified Internal Rate of Return (MIRR) Select one: The opposite of NPV A reinvestment rate to account for positive cash flows reinvested into a project An approach to discounting The finance rate of a projectarrow_forwardWhich of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Select one: a. The lower the WACC used to calculate it, the lower the calculated NPV will be. b. If a project's NPV is greater than zero, then its IRR must be less than zero. c. The NPV of a relatively low-risk project should be found using a relatively high WACC. d. A project's NPV is found by compounding the cash inflows at the IRR to find the terminal value (TV), then discounting the TV at the WACC. e. If a project's NPV is less than zero, then its IRR must be less than the WACC.arrow_forward
- Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $2,225,000. The project’s expected cash flows are: Year Cash Flow Year 1 $350,000 Year 2 –125,000 Year 3 450,000 Year 4 450,000 Green Caterpillar Garden Supplies Inc.’s WACC is 7%, and the project has the same risk as the firm’s average project. Calculate this project’s modified internal rate of return (MIRR): -12.63% 26.46% 30.64% 29.24% If Green Caterpillar Garden Supplies Inc.’s managers select projects based on the MIRR criterion,…arrow_forwardThe payback period is a non - discounted cash flow technique that measures: a. The time required to recover the initial investment b. The profitability of the project c. The net present value of the project d. The internal rate of return of the projectarrow_forwardYou have determined the profitability of a planned project by finding the present value of all the cash flows from that project. Which of the following would cause the project to look more appealing in terms of the present value of those cash flows? A. The discount rate increases. B. The cash flows are extended over a longer period of time, but the total amount of the cash flows remains the same. C. The discount rate decreases. D. Answers B and C above. E. Answers A and B above.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeSurvey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License