a)
To determine: The number of machines of each type required to handle the demand and its capacity and the machine that would have lower total cost.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
a)

Answer to Problem 11P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type A, type B, or type C. The cost of type A machine is $40,000, cost of type B machine is $30,000, and the cost of type C machine is $80,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per unit | ||
A | B | C | ||
1 | 16,000 | 3 | 4 | 2 |
2 | 12,000 | 4 | 4 | 3 |
3 | 6,000 | 5 | 6 | 4 |
4 | 30,000 | 2 | 2 | 1 |
Determine the number of machines of each type required and its capacity:
It is given that the machines will operate 60 minutes per hour, 10 hours per day and 250 days per year.
Determine the minutes available for all types of machine:
It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type A, type B, and type C is 150,000 minutes per year.
Determine the processing requirement of product 1 using machine type A:
It is calculated by multiplying annual demand of product 1 and the processing time per unit on type A. Hence, the processing requirements of product 1 using machine type A is 48,000 minutes.
Determine the processing requirement of product 2 using machine type A:
It is calculated by multiplying annual demand of product 2 and the processing time per unit on type A. Hence, the processing requirements of product 2 using machine type A is 48,000 minutes.
Determine the processing requirement of product 3 using machine type A:
It is calculated by multiplying annual demand of product 3 and the processing time per unit on type A. Hence, the processing requirements of product 3 using machine type A is 30,000 minutes.
Determine the processing requirement of product 4 using machine type A:
It is calculated by multiplying annual demand of product 4 and the processing time per unit on type A. Hence, the processing requirements of product 4 using machine type A is 60,000 minutes.
Determine the total processing requirement using machine type A:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type A is 186,000 minutes.
Determine the needed number of machine type A:
It is calculated by dividing the total processing requirement and available minutes for machine type A. Hence, the needed number of machine type A is 2 machines.
Determine the processing requirement of product 1 using machine type B:
It is calculated by multiplying annual demand of product 1 and the processing time per unit on type B. Hence, the processing requirements of product 1 using machine type B is 64,000 minutes.
Determine the processing requirement of product 2 using machine type B:
It is calculated by multiplying annual demand of product 2 and the processing time per unit on type B. Hence, the processing requirements of product 2 using machine type B is 48,000 minutes.
Determine the processing requirement of product 3 using machine type B:
It is calculated by multiplying annual demand of product 3 and the processing time per unit on type B. Hence, the processing requirements of product 3 using machine type B is 36,000 minutes.
Determine the processing requirement of product 4 using machine type B:
It is calculated by multiplying annual demand of product 4 and the processing time per unit on type B. Hence, the processing requirements of product 4 using machine type B is 60,000 minutes.
Determine the total processing requirement using machine type B:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type B is 208,000 minutes.
Determine the needed number of machine type B:
It is calculated by dividing the total processing requirement and available minutes for machine type B. Hence, the needed number of machine type B is 2 machines.
Determine the processing requirement of product 1 using machine type C:
It is calculated by multiplying annual demand of product 1 and the processing time per unit on type B. Hence, the processing requirements of product 1 using machine type B is 32,000 minutes.
Determine the processing requirement of product 2 using machine type C:
It is calculated by multiplying annual demand of product 2 and the processing time per unit on type B. Hence, the processing requirements of product 2 using machine type B is 36,000 minutes.
Determine the processing requirement of product 3 using machine type C:
It is calculated by multiplying annual demand of product 3 and the processing time per unit on type B. Hence, the processing requirements of product 3 using machine type B is 24,000 minutes.
Determine the processing requirement of product 4 using machine type C:
It is calculated by multiplying annual demand of product 4 and the processing time per unit on type B. Hence, the processing requirements of product 4 using machine type B is 30,000 minutes.
Determine the total processing requirement using machine type C:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type C is 122,000 minutes.
Determine the needed number of machine type C:
It is calculated by dividing the total processing requirement and available minutes for machine type C. Hence, the needed number of machine type C is 1 machine.
Determine the total cost considering purchase cost of machine type A:
It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $80,000.
Determine the total cost considering purchase cost of machine type B:
It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $60,000.
Determine the total cost considering purchase cost of machine type C:
It is calculated by multiplying number of machines and the cost of the machine. Hence, the total cost is $80,000.
Hence, Buying 2 of the B machines at a total cost of $60,000 have lower total cost.
b)
To determine: The machine that would have lower total cost considering operating cost.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
b)

Answer to Problem 11P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type A, type B, or type C. The cost of type A machine is $40,000, cost of type B machine is $30,000, and the cost of type C machine is $80,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per unit | ||
A | B | C | ||
1 | 16,000 | 3 | 4 | 2 |
2 | 12,000 | 4 | 4 | 3 |
3 | 6,000 | 5 | 6 | 4 |
4 | 30,000 | 2 | 2 | 1 |
Operating cost for machine A is $10 per hour, operating cost for machine B is $11 per hour, and operating cost for machine C is $12 per hour.
Calculate the total cost considering both purchasing cost and operating cost for machine A:
It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.
Calculate the total cost considering both purchasing cost and operating cost for machine B:
It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.
Calculate the total cost considering both purchasing cost and operating cost for machine C:
It is calculated by adding the total cost considering purchasing cost and the operating cost which can be attained by multiplying operating cost per hour and the total processing hours.
Hence, buying two B machines would have lower total cost.
Want to see more full solutions like this?
Chapter 5 Solutions
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
- With your experience and research, discuss;(a) what type of “Leadership Style” is used in communications services (Digicel Group Limited)?(b) whether the style used is successful or not and why. Justify your position with relevant citation and references ( Rubic is attached to guide the essay ) NOTE: NO AI RESPONSES PLEASEarrow_forwardby the end of 2013, the IPL port was operational and the naphtha was flowing to the Himachal Fertilizer Corporation (HFC) plant in Central India after being granted the port contract in Summer 2012. The plant was located in an industrial area that had several pipelines in the general geographic area including a crude oil pipeline leading to a refinery, and a pipeline carrying pesticides to be processed and redistributed to local farms in the area. In July 2014, Ajay Patel, the logistics general manager received notification that there were some minor leaks along the pipeline that were being fixed. Workers in the area had experienced sudden headaches and lightheadedness and the company immediately moved to investigate the leak and address faulty seams that had eroded and weakened. The flow of naphtha was temporarily stopped for 72 hours so two portions of the pipeline could be removed, and the eroded portions replaced. Patel put enormous pressure on the repair team to get the repair…arrow_forwardin the MABE: learning to be multinational case report, what is the reccomended course of action?arrow_forward
- In the MABE case report what would be the reccomened course of action?arrow_forwardQuestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i) Solve this LPP by using graphical analysis ii) What will be the slack at the optimal solution point? Show calculation.arrow_forwardqusestion 6. An electrical engineering company is designing two types of solar panel systems: Standard Panels (S) and High-Efficiency Panels (H). The company has certain constraints regarding the hours of labor and material available for production each week. Each Standard Panel requires 4 hours of labor and 2 units of material and each High-Efficiency Panel requires 3 hours of labor and 5 units of material. The company has a maximum of 60 hours of labor and 40 units of material available per week. The profit from each Standard Panel is GH¢80, and the profit from each High-Efficiency Panel is GH¢100. The company wants to determine how many of each type of panel to produce in order to maximize profit. i. Formulate a linear programming model of the problem for the company. ii Convert the linear programming model formulated in (a) to a standard form.arrow_forward
- G ווח >>> Mind Tap Cengage Learning 1- CENGAGE MINDTAP Chapter 09 Excel Activity: Exponential Smoothing Question 1 3.33/10 e Submit 自 A ng.cengage.com C Excel Online Student Work G A retail store records customer demand during each sales period. 1. What is the f... Q Search this course ? ✓ Co Excel Online Tutorial Excel Online Activity: Exponential Smoothing A-Z A retail store records customer demand during each sales period. The data has been collected in the Microsoft Excel Online file below. Use the Microsoft Excel Online file below to develop the single exponential smoothing forecast and answer the following questions. Office Video X Open spreadsheet Questions 1. What is the forecast for the 13th period based on the single exponential smoothing? Round your answer to two decimal places. 25.10 2. What is the MSE for the single exponential smoothing forecast? Round your answer to two decimal places. 21.88 Activity Frame ? 3. Choose the correct graph for the single exponential…arrow_forwardNot use ai pleasearrow_forwardItems removed from the work area (5S) were taken to a storage area called ___________. Choose from: SORT, STORD, KNUJ, STUFF, FUDG SORT STORD KNUJ STUFF FUDGarrow_forward
- Could you please help explain How was the poor strategic decisions lead to economic downturns of Circuit City Company? What are the sequences of key events and problems that contribute to its collapse. Could you please explain each one them and give the examples If Circuit City would apply Lean Six Sigma. would it helped prevent businesses from collapsed?? How Qualitative and quantitative Research Methodology in Case Study Research would affect Circuit City?arrow_forwardApple is a global technology company renowned for its innovation and design. To create its products, Apple has established a world class global supply chain to bring their products to market. What strategies is Apple using to source and manufacture its products? How does Apple view its responsibility to its suppliers and those who build its products?arrow_forwardCritical Path Method (CPM) is an important Project Management Tool that has wide industry application in modern day Project Management. By using an example of the project of your choice, critically examine the practical application of CPM as a Project Management Tool.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning
- Management, Loose-Leaf VersionManagementISBN:9781305969308Author:Richard L. DaftPublisher:South-Western College Pub