
A company must decide which type of machine to buy, and how many units of that type, given the following information:
Product demand and processing times for the equipment are:
a. How many machines of each type would be required to handle demand if the machines will operate 8 hours a day, 250 days a year, and what annual capacity cushion in processing time would result for each?
b. With high certainty of annual demand, which type of machine would be chosen if that was an important consideration?
c. If purchasing and operating costs are taken into account, which type of machine would minimize total costs, given your answer for part a? Operating costs are $6/hr for type 1 and $5/hr for type 2.
a)

To determine: The number of machines of each type required to handle the demand and its capacity.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Determine the number of machines of each type required and its capacity:
It is given that the machines will operate 60 minutes per hour, 8 hours per day and 250 days per year.
Determine the minutes available for machine type 1:
It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type 1 is 120,000 minutes per year.
Determine the processing requirement of product 001 using machine type 1:
It is calculated by multiplying annual demand of product 001 and the processing time per unit on type 1. Hence, the processing requirements of product 001 using machine type 1 is 48,000 minutes.
Determine the processing requirement of product 002 using machine type 1:
It is calculated by multiplying annual demand of product 002 and the processing time per unit on type 1. Hence, the processing requirements of product 002 using machine type 1 is 90,000 minutes.
Determine the processing requirement of product 003 using machine type 1:
It is calculated by multiplying annual demand of product 003 and the processing time per unit on type 1. Hence, the processing requirements of product 003 using machine type 1 is 90,000 minutes.
Determine the total processing requirement using machine type 1:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 1 is 228,000 minutes.
Determine the needed number of machine type 1:
It is calculated by dividing the total processing requirement and available minutes for machine type 1. Hence, the needed number of machine type 1is 2 machines.
Determine the capacity of the machines:
It is calculated by multiplying the number of machine type 1 needed and the available minutes for machine type 1. Hence, the capacity of the machine is 240,000 minutes.
Determine the capacity cushion:
It is calculated by subtracting total processing requirement from capacity of machines.
Determine the minutes available for machine type 2:
It is calculated by multiplying number of days per year, hours per day, and minutes per hour. Hence, the available minutes per year for machine type 2 is 120,000 minutes per year.
Determine the processing requirement of product 001 using machine type 2:
It is calculated by multiplying annual demand of product 001 and the processing time per unit on type 2. Hence, the processing requirements of product 001 using machine type 2 is 72,000 minutes.
Determine the processing requirement of product 002 using machine type 2:
It is calculated by multiplying annual demand of product 002 and the processing time per unit on type 2. Hence, the processing requirements of product 002 using machine type 2 is 90,000 minutes.
Determine the processing requirement of product 003 using machine type 2:
It is calculated by multiplying annual demand of product 003 and the processing time per unit on type 2. Hence, the processing requirements of product 003 using machine type 2 is 54,000 minutes.
Determine the total processing requirement using machine type 2:
It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 2 is 216,000 minutes.
Determine the needed number of machine type 2:
It is calculated by dividing the total processing requirement and available minutes for machine type 2. Hence, the needed number of machine type 2 is 2 machines.
Determine the capacity of the machines:
It is calculated by multiplying the number of machine type 2 needed and the available minutes for machine type 2. Hence, the capacity of the machine is 240,000 minutes.
Determine the capacity cushion:
It is calculated by subtracting total processing requirement from capacity of machines.
b)

To determine: The machine type that can be chosen for the high and low certainty of demand.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Determine the machine type that can be chosen for the high and low certainty of demand:
The machine with the high capacity cushion should be selected, if the firm faced high certainty of annual demand. hence, machine type 2 should be selected.
The machine with the low capacity cushion should be selected, if the firm faced low certainty of annual demand. hence, machine type 1 should be selected.
c)

To determine: The machine type that would minimize the total cost, if purchasing and operating costs are considered.
Introduction: Capacity planning is the process of planning the required production output based on the requirement or the demand that is predicted.
Answer to Problem 10P
Explanation of Solution
Given information:
A company should decide whether to buy machine of type 1 or type 2. The cost of type 1 machine is $10,000 and the cost of type 2 machine is $14,000.
Annual demand and processing unit is given as follows for each product:
Product | Annual demand | Processing time per minute | |
Type 1 | Type 2 | ||
001 | 12,000 | 4 | 6 |
002 | 10,000 | 9 | 9 |
003 | 18,000 | 5 | 3 |
Operating cost is given as $6 per hour for type 1 and $5 per hour for type 2.
Determine the purchase cost for machine type 1:
It is calculated by multiplying the number of machines and cost of type 1 machine. Hence, the purchase cost for machine type 1 is $20,000.
Determine the total operating time for machine type 1:
Total operating time is the total processing requirement. It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 1 is 228,000 minutes.
Determine the total operating cost:
Total operating cost is calculated by multiplying the total operating time and the operating cost per hour. Hence, the total operating cost is $22,800.
Determine the total cost:
It is calculated by adding the purchasing cost of machine type 1 and total operating cost. Hence, the total cost is $42,800.
Determine the purchase cost for machine type 2:
It is calculated by multiplying the number of machines and cost of type 2 machine. Hence, the purchase cost for machine type 2 is $28,000.
Determine the total processing requirement using machine type 2:
Total operating time is the total processing requirement. It is calculated by adding the processing requirement of all the products. Hence, the total processing requirement using machine type 2 is 216,000 minutes.
Determine the total operating cost:
Total operating cost is calculated by multiplying the total operating time and the operating cost per hour. Hence, the total operating cost is $18,000.
Determine the total cost:
It is calculated by adding the purchasing cost of machine type 2 and total operating cost. Hence, the total cost is $46,000.
Hence, Machine type 1 would minimize the total cost.
Want to see more full solutions like this?
Chapter 5 Solutions
Loose Leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
- Prepare a graph of the monthly forecasts and average forecast demand for Chicago Paint Corp., a manufacturer of specialized paint for artists. Compute the demand per day for each month (round your responses to one decimal place). Month B Production Days Demand Forecast Demand per Day January 21 950 February 19 1,150 March 21 1,150 April 20 1,250 May 23 1,200 June 22 1,000' July 20 1,350 August 21 1,250 September 21 1,050 October 21 1,050 November 21 December 225 950 19 850arrow_forwardThe president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 2,300 January 1,500 May February 1,700 June 2,100 March April 1,700 1,700 July August 1,900 1,500 Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $25 per unit per month. Ignore any idle-time costs. The plan is called plan C. Plan C: Keep a stable workforce by maintaining a constant production rate equal to the average gross requirements excluding initial inventory and allow varying inventory levels. Conduct your analysis for January through August. The average monthly demand requirement = units. (Enter your response as a whole number.) In order to arrive at the costs, first compute the ending inventory and stockout units for each month by filling in the table below (enter your responses as whole numbers). Ending E Period…arrow_forwardMention four early warning indicators that a business may be at risk.arrow_forward
- 1. Define risk management and explain its importance in a small business. 2. Describe three types of risks commonly faced by entrepreneurs. 3. Explain the purpose of a risk register. 4. List and briefly describe four risk response strategies. (5 marks) (6 marks) (4 marks) (8 marks) 5. Explain how social media can pose a risk to small businesses. (5 marks) 6. Identify and describe any four hazard-based risks. (8 marks) 7. Mention four early warning indicators that a business may be at risk. (4 marks)arrow_forwardState whether each of the following statements is TRUE or FALSE. 1. Risk management involves identifying, analysing, and mitigating risks. 2. Hazard risks include interest rate fluctuations. 3. Entrepreneurs should avoid all forms of risks. 4. SWOT analysis is a tool for risk identification. 5. Scenario building helps visualise risk responses. 6. Risk appetite defines how much risk an organisation is willing to accept. 7. Diversification is a risk reduction strategy. 8. A risk management framework must align with business goals. 9. Political risk is only relevant in unstable countries. 10. All risks can be eliminated through insurance.arrow_forward9. A hazard-based risk includes A. Political instability B. Ergonomic issues C. Market demand D. Taxation changesarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning

