Question
Chapter 4, Problem 125P
Summary Introduction
To determine: A way to minimize the cost of meeting the daily requirements of the police department.
Linear programming:
It is a mathematical modeling procedure were a linear function is maximized or minimized subject to certain constraints. This method is widely useful in making a quantitative analysis which is essential for making important business decisions.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
A company has one machine which can be used to make product Alpha and product Beta.
Each unit of product Alpha requires 45 minutes of machine time, while
each unit of product Beta requires 37 minutes of machine time.
The machine can be used for 8 hours per day and 5 days per week.
Next week the company will produce 23 units of product Alpha.
After completing the production of Alpha, the company will produce product Beta.
How many units of product Beta can be produced next week?
Use at least 4 decimals.You must showm your calculation steps and brief explanation on your Excel spreadsheets.
Please answer question completely and explain your answer
A large food chain owns a number of pharmacies that operate in a variety of settings. Some are situated in small towns and are open for only 8 hours a day, 5 days per week. Others are located in shopping malls and are open for longer hours. The analysts on the corporate staff would like to develop a model to show how a store’s revenues depend on the number of hours that it is open. They have collected the following information from a sample of stores.
Hours of Operation
Average Revenue ($)
40
5958
44
6662
48
6004
48
6011
60
7250
70
8632
72
6964
90
11097
100
9107
168
11498
Use a linear function (e.g., y = ax + b; where a and b are parameters to optimize) to represent the relationship between revenue and operating hours and find the values of the parameters using the nonlinear solver that provide the best fit to the given data. What revenue does your model predict for 120 hours?
Suggest a two-parameter…
Chapter 4 Solutions
PRACTICAL MGT. SCIENCE (LL)-W/MINDTAP
Ch. 4.2 - Prob. 1PCh. 4.2 - Prob. 2PCh. 4.2 - Prob. 3PCh. 4.2 - Prob. 4PCh. 4.2 - Prob. 5PCh. 4.2 - Prob. 6PCh. 4.3 - Prob. 7PCh. 4.3 - Prob. 8PCh. 4.3 - Prob. 9PCh. 4.3 - Prob. 10P
Ch. 4.3 - Prob. 11PCh. 4.3 - Prob. 12PCh. 4.4 - Prob. 13PCh. 4.4 - Prob. 14PCh. 4.4 - Prob. 15PCh. 4.4 - Prob. 16PCh. 4.4 - Prob. 17PCh. 4.4 - Prob. 18PCh. 4.4 - Prob. 19PCh. 4.5 - Prob. 20PCh. 4.5 - Prob. 21PCh. 4.5 - Prob. 22PCh. 4.5 - Prob. 23PCh. 4.5 - Prob. 24PCh. 4.5 - Prob. 25PCh. 4.6 - Prob. 26PCh. 4.6 - Prob. 27PCh. 4.6 - Prob. 28PCh. 4.6 - Prob. 29PCh. 4.7 - Prob. 30PCh. 4.7 - Prob. 31PCh. 4.7 - Prob. 32PCh. 4.7 - Prob. 33PCh. 4.7 - Prob. 34PCh. 4.7 - Prob. 35PCh. 4.7 - Prob. 36PCh. 4.7 - Prob. 37PCh. 4.7 - Prob. 38PCh. 4.7 - Prob. 39PCh. 4.7 - Prob. 40PCh. 4.8 - Prob. 41PCh. 4.8 - Prob. 42PCh. 4.8 - Prob. 43PCh. 4.8 - Prob. 44PCh. 4 - Prob. 45PCh. 4 - Prob. 46PCh. 4 - Prob. 47PCh. 4 - Prob. 48PCh. 4 - Prob. 49PCh. 4 - Prob. 50PCh. 4 - Prob. 51PCh. 4 - Prob. 52PCh. 4 - Prob. 53PCh. 4 - Prob. 54PCh. 4 - Prob. 55PCh. 4 - Prob. 56PCh. 4 - Prob. 57PCh. 4 - Prob. 58PCh. 4 - Prob. 59PCh. 4 - Prob. 60PCh. 4 - Prob. 61PCh. 4 - Prob. 62PCh. 4 - Prob. 63PCh. 4 - Prob. 64PCh. 4 - Prob. 65PCh. 4 - Prob. 66PCh. 4 - Prob. 67PCh. 4 - Prob. 68PCh. 4 - Prob. 69PCh. 4 - Prob. 70PCh. 4 - Prob. 71PCh. 4 - Prob. 72PCh. 4 - Prob. 73PCh. 4 - Prob. 74PCh. 4 - Prob. 75PCh. 4 - Prob. 76PCh. 4 - Prob. 77PCh. 4 - Prob. 78PCh. 4 - Prob. 79PCh. 4 - Prob. 80PCh. 4 - You want to take out a 450,000 loan on a 20-year...Ch. 4 - Prob. 82PCh. 4 - Prob. 83PCh. 4 - Prob. 84PCh. 4 - Prob. 85PCh. 4 - Prob. 86PCh. 4 - Prob. 87PCh. 4 - Prob. 88PCh. 4 - Prob. 89PCh. 4 - Prob. 90PCh. 4 - Prob. 91PCh. 4 - Prob. 92PCh. 4 - Prob. 93PCh. 4 - Prob. 94PCh. 4 - Prob. 95PCh. 4 - Prob. 96PCh. 4 - Prob. 97PCh. 4 - Prob. 98PCh. 4 - Prob. 99PCh. 4 - Prob. 100PCh. 4 - Prob. 101PCh. 4 - Prob. 102PCh. 4 - Prob. 103PCh. 4 - Prob. 104PCh. 4 - Prob. 105PCh. 4 - Prob. 106PCh. 4 - Prob. 107PCh. 4 - Prob. 108PCh. 4 - Prob. 109PCh. 4 - Prob. 110PCh. 4 - Prob. 111PCh. 4 - Prob. 112PCh. 4 - Prob. 113PCh. 4 - Prob. 114PCh. 4 - Prob. 115PCh. 4 - Prob. 116PCh. 4 - Prob. 117PCh. 4 - Prob. 118PCh. 4 - Prob. 119PCh. 4 - Prob. 120PCh. 4 - Prob. 121PCh. 4 - Prob. 122PCh. 4 - Prob. 123PCh. 4 - Prob. 124PCh. 4 - Prob. 125PCh. 4 - Prob. 126PCh. 4 - Prob. 127PCh. 4 - Prob. 128PCh. 4 - Prob. 129PCh. 4 - Prob. 130PCh. 4 - Prob. 131PCh. 4 - Prob. 132PCh. 4 - Prob. 133PCh. 4 - Prob. 134PCh. 4 - Prob. 135P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A roller coaster is being designed for a new theme park. Two "trains" are on the track at any given time. One train is being unloaded/reloaded while the other is moving along the track. The track itself takes 10 minutes to complete. The train being loaded should depart before the arriving train is no closer than one minute away. Each car of a train accommodates four people. Loading a car is estimated to take 6 seconds per passenger. Unloading is estimated to take 6 seconds per passenger. Suppose that (unlike actual roller coasters), only one car can be loaded or unloaded at a time. Unloading can NOT occur at the same time as loading. In order to maximize the number of potential passengers, how many cars should the train be made up of? Round your answer to the nearest whole car.arrow_forwardPlease help me. Thankyou.arrow_forwardDear weber, Unfortunately, my question always has no unable to answer. Here, I want to help you to solve my question. The Answer to my last question regarding the formulation of the problem is: The Reliance Manufacturing Company produces an aircraft part. The company can produce the part entirely at a flexible work center with multiple computerized machines. The company has four work centers, all of which are different because they were purchased at different times. Each work center has a single operator; however, the company’s operators have different skill levels, resulting in different levels of daily output and product quality. The following tables show the average daily output and an average number of defects per day for each of the company’s five operators who are capable of producing the aircraft part: Table 1 Operator Average Daily Output per Machine A B C D 1 18 20 21 17 2 19 15 22 18 3 20 20 17 19 4 24 21 16 23…arrow_forward
- There are two companies manufacturing drones. Company A manufactures mass market drones, while company B manufactures customised drones according to customers’ requirements. In 2020, company A produces 3,200 drones, 3% of which were found to be defective and cannot pass the quality check. Company A employs 5 workers working an average of 8 hours a day in the drone production, and they worked 200 working days in 2020.In contrast, company B produces 900 drones, 10% of which were found to be defective and cannot pass the quality check. Company B employs 3 workers working an average of 6 hours a day in the drone production, and they worked 170 days in 2020. (a) If the drone manufacturing is seen as a process, what is considered as the output of the production processes of companies A and B and why? (b) Measure the single-factor manpower productivity for the two companies. (c) Is it reasonable to compare the manpower productivity of the two companies and reach a conclusion that one company…arrow_forwardAuthor: Leo A. Ruggle, Professor, Department of Accounting, Mankato State University Arnie Armstrong has been with Pierce Auto Parts Manufacturing Company for 23 years. Recently, he was appointed Director of Manufacturing Computer Services. In just six weeks in this new position, [he] has moved to reduce the amount of information provided to manufacturing department managers by 60 percent. He argues that excess data is distracting, unused, and expensive to provide. Willy McClean has been department manager for 12 years. During a coffee break with some of his department production supervisors, Willy is quite vocal about the change. “Who’s this guy Armstrong to tell us what data we need? He needs to be out here for a few weeks to find out what it’s like. Keep it quiet, but I’ve got a contact in Computer Services who’ll get me all the data analyses I want for just a $20 bill each month. It’s a good deal, and Armstrong will never know. How does he expect us to make good decisions about…arrow_forwardA small petroleum company owns two refineries plant. Refinery 1 costs $20,000 per day to operate, and it can produce 400 barrels of high-grade oil, 300 barrels of medium-grade oil, and 200 barrels of low-grade oil each day. Refinery 2 is newer and more modern. It costs $25,000 per day to operate, and it can produce 300 barrels of high-grade oil, 400 barrels of medium- grade oil, and 500 barrels of low-grade oil each day. The company has orders totaling 25,000 barrels of high-grade oil, 27,000 barrels of medium-grade oil, and 30,000 barrels of low-grade oil. Set up linear minimization problem using Simplex method. Determine the days to run each refinery to minimize the cost in order to meet its order.arrow_forward
- Do not use chatgpt.arrow_forwardThe Decision Sciences Department is tyring to determine whether to rent a slow or fast copier. The department believes that an employee's time is worth $15/hour. The slow copier rents for $4/hr, and it takes an employee an average of 10 minutes to complete copying. The fast copier rents for $15/hr, and it takes an employee an average of 6 minutes to complete copying. On average, four employees per hour need to use the copying machine. (Assume the copying times and interarrival times to the copying machine are exponentially distributed.) Which machine should the department rent to minimize expected total cost per hour? Please note this class revolves around Microsoft Excel so the answer I need needs to show the formulas in Excel, along with any corresponding graphs, etc. Thank you in advance!arrow_forwardA company makes four products that have the following characteristics: Product A sells for $75 but needs $40 of materials to produce; Product B sells for $90 but needs $65 of materials to produce; Product C sells for $110 but needs $80 of materials to produce; Product D sells for $135 but needs $105 of materials to produce. The processing requirements for each product on each of the four machines are shown in the table. Work centers W, X, Y, and Z are available for 5 days per week, 1 shift per day (8 hrs.) and have no setup time when switching between products. Market demand is 50 As, 60 Bs, 70 Cs, and 80 Ds per week. In the questions that follow, the traditional method refers to maximizing the contribution margin per unit for each product, and the bottleneck method refers to maximizing the contribution margin per minute at the bottleneck for each product. Each worker is paid $15 per hour and is paid for an entire week, regardless of how much the worker is used. Answer the following…arrow_forward
- PepsiCo sells its soft drinks in approximately 400,000 retail establishments, such as supermarkets, discount stores, and convenience stores. Sales representatives call on each retail account weekly, which means each account is called on by a sales rep 52 times per year. The average length of a sales call is 75 minutes (or 1.25 hours). An average salesperson works 2,000 hours per year (50 weeks per year * 40 hours perweek), but each spends 10 hours a week on nonselling activities, such as administrative tasks and travel. How many salespeople does PepsiCo need?arrow_forwardThe Decision Sciences Department is trying to determine whether to rent a slow or a fast copier. The department believes that an employee’s time is worth $15 per hour. The slow copier rents for $4 per hour, and it takes an employee an average of 10 minutes to complete copying. The fast copier rents for $15 per hour, and it takes an employee an average of six minutes to complete copying. On average, four employees per hour need to use the copying machine. (Assume the copying times and interarrival times to the copying machine are exponentially distributed.) Which machine shouldthe department rent to minimize expected total cost per hour?arrow_forwardForrester and Cohen is a small accounting firm, managed by Joseph Cohen since the retirement in December of his partner Brad Forrester. Cohen and his 3 CPAs together bill 620 hours per month. When Cohen or another accountant bills more than 155 hours per month, he or she gets an additional "overtime" pay of $63.20 for each of the extra hours: this is above and beyond the $4,900 salary each draws during the month. (Cohen draws the same base pay as his employees.) Cohen strongly discourages any CPA from working (billing) more than 250 hours in any given month. The demand for billable hours for the firm over the next 6 months is estimated below: Month Jan. Feb. Mar. Apr. Estimate of Billable Hours 600 500 1,020 1,230 640 570 May June Cohen has an agreement with Forrester, his former partner, to help out during the busy tax season, up to 250 hours in any given month if needed, for an hourly fee of $120. Cohen will not even consider laying off one of his colleagues in the case of a slow…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,