Concept explainers
a)
To draw: A process flow diagram for this process.
a)
Explanation of Solution
Given information:
Process flow diagram:
b)
To determine: The capacity at the resource “Apply a lid”.
b)
Explanation of Solution
Given information:
Calculation of capacity:
The capacity is 1,200 bottles.
c)
To determine: The bottleneck in the process.
c)
Explanation of Solution
Given information:
Determination of bottleneck:
The process step with the longest processing time “seconds per bottle” is the bottleneck in the process. Packaging has the highest time of 3 seconds per bottle.
Hence, the bottleneck is Packaging.
d)
To determine: The flow rate.
d)
Explanation of Solution
Given information:
Determination of flow rate:
The flow rate is 900 bottles.
e)
To determine: The utilization of resource “Apply a lid”
e)
Explanation of Solution
Given information:
Calculation of utilization:
The utilization is 75%.
f)
To determine: The utilization of bottling.
f)
Explanation of Solution
Given information:
Calculation of utilization:
The utilization is 20%.
g)
To determine: The cycle time of the process.
g)
Explanation of Solution
Given information:
Calculation of cycle time:
The demand is constrained and has a flow rate of
The cycle time is 5 seconds.
h)
To determine: The time taken to produce 500 bottles.
h)
Explanation of Solution
Given information:
Calculation of time taken to produce 500 bottles:
The time taken to produce 500 bottles is 2,515 seconds.
Want to see more full solutions like this?
Chapter 3 Solutions
Operations Management
- Understanding the process begins with determining the key process objectives. Select one: a True . Falsearrow_forwardHow many orders of magnitude larger is the difference between a process that operates in nanoseconds and one that operates in milliseconds?arrow_forwardProcess Redesign is concerned with increasing the performance of processes without changing the order of activities within the process or fundamentally changing the activities themselves. focuses on eliminating costs works to find ways to eliminate activities within a process. is concerned with improving performance by changing the order of activities or fundamentally changing the activities themselves.arrow_forward
- A chemical process involves adding various agents to a vat and then waiting for theagents to react to make a final compound. The vat holds up to 1000 gallons. Chemicalagents are added to the vat at a rate of 4.5 gallons per minute. Once the agents have beenadded to the vat, the reaction takes 85 minutes no matter the actual number of gallonsin the batch. After the batch is complete, the vat must be cleaned. Cleaning always takes15 minutes. What is the setup time of this process?a. 15 minutes c. 100 minutesb. 85 minutes d. 222.22 minutesarrow_forwardThe Flip Chip Company manufactures nacho chips, potato chips, and related products. There has been a problem in the manufacture of nacho chips. The process begins with the mixing of water, corn and lime (called the MASA). A mixer can produce a batch of 300 lbs of MASA in 2 minutes. The MASA is then cooked. This takes 30 minutes. Only 95% of the MASA makes it to the ovens and of that only 75% is transferred to the next step. There are four ovens. The next step is chip making. The MASA is extruded into the chip itself and the chips are baked. There are 2 chip machines. A total of 950 chips/minute are produced (each chip weighs approximately .5oz). The yield from this process is 72%. The chips are then placed in 20 oz bags. This step takes 2 seconds for each bag. Where is the bottleneck? What recommendation would you make?arrow_forwardBurger Doodle is a fast-food restaurant that processes an average of 700 food orders each day. The average cost of each order is $6.05. Four percent of the orders are incorrect, and only 8% of the defective orders can be corrected with additional food items at an average cost of $1.75. The remaining defective orders have to be thrown out.arrow_forward
- Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs have been assigned to each activity using direct tracing and resource drivers as follows: Activity Expected Cost Activity Driver Activity Capacity Engineering $1,000,000 Engineering hours 5,000 hours Setups 900,000 Setups 200 setups Machining 2,000,000 Machine hours 25,000 machine hours Inspection 800,000 Inspection hours 2,500 inspection hours Quasi-Tech produces two models: Model C and Model D. The following table…arrow_forwardConsider a production process making controllers for video game consoles. The processoperates on a 30-second/unit cycle time. It has 10 stations, with the most error-proneactivity carried out at station 2. Inspection happens at the end of the process and thereare about 600 units of inventory between step 2 and the inspection.What would be the information turnaround time for a defect made at station 2?arrow_forwardConsider the two stage process depicted below: Stage 1 Stage 2 The first stage of the process requires 6 minutes of work for a single employee to complete. There are 8 employees working at this process stage - each for a total of 5 hours per day. This stage includes an inspection where 14% of WIP is rejected and exits the system after completing Stage 1. The remaining WIP continues to Stage 2 of the process. At this stage, 7 employees work - each for a total of 4 hours per day. WIP is processed at Stage 2 in 10 minutes by a single employee. What is the daily process capacity? Round your answer to the nearest first decimal place. Your Answer: Answerarrow_forward
- A fleet repair center resets its computerized diagnostic system after every 15 trucks to help ensure there are limited major downtimes from system failure. The reset takes 22 minutes on average with a CV of 0.3. Each trucks diagnosis takes 28 minutes on average with a CV of 1.75 not considering the resets. 1. What is the effective process time and its CV? 2. If the reset system is not used, failures will occur after 57 hours on average with an average repair time of 3 hours. The CV of repair time is 0.9. What is the effective process time and its CV? Is the maintenance system beneficial if it prevents breakdowns? Just consider effective processing time parameters. 3. The maintenance program costs $10,000 annually. The average profit per car from the diagnostic service is $75. Assume the service center operates 250 days per year, 10 hours per day. Is the maintenance program economically beneficial? What assumptions are needed?arrow_forwardWhy do you need to develop the mathematical model of a process you want to control?arrow_forwardWellplace Insurance Company processes insurance policy applications in batches of 100. One day, they had eleven batches to process and, after inspection, it was found that four batches had nonconforming policies. One batch had seven nonconformances, another had two, another had one, and another had five nonconformance. a. What was the proportion nonconforming for each batch? Round your answers to two decimal places. The proportion nonconforming for the first batch: The proportion nonconforming for the second batch: The proportion nonconforming for the third batch: The proportion nonconforming for the fourth batch: b. What was the nonconformance per unit (NPU) in total for the eleven batches? Round your answer to three decimal places. Total nonconformances per unit for all batches:arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.