Concept explainers
Explanation of Solution
Formulation of Linear
Let consider,
- “xi” be the number of production of air conditioners during month “i”:
- “yi” be the number of production of air conditioners during month “i”:
- “Ii” be the inventory at the end of month “i”:
The objective is to minimize the cost of meeting the three months’ demand.
Therefore, the objective function is,
Minimize
Constraint 1:
During month 1, 300 air conditioners are in demand and at the beginning of month 1 Airco has 200 air conditioner.
Constraint 2:
During month 2, 400 air conditioners are in demand.
Constraint 3:
During month 3, 500 air conditioners are in demand
Trending nowThis is a popular solution!
Chapter 3 Solutions
Operations Research : Applications and Algorithms
- ACE Hardware wants to develop a daily schedule for its employees in one of its stores in Omaha. Currently,this store has five employees and the store is opened from 12pm to 9pm. The store must always have at leasttwo people on hand. Each employee must work at least four hours and no more than eight hours per day.Employee #1 goes to school and cannot start before 4pm while all other employees can work at any time.Furthermore, employee #1 earns $10 per hour while all other employees earn $12 per hour. Because all fiveemployees live so close to the store, you must assume that they do not need to work consecutive hours.a) Formulate an optimization model for this problem.b) Solve the optimization model using either the Microsoft Excel Solver or the IBM ILOG CPLEXOptimization Studio.arrow_forwardThe JAV Company manufactures two types of lamps; Special lamp and regular lamp. Each special lamp requires 4 pounds of brass and each regular lamp requires 8 pounds of brass. During each production period, the company's brass supply limited to 640 pounds. Each special lamp requires 6 hours of milling time in the machines and each regular lamp requires 2 hours of milling time in the machine, The company's machine are available only for 360 hours in each production period. Each special lamp requires 5 light bulbs that must be imported from Hongkong. The importation of these bulb is limited to 200 units. The contribution to profit of each special lamp and regular lamp are P400 and P360 respectively. How many units of the special lamp and regular lamp should be produced per production period in order to maximize the profit?arrow_forwardMississippi Agricultural Co. owns a wheat warehouse with a capacity of 20,000 bushels. At the beginning of month 1, they have 6,000 bushels of wheat. Each month, wheat can be bought and sold at the price per 1000 bushels given in the table below. The sequence of events during each month is as follows: i) The initial stock of wheat is counted. ii) Any amount of wheat up to your initial stock can be sold at the current month's selling price. iii) The company can buy (at the current month's buying price) as much wheat as they want, subject to the warehouse size limitation. Do the following: 1- Formulate an LP that can be used to determine how to maximize the profit earned over the next 10 months and. 2- Solve your LP using AMPL solver python. Month 1 2 3 4 5 6 7 8 9 10 Selling Price Purchase Price 3 6 7 1 4 5 5 1 3 2 ∞∞№343 8 8 2 325 10 2 5arrow_forward
- Wilson Creek Farm has 200 acres of land available for planting. The owner is considering planting three crops: corn, soybeans, and wheat. The production yield, water requirements, and labor requirements for a salable crop are given here. The owner expects to have only 35,000 gallons of water available per week to use for the crops, and during the growing season he will only have 8000 person-hours of labor available. The expected profit per bushel of each crop is $1.00 for corn, $1.60 for soybeans, and $3.00 for wheat. The owner can use any mix of crops (i.e., he can plant the same crop on all 200 acres or he can plant all three crops in different proportions). d. Solve the problem using Excel Solver Tool. Add supporting pictures from the software for each step. Discuss your output in line with the given reports from Excel. Bushels/ Acre Water Required Produced (gal/acre/week) Crop 300 Corn Soybeans 200 Wheat 80 200 150 125 Person-Hours Labor Required/Acre 35 40 30arrow_forwardComet Enterprises assembles hand-held vacuum cleaners and desk fans in Memphis, TN. Each vacuum cleaner requires one electric motor, 4 hours of labor, and 20 ounces of stainless steel, and brings $12 profit. Each fan requires one electric motor, 1 hour of labor, and 10 ounces of stainless steel, and brings $4 profit. There are 100 electric motors, 160 hours of labor, and 1100 ounces of stainless steel available for this week's production. (a) Formulate a linear program to determine Comet's production plan for this week to maximize total profit, that is, how many hand-held vacuum cleaners, and how many desk fans should the company produce.arrow_forwardA certain grade of steel is graded according to the following condition: 1. Hardness must be greater than 40 2. Carbon contents must be less than 0.8 3. Tensile strength must be greater than 5000 The grades are as follows: § Grade is 10 if all the three conditions are met. § Grade is 9 if conditions 1 and 2 are met. § Grade is 8 if conditions 2 and 3 are met. § Grade is 7 if conditions 1 and 3 are met. § Grade is 6 if only one condition is met. § Grade is 5 if none of the conditions are met. Write a C++ program which will require user to give values of hardness, carbon content and tensile strength of the steel under consideration then determine the grade of steel and outputs the grade of the steelarrow_forward
- 3. National Disc Corp. produces the discs used in producing Xbox and PlayStation discs. Their local plant runs 24 hours a day, 7 days a week. In a given day, there are requirements for the total number of employees that must be at the plant. These are given below. Employees Needed Hours 12am - 4am 4am - 8am 8am-12pm 12pm - 4pm 4pm - 8pm 8pm-12am 8 10 16 21 18 12 Employees can either work 8-hour or 12-hour shifts, starting at the times stated above (12- hour shifts can start only at 12 am/pm or 8 am/pm). Those working 8-hour shifts cost the company $40 per hour in benefits, and those working 12-hour shifts cost the company $60 per hour. Develop a linear program that can be used to determine how National should staff the local plant so as to minimize labor costs (you do not need to solve the model). Be sure to clearly identify your variables.arrow_forwardamyo Manufacturing produces four parts that require the use of a lathe and a drillpress. The two machines operate 10 hours a day. The following table provides the time inminutes required by each part:It is desired to balance the two machines by limiting thedifference between their total operation times to at most 30 minutes. The market demand for each part is at least 10 units. Additionally, the number of units of part 1 may not exceed that of part 2. b)Solve the following problems by B&B:Maximize ?=18?1+14?2+8?3+4?4subject to15?1+12?2+7?3+4?4+?5≤37?1,?2,?3,?4,?5=(0,1) Part 6arrow_forwardHarry and Melissa Jacobson produce handcrafted furniture in a workshop on their farm. They have obtained a load of 600 board feet of birch froma neighbor and are planning to produce round kitchen tables and ladder-back chairs during the next 3 months. Each table will require 30 hours oflabor, each chair will require 18 hours, and between them they have a total of 480 hours of labor available. A table requires 40 board feet of woodto make, and a chair requires 15 board feet. A table earns the couple $575 in profit, and a chair earns $120 in profit. Most people who buy a tablealso want four chairs to go with it, so for every table that is produced, at least four chairs must also be made, although additional chairs can also besold separately. Formulate and solve an integer programming model to determine the number of tables and chairs the Jacobsons should make tomaximize profit. What is the maximized profit?arrow_forward
- The Callaghan family owns 410 acres of farmland in Co. Cork on which they grow wheat and oats. Each acre of wheat costs €105 to plant, cultivate, and harvest; each acre of oats costs €210. The Bradleys have a budget of €52,500 for next year. The government limits the number of acres of oats that can be planted to 100. The profit from each acre of wheat is €300; the profit from each acre of oats is €520. The Callaghans want to know how many acres of each crop to plant in order to maximize their profit. ii. Formulate a linear programming model for this problem.arrow_forwardb. Employees of a certain firm are paid on hourly basis at the end of each week. If an employee works up to 40hrs the employee is paid 6 cedis and 7 cedis per hour for a male and female respectively. If an employee works for more than 40 hours then the employee is also paid 1.5 the corresponding regular rate for hours worked in excess of 40. All employees are to pay 15 % of their gross as INCOME TAX and 5% towards the NHIS. If an employee has more than 3 children then he or she pays 2 cedis per child in excess of three towards GETFUND. Write an algorithm and draw a flow chart for a software solution that can solve for the above problem. |arrow_forwardA company uses four special tank trucks to deliver four different gasoline products to customers. Eachtank has five compartments with capacities: 500, 750, 1200, 1500, and 1750 gallons. The daily demands forthe four products are 10000, 15000, 12000, and 8000 gallons. Any quantities that cannot be delivered by thecompany’s four trucks must be subcontracted at the additional costs of 5, 12, 8, and 10 cents per gallon forproducts 1, 2, 3, and 4, respectively. The goal is to develop the optimal daily loading schedule for the fourtrucks that will minimize the additional cost of subcontracting. Formulate this problem as an integer linearprogram, and solve it (not by hand).arrow_forward
- Operations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks Cole