Concept explainers
Variance:
Variance is the difference between the actual cost and budgeted cost for particular level of activity. It is computed by deducting the budgeted cost from the actual cost of the production.
Direct Material Cost Variance:
The difference between the actual cost incurred on the direct material and the budgeted cost expected to be incurred is called the direct material cost variance. It can either calculated by deducting the budgeted cost from the actual cost or adding the direct material price variance and direct material quantity variance.
Direct Labor Cost Variance:
The variance between the actual labor cost incurred and the budgeted labor cost is termed as direct labor cost variance. It can be computed by deducting the budgeted labor cost from the actual cost. On the contrary, it can also be ascertained by adding the direct labor rate variance and direct labor efficiency variance.
Controllable Variance:
The overall variance which comprises of variable
Volume Variance:
The variance which arises due to difference in the budgeted level of activity and the actual level is called volume variance. The sole reason for this kind of variance is the variation in the level of activity.
1. Computation of direct materials cost variance with its price and quantity variances.
2. Computation of direct labor cost variance with its rate and efficiency variances.
3. Computation of overhead controllable and volume variances.

Answer to Problem 4APSA
Solution:
1. Trico Company has unfavorable variance in direct material cost variance of $141,500 with unfavorable price variance of $161,500 and favorable quantity variance of $20,000.
2. Direct labor cost variance is $136,250 (F) with both favorable variance in rate of $66,250 and efficiency of $70,000.
3. The company has favorable variance of $310,000 in controllable variance and favorable variance of $300,000 in volume variance.
Explanation of Solution
1. Computation of direct materials cost variance with its price and quantity variances.
2. Computation of direct labor cost variance with its rate and efficiency variances.
3. Computation of overhead controllable and volume variances.
1. The direct material price variance is $161,500 Unfavorable.
2. The direct material quantity variance is $20,000 Favorable.
3. The direct material cost variance is $141,500 Unfavorable.
Want to see more full solutions like this?
Chapter 23 Solutions
Fundamental Accounting Principles -Hardcover
- Robinson Manufacturing discovered the following information in its accounting records: $519,800 in direct materials used, $223,500 in direct labor, and $775,115 in manufacturing overhead. The Work in Process Inventory account had an opening balance of $72,400 and a closing balance of $87,600. Calculate the company’s Cost of Goods Manufactured.arrow_forwardSanjay would like to organize HOS (a business entity) as either an S corporation or as a corporation (taxed as a C corporation) generating a 16 percent annual before-tax return on a $350,000 investment. Sanjay’s marginal tax rate is 24 percent and the corporate tax rate is 21 percent. Sanjay’s marginal tax rate on individual capital gains and dividends is 15 percent. HOS will pay out its after-tax earnings every year to either its members or its shareholders. If HOS is taxed as an S corporation, the business income allocation would qualify for the deduction for qualified business income (assume no limitations on the deduction). Assume Sanjay does not owe any additional Medicare tax or net investment income tax. Required 1. For each scenario, C corporation and S corporation, calculate the total tax (entity level and owner level). 2. For each scenario, C corporation and S corporation, calculate the effective tax rate. C Corporation S Corporation 1. Total tax…arrow_forwardI need correct solution of this general accounting questionarrow_forward
- Hii expert please given correct answer general accountingarrow_forwardMarkowis Corp has collected the following data concerning its maintenance costs for the pest 6 months units produced Total cost July 18,015 36,036 august 37,032 40,048 September 36,036 55,055 October 22,022 38,038 November 40,040 74,575 December 38,038 62,062 Compute the variable coot per unit using the high-low method. (Round variable cost per mile to 2 decimal places e.g. 1.25) Compute the fixed cost elements using the high-low method.arrow_forwardUse the following data to determine the total dollar amount of assets to be classified as current assets. Marigold Corp. Balance Sheet December 31, 2025 Cash and cash equivalents Accounts receivable Inventory $67000 Accounts payable $126000 86500 Salaries and wages payable 11100 149000 Bonds payable 161500 Prepaid insurance 83000 Total liabilities 298600 Stock investments (long-term) 193000 Land 199500 Buildings $226000 Common stock 309400 Less: Accumulated depreciation (53500) 172500 Retained earnings 475500 Trademarks 133000 Total stockholders' equity 784900 Total assets $1083500 Total liabilities and stockholders' equity $1083500 ○ $269100 $385500 ○ $236500 ○ $578500arrow_forward
- Should the machine be replaced?arrow_forwardUsing the following balance sheet and income statement data, what is the total amount of working capital? Current assets $39700 Net income $52100 Current liabilities 19800 Stockholders' equity 96700 Average assets 198400 Total liabilities 52100 Total assets 148800 Average common shares outstanding was 18600. ○ $9900 ○ $39700 ○ $19900 ○ $12400arrow_forwardSuppose that Old Navy has assets of $4265000, common stock of $1018000, and retained earnings of $659000. What are the creditors' claims on their assets? ○ $2588000 ○ $3906000 ○ $1677000 ○ $4624000arrow_forward
- Brody Corp. uses a process costing system. Beginning inventory for January consisted of 1,400 units that were 46% completed. 10,300 units were started during January. On January 31, the inventory consisted of 550 units that were 77% completed. How many units were completed during the period?arrow_forwardCurrent Attempt in Progress Whispering Winds Corp. has five plants nationwide that cost $275 million. The current fair value of the plants is $460 million. The plants will be reported as assets at $735 million. O $460 million. $275 million. O $185 million.arrow_forwardBased on the following data, what is the amount of current assets? Accounts payable $62000 Accounts receivable 116000 Cash 66000 Intangible assets 116000 Inventory 142000 Long-term investments 161500 Long-term liabilities 199000 Short-term investments 85000 Notes payable 56500 Property, plant, and equipment 132000 Prepaid insurance 2500arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education