(a)
The time required for 5th installation.
Answer to Problem 63P
The time required to the 5th installation is 58.7175hrs.
Explanation of Solution
Given information:
- Time required to install 1st unit = 75 hours
- Learning curve = 90%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition
For estimating the time for repetitive tasks is given by following formula:
Where:
TN− time required for Nth production
Tinitial − time required for 1st production
N − Number of completed units
b − Learning curve exponent
The learning curve exponent is calculated as
Where: LC − Learning Curve.
Calculation:
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
- Calculating Time in the 5th installation
Conclusion:
The time required to the 5th installation is 58.7175hrs.
(b)
The time required for 10th installation.
Answer to Problem 63P
The time required to 10th installation is 52.85hrs.
Explanation of Solution
Given information:
- Time required to install 1st unit = 75 hours
- Learning curve = 90%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition
For estimating the time for repetitive tasks is given by following formula:
where:
TN− time required for Nth production
Tinitial − time required for 1st production
N − number of completed units
b − learning curve exponent
The learning curve exponent is calculated as
where: LC − Learning Curve.
Calculation:
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
- Calculating Time in the 10th installation
Conclusion:
The time required to 10th installation is 52.85hrs.
(c)
The time required for 20th installation.
Answer to Problem 63P
The time required to the 20th installation is 46.815hrs.
Explanation of Solution
Given information:
- Time required to install 1st unit = 75 hours
- Learning curve = 90%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition
For estimating the time for repetitive tasks is given by following formula:
where:
TN− time required for Nth production
Tinitial − time required for 1st production
N − number of completed units
b − learning curve exponent
The learning curve exponent is calculated as
where: LC − Learning Curve.
Calculation:
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
Calculating Time in the 20th installation
Conclusion:
The time required to the 20th installation is 47.565hrs.
(d)
Research on AMCF and write down its similarities with the engineering code of ethics.
Explanation of Solution
The AMFC stands for Association of Management Consulting firms. The members who are a part of this association are expected to adhere to the policies of integrity, collaboration, professionalism, accounting, dedication and respect. While in terms of values and practices both the code of ethics more or less remains the same, and is enforceable on the membership. However, AMFC is mostly for the Management Consulting Firms and may not be sometimes useful from the perceptive of the engineering.
Want to see more full solutions like this?
Chapter 2 Solutions
ENGINEERING ECO ANALYSIS W/STUDY GUIDE
- I need expert handwritten solutionsarrow_forwardmachine A operated manually cost 2000naira has a life of 2 years, while an automatic machine B cost 5000naira but has a life of 4 years,operating cost for machine A is 4000naira per year while of machine B is 3000naira only, which should be purchased?consider 10% interest I need expert handwritten solutionsarrow_forwardDon't used Ai solutionarrow_forward
- not use ai pleasearrow_forwardUse the following table to work Problems 5 to 9. Minnie's Mineral Springs, a single-price monopoly, faces the market demand schedule: Price Quantity demanded (dollars per bottle) 10 8 (bottles per hour) 0 1 6 2 4 3 2 4 0 5 5. a. Calculate Minnie's total revenue schedule. b. Calculate its marginal revenue schedule. 6. a. Draw a graph of the market demand curve and Minnie's marginal revenue curve. b. Why is Minnie's marginal revenue less than the price? 7. a. At what price is Minnie's total revenue maxi- mized? b. Over what range of prices is the demand for water from Minnie's Mineral Springs elastic? 8. Why will Minnie not produce a quantity at which the market demand for water is inelastic?arrow_forwardDon't give AI generated solution otherwise I will give you downward Give correct answer with explanationarrow_forward
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education