(a)
The time required to build the 5th house.
Answer to Problem 61P
The time required to the 5th House is 2,833.65.
Explanation of Solution
Given information:
- Time required to produce 1st unit = 3500 manual labor hours
- Learning curve = 92%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition
For estimating the time for repetitive tasks is given by following formula:
Where:
TN− time required for Nth production
Tinitial − time required for 1st production
N − number of completed units
b − learning curve exponent
The learning curve exponent is calculated as
Where: LC − Learning Curve.
Calculation:
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
- Calculating Time in Manual labor hours for constructing the 5th house
Conclusion:
The time required to the 5th House is 2,833.65.
(b)
The time required to build the 10th house.
Answer to Problem 61P
The time required to build the 10th house is 2,653.
Explanation of Solution
Given information:
- Time required to produce 1st unit = 3500 manual labor hours
- Learning curve = 92%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition
For estimating the time for repetitive tasks is given by following formula:
Where:
TN− time required for Nth production
Tinitial − time required for 1st production
N − number of completed units
b − learning curve exponent
The learning curve exponent is calculated as
Where: LC − Learning Curve.
Calculation:
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
- Calculating Time in Person-hours for constructing the 10th house
Conclusion:
The time required to build the 10th house is 2,653.
(c)
The time required to build the 18th house.
Answer to Problem 61P
The time required to the construct the 18th house is 2472.05.
Explanation of Solution
Given information:
- Time required to produce 1st unit = 3500 manual labor hours
- Learning curve = 92%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition
For estimating the time for repetitive tasks is given by following formula:
Where:
TN− time required for Nth production
Tinitial − time required for 1st production
N − number of completed units
b − learning curve exponent
The learning curve exponent is calculated as
Where: LC − Learning Curve.
Calculation:
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
- Calculating Time in Person-hours for constructing the 18th house
Conclusion:
The time required to the construct the 18th house is 2472.05.
(d)
The time required to build the 18th house with 70% learning curve.
Answer to Problem 61P
The time required to the 18th House with 70% learning curve is 790.65.
Explanation of Solution
Given information:
- Time required to produce 1st unit = 3500 manual labor hours.
- Learning curve = 70%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition.
For estimating the time for repetitive tasks is given by following formula:
where:
TN− time required for Nth production.
Tinitial − time required for 1st production.
N − number of completed units.
b − learning curve exponent.
The learning curve exponent is calculated as
where: LC − Learning Curve.
Calculation:
- Learning Curve - 70%
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
- Calculating Time in Manual labor hours for constructing the 18th house
Conclusion:
The time required to the 18th House with 70% learning curve is 790.65.
(e)
The time required to build the 18th house with 75% learning curve.
Answer to Problem 61P
The time required to the 18th House with 75% learning curve is1054.55.
Explanation of Solution
Given information:
- Time required to produce 1st unit = 3500 manual labor hours
- Learning curve = 75%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition
For estimating the time for repetitive tasks is given by following formula:
where:
TN− time required for Nth production
Tinitial − time required for 1st production
N − number of completed units
b − learning curve exponent
The learning curve exponent is calculated as
where: LC − Learning Curve.
Calculation:
- Learning Curve - 75%
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
- Calculating Time in Manual labor hours for constructing the 18th house
Conclusion:
The time required to the 18th House with 75% learning curve is1054.55.
(f)
The time required to build the 18th house with 80% learning curve.
Answer to Problem 61P
The time required to the 18th House with 80% learning curve is 1380.05.
Explanation of Solution
Given information:
- Time required to produce 1st unit = 3500 manual labor hours
- Learning curve = 80%
- Learning Curve: The learning curve captures the relationship between the task performance and task repetition
For estimating the time for repetitive tasks is given by following formula:
where:
TN− time required for Nth production
Tinitial − time required for 1st production
N − number of completed units
b − learning curve exponent
The learning curve exponent is calculated as
where: LC − Learning Curve.
Calculation:
- Learning Curve - 80%
We can now calculate the value of b (using the formula 2)
Using the formula (2):
Using the formula (1):
- Calculating Time in Manual labor hours for constructing the 18th house
Conclusion:
The time required to the 18th House with 80% learning curve is 1380.05.
Want to see more full solutions like this?
Chapter 2 Solutions
ENGINEERING ECONOMIC ENHANCED EBOOK
- In economics, the cost of producing a good: Question 6 options: is the maximum value of other goods that could have been produced using the same resources. equals the out-of-pocket costs incurred in producing the good. is the value of inputs used up in production. is the value of other goods that could have been produced using the same resources.arrow_forwardPlease correct answer and don't used hand raiting and don't used Ai solutionarrow_forwardnot use ai pleasearrow_forward
- Gates Doubles Down on Malaria Eradication The End Malaria Council, convened by Bill Gates and Ray Chambers, seeks to mobilize resources to prevent and treat malaria. The current level of financing is too low to end malaria. Bruno Moonen, deputy director for malaria at the Gates Foundation, says that more resources, more leadership, and new technologies are needed to eradicate malaria in the current generation. Is Bruno Moonen talking about production efficiency or allocative efficiency or both? Bruno Moonen is talking about _______. A. production efficiency but not allocative efficiency B. production efficiency and allocative efficiency C. allocative efficiency but not production efficiency D. neither production efficiency nor allocative efficiencyarrow_forwardWhat challenges do medical facilities face when trying to become more culturally competent? What kinds of assumptions do providers sometimes make about people from other cultures? What factors may cause providers to relate to patients in a biased manner? What can healthcare organizations do to ensure cultural competence among their employees?arrow_forwardBrazil, Russia, India, China, and South Africa, also known as BRICS, are emerging countries poised to be dominant economic players in the 21st century. What are some of the political, legal and economic conditions that help or hinder economic expansion for these countries?arrow_forward
- Explain what is Microeconomics? Why is it important for all of us to understand what are the drivers in microeconomics?arrow_forwardThe production function for a product is given by Q =100KL.if the price of capital is 120 dollars per day and the price of labor 30 dollars per day what is the minimum cost of producing 1000 units of output ?arrow_forwardخصائص TVAarrow_forward
- please show complete solution, step by step, thanksarrow_forwardTo determine the benefits of extending hours of operation for a food truck business, the couple should calculate additional revenue, break-even analysis, market demand, and raise prices. They should analyze competitors' prices and customer sensitivity to price changes, determine price elasticity, and test the strategy by implementing a slight price increase and monitoring sales closely. If costs exceed revenues, the couple should analyze their financials, evaluate their business model, explore new revenue streams, and consider long-term viability. They should analyze their financial statements to identify high costs and areas for reduction, evaluate their business model based on market demand, and explore new revenue streams like catering, special events, or partnerships with local businesses. Long-term viability is a key consideration, as if the business still operates at a loss after making adjustments, it may be necessary to consider shutting down. Staying in business should be…arrow_forwardRespond to following post. You can charge higher prices if the parents think these are valuable by providing different services such as extended hours, healthy lunches, and smaller staff-to-child ratios. But pushing for prices much higher won’t make sense unless parents think the added value is worth the price hike. You should research your local parents to find out what they want. If you want your business to be profitable, then focus on your strengths, do great work and have a reputation. Promote your special products and keep your prices low. If you want to see if you’re making money, keep a log of all your profits and losses. You’re making money if you’re earning more than you’re losing. A break-even analysis can help you figure out how many customers you need to eat and start making money. Keep an eye on your budget so you don’t get off track.arrow_forward
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education